CPM Final Exam

0.0(0)
studied byStudied by 0 people
learnLearn
examPractice Test
spaced repetitionSpaced Repetition
heart puzzleMatch
flashcardsFlashcards
Card Sorting

1/29

encourage image

There's no tags or description

Looks like no tags are added yet.

Study Analytics
Name
Mastery
Learn
Test
Matching
Spaced

No study sessions yet.

30 Terms

1
New cards

The purpose of tracking work

1.) Ensure that the project is staying within schedule.

2.) Ensure that the work is being completed withing the budget constraints.

3.) Ensure that the project is meeting the quality criteria standards.

2
New cards

What work should you track?

1.) The completion of work packages as compared to the plan to check if you are on schedule.

2.) The scope of work being performed to prevent scope creep.

3.) The quality of work being performed against the requirements for the project.

4.) The costs and expenditures as compared to the plan to check your budget.

5.) The cohesiveness and cooperation of team members.

3
New cards

Progress measurement of design

1.) Units completed.

2.) Incremental milestones.

3.) Start/Finish percentages.

4.) Ratio

4
New cards

Units completed

Writing specifications.

%work= Number of specifications completed/Total number of specifications to be produced

5
New cards

Incremental milestones

Easily recognized milestones

- Production of drawings

- Procurement activities

6
New cards

Start/finish percentages

Activities that lacks definable intermediate milestones.

Effort and time required is difficult to estimate.

- Planning

- Designing

- Model building

7
New cards

Ratio

Have no particular end product.

- Project management

- Project control

%complete= Hours (cost) spent to date/Estimated hours (cost) at completion

8
New cards

Progress measurement of construction

1.) Units completed

2.) Incremental milestones

3.) Start/finish percentages

4.) Supervisor opinion

5.) Cost ratio

6.) Weighted units

9
New cards

Units completed

Repetitive tasks that require a uniform effort.

Work package level.

10
New cards

Incremental milestones

Task that include subtasks that must be handled in sequence.

11
New cards

Start/finish percentages

Tasks that do not have well-defined intermediate milestones.

12
New cards

Supervisor opinion

Subjective approach.

Minor tasks.

13
New cards

Cost ratio

Administrative tasks.

- Project management

- Quality assurance

- Control administration

- Project control

%Complete=Actual (cost) work-hours to date/ Forecast at completion

14
New cards

Weighted units

- Tasks that involve major efforts of work that occur over a long duration of time.

- A weight is assigned to each subtask to represent the estimated level of effort.

15
New cards

Earned-value system

Earned-value system is used to monitor the progress of work and compare accomplished work with planned work.

16
New cards

Earned value analysis

BCWS - Budgeted cost of work scheduled (Planned)

BCWP - Budgeted cost of work performed (Earned)

ACWP - Actual cost of work performed (Actual)

17
New cards

Variances

CV = BCWP - ACWP (Cost variance = Earned - Actual)

SV = BCWP - BCWS (Schedule variance = Earned - Planned)

18
New cards

Indices

CPI = BCWP/ACWP (Cost performance index = Earned/Planned)

SPI = BCWP/BCWS (Schedule performance index = Earned/Planned)

19
New cards

Forecasting

BAC = Original project estimate (Budget at completion)

ETC = (BAC-BCWP)/CPI (Estimate to complete)

EAC = ACWP + ETC (Estimate at completion)

20
New cards

Causes of Cost/Schedule variance

-Estimating errors

-Technical problems

-Design errors

-Test data problems

-Constructability

-Equipment problems

-Management problems

-Scope control (change orders)

-Personal skill level

-Resource availability

-Economic/inflation

-Delay material delivery

-Delay equipment delivery

-Acts of god (Weather, fire, flood, ... etc.)

-Accidents during construction

21
New cards

PERT

-Probabilistic vs. CPM which is Deterministic

-Useful when difficult to estimate activity durations; May be a range of durations.

-Uses statistics to determine probability of reaching an event earlier/later than expected.

-Uses three estimates of duration:

1.) Optimistic time

2.) Pessimistic time

3.) Most likely time

22
New cards

Central limit theorem

The theory that, as sample size increases, the distribution of sample means of size n, randomly selected, approaches a normal distribution.

23
New cards

Deviation

Accounts for various probabilities of uncertainty.

24
New cards

Major phases of projects

1.) Project conception

2.) Design

3.) Procurement

4.) Construction

5.) Project Close-Out

25
New cards

Smooth closeout essentials

Planning

-Start as soon as the project begins

-Requirements for closeout

1.) Warranties

2.) Documents

Organization

-Documentation organizing system in place

Communication

-What to expect

-Timeline

26
New cards

Poorly planned closeout

Prolonged closeout process.

Delays and headaches.

Wasting resources.

-For owners losing money/profit

-For contractors

1.) losing capacity to work something else

2.) Maybe responsible for liquidated damages

27
New cards

System testing and startup

Heavy industrial plant

-Inspection performed throughout the project.

-system testing- identified by 30% into construction

-coordinated between owners rep., designers, construction contractors, equipment manufacturers.

-Develop an agreement on the tested system and type of tests

-Start-up plan - Completed by 70% into construction.

- specify the "need date" by the owner's operating personnel.

-Substantial completion

- Owner and contractor agree a building is ready for intended use

- There is still remaining work

- Punchlist is generated

- A certificate of substantial completion may be issued.

- Certificate of substantial completion vs certificate of occupancy

- Certificate occupancy is issued by local authority

28
New cards

Steps to a building project closeout

- Completion of punch list items

- Generate from the substantial completion walkthrough

- GC assigned them to subcontractors

- Owners approval is needed when items are addressed

- Submission of closeout documents

- Guarantees and warranties

- Certificates of completion

- O&M manuals

- Spare parts, special tools

- As-Builts

- Final inspection

- A step to obtain a certificate of occupancy

- Check issues from previous inspections being addressed

- Check compliance with local building codes

- done by a licensed inspector from local building authority.

- Owner startup program

- develop an owner startup schedule and assign responsibilities for oversight.

- Test and accept all major project components

- Train O&M personnel

- Accept and log all contractor furnished documents

- Final payments and release of retainage

- Retainage: Withhold 5-10% of contract value until the work is done

- Retainage released at issuance of certificate of substantial completion or occupancy.

-Settle outstanding bill, change orders, etc.

- Acquisition of certificate of occupancy

29
New cards

Contractor closeout

- Decommission field office.

- Inventory equipment and supplies

- Change field office

- Terminate phone, radio and pager accounts

- Terminate rentals and leases

- Demobilize office and take off site

- Reassign field personnel

30
New cards

Post-Project review

- Review the projects objectives and scope

- Assess the projects performance against key metrics (budget, schedule, quality, safety)

- Document lessons learned

- Identify areas for improvement.