1/89
Looks like no tags are added yet.
Name | Mastery | Learn | Test | Matching | Spaced | Call with Kai | Chat |
|---|
No analytics yet
Send a link to your students to track their progress
The ______________ is based on the assumptions that project activity times can be estimated accurately and that they do not vary.
critical path method
The _____________ of activities in a project is the sequence of activities that form the longest chain in terms of their time to complete.
critical path
t/f: if any one of the activities in the critical path is delayed, then the entire project is delayed.
True
The ___________________ of an activity is the activities that need to be completed immediately before another activity.
immediate predecessor
____________ in an activity refers to the leeway in when an activity can start and finish.
Slack time
The difference between the late start time and the early start time is the ____________.
slack time.
Do you start from the beginning or end of the network when determining late start times?
The end
An _______________ lists all activities by their earliest start time.
early start schedule
Activities not on the critical path will have ______________ between the completion of each activity and the start of the next activity.
slack time
The _______________ lists the activities to start as late as possible without delaying the completion date of the project.
late start schedule
____________________ are extensions of the basic critical path method in an attempt to develop a minimum-cost schedule for an entire project and to control expenditures during the project.
Time-cost models
_____________ in a minimum-cost schedule refers to the compression or shortening of the time to complete the project.
Crashing
The costs associated with expediting activities are termed ___________________ and add to the project direct costs.
activity direct costs
The costs associated with sustaining the project are termed ________________, such as overhead, facilities, and resource opportunity costs.
project indirect costs
What are the four categories of projects?
Product change, process change, research and development, and alliances and partnerships
A ____________ project is where the team works full-time on a project.
pure
A ______________ project is where team members stay in their functional groups and work on many different projects
functional
A ____________ project blends the pure project and functional project structures
matrix
Crashing creates a shorter project that costs ____________.
more
T/F: The manager must weigh the added cost of providing more rapid service (more traffic lanes, additional landing strips, more checkout stands) against the inherent cost of waiting.
True
T/F: Frequently, the cost trade-off decision is straightforward on the phone for technical help.
True
Segmenting the customers, training your servers to be friendly, informing your customers of what to expect, diverting the customers' attention, and encouraging customers to come during slack periods are all methods of ________________ in the banking industry.
managing queues
The ______________ consists of three major components: (1) the source population and the way customers arrive, (2) the servicing system, and (3) the condition of the customers exiting the system.
queuing system
______________ at the service system may be drawn from finite or infinite populations.
Arrivals
A ____________ population refers to the limited-size customer pool that will use the service, and at times, form a line.
finite
An _____________ population is large enough in relation to the service system that the population size is not affected by subtractions or additions to the population.
infinite
An ____________ rate is the number of units per period.
arrival
A ____________ arrival distribution is periodic, with the same time between each successive arrival.
constant
Factors to consider with ______________ include line length, number of lines, and queue discipline.
waiting lines
_____________ is the capacity of the service in units per time period.
Service rate
When the arrival process is random during some time period t, which distribution should be used?
Poisson
What factors impact flow time?
critical path, variability, WIP limit, batch size, and setup times
______________ can enter a system through many ways, primarily through (1) the interarrival time of successive jobs to the system, (2) the service time of processing steps within the system
Does slowness accumulate in an interdependent system with variability?
yes
Does fastness accumulate in an interdependant system with variability?
no
Does reducing variability reduce system flow times?
yes
Will you always improve flow time when you add capacity to a bottleneck?
No
To ensure you are reducing flow time, you should focus on the ___________ of a process flow and variability in the system.
critical path
CV=
standard deviation/mean
A CV less than 1 is _____________ reliable processing due to things like reservation systems or standard operating procedures.
more
A CV more than 1 is __________ reliable behavior such as "clumpy" arrivals or unpredictable processing times.
less
Does a CV of 2 have more or less variation than a
Is a CV=2 more or less reliable than CV=1?
Less (because more variation)
What is it called when CV=1?
Markovian
What is it called when CV=2
general
What is it called when CV=0.5?
General
What is it called when CV=0?
deterministic
Does a CV=0 have any variation?
No
When managing a line, a manager must consider the trade-off between___________________________.
the cost of providing more rapid service and the cost of waiting
The queuing system consists essentially of three major components. What are they? Check all that apply.
1.) The condition of the customers on exit
2.) The servicing system
3.) The source population and how it arrives
When the arrival process is random during some time period T, what distribution should be used?
Poisson
When using the exponential distribution as an approximation of the service times, we will refer to μ as what?
Average number of units that can be served per time period
Early finish =
early start + duration
Does crashing create a shorter or longer project?
shorter
Does crashing increase or decrease the costs of a project?
increases
What type of arrivals occur when customers arrive with exactly the same time between successive arrivals?
constant
When customers arrive at a service facility in a purely random fashion, it is expected that it follows which distribution?
exponential
Which Greek symbol is used to represent the average service time in an infinite queuing model?
1/μ
________________ refers to the compression or shortening of the time to complete the project.
crashing
Which Greek symbol is used to represent the service rate in an infinite queuing model?
μ
A constant service time is generally limited to _______________ operations.
machine-controlled
Slack time =
late start - early finish
Which Greek symbol is used to represent the average time between arrivals in an infinite queuing model?
1/λ
Which of the following terms describes the number of customers that can be handled during a given time period?
service rate
Is the distraction technique selected a major component of the queuing system?
no
Can a project have multiple critical paths?
yes
How many elements must a population have before it can be defined as infinite?
it depends
Any activity on the critical path will have a slack time of __________.
0
Do activities not on the critical path have slack time?
Yes
__________________ is the practice of producing or processing multiple units of an item together as a group, rather than producing one at a time.
Batching (lot sizing)
Batching refers to the decision of ______________ to produce (or order) at one time.
how many units
What is the first stage of the little field game?
Board stuffing
Jobs can get processed __________ with smaller lot sizes.
faster
______________ is the time required to prepare a machine for the process or production of the next job.
Setup time
Total processing time =
setup time + (pure processing time * # items in a batch)
When pooling several servers (processors), while keeping everything else (e.g., arrival rate, processing times, variability in arrivals and service times) the same, what happens to the average utilization?
nothing ( the average utilization stays the same)
Does increasing capacity at the bottleneck change throughput?
Yes, it increases throughput
Does increasing capacity at the bottleneck change flowtime?
Yes, it decreases flowtime (less waiting upstream since the bottleneck clears faster)
Does increasing capacity at the bottleneck impact utilization?
Yes, it decreases utilization (since the bottleneck has more capacity relative to demand)
Utilization=
Arrival Rate/Service Rate
Does increasing demand (arrival rate/workload) impact flow time?
Yes, it increases flow time (more WIP builds up before the bottleneck)
Does increasing demand (arrival rate/workload) impact capacity?
No, capacity remains unchanged (capacity is a design limit; it is not impacted by demand)
Does increasing demand (arrival rate/workload) impact utilization?
Yes, increases utilization at the bottleneck (utilization approaches 100%)
Does adding a parallel server at the bottleneck impact throughput?
Yes, it increases throughput
Does adding a parallel server at the bottleneck impact flowtime?
Yes, it decreases flowtime (fewer customers waiting)
Does adding a parallel server at the bottleneck impact capacity?
Yes, it increases capacity (and a new bottleneck may emerge elsewhere in the system)
Can changes at the non-bottleneck activities impact overall system utilization?
No
If demand>capacity, then utilization=
100%
If demand
demand/capacity
Flowtime=
inventory (WIP)/throughput