Mother Load

0.0(0)
Studied by 0 people
call kaiCall Kai
Locked
learnLearn
examPractice Test
spaced repetitionSpaced Repetition
heart puzzleMatch
flashcardsFlashcards
GameKnowt Play
full-widthPodcast
1
Card Sorting

1/491

flashcard set

Earn XP

Description and Tags

Merged set for C215

Last updated 4:31 AM on 8/5/26
Name
Mastery
Learn
Test
Matching
Spaced
Call with Kai
Chat

No analytics yet

Send a link to your students to track their progress

492 Terms

1
New cards

Raw materials

Purchased items or extracted materials to be transformed into components or products.

2
New cards

Components

Parts or subassemblies used in a final product.

3
New cards

Work-in-process (WIP)

Items that are currently in process throughout the manufacturing plant.

4
New cards

Finished goods

Completed products that are sold to customers.

5
New cards

Distribution inventory

Finished goods that are currently in the distribution system.

6
New cards

Maintenance, repairs, & operating (MRO) supplies

Includes maintenance supplies, spare parts, lubricants, cleaning agents, and daily operating supplies needed to facilitate day-to-day operations.

7
New cards

Anticipation inventory

Items built in anticipation of future demand, allowing a company to maintain a level production strategy.

8
New cards

Fluctuation inventory

Inventory that protects against unexpected demand variations and assures customer service levels.

9
New cards

Lot-size inventory

Inventory that results from the actual quantity purchased, allowing for lower unit costs.

10
New cards

Transportation inventory

Items currently in movement between locations, such as from the manufacturer to distribution facilities.

11
New cards

Speculative inventory

Extra inventory built up or purchased to protect against future events and allow for a continuous supply.

12
New cards

Inventory turnover

A measurement of inventory investment calculated as the annual cost of goods sold divided by the average inventory in dollars.

13
New cards

Weeks of supply

A measurement of inventory investment calculated as: Average inventory on handAverage weekly cost of goods sold\frac{\text{Average inventory on hand}}{\text{Average weekly cost of goods sold}}

14
New cards

Days of supply

A measurement of inventory investment calculated as: Average inventory on handAverage daily usage\frac{\text{Average inventory on hand}}{\text{Average daily usage}}

15
New cards

Item cost

The price paid per item plus any other direct costs associated with getting the item to the plant.

16
New cards

Holding costs

Costs including capital, storage, and risk costs associated with keeping inventory.

17
New cards

Ordering costs

A fixed, constant dollar amount incurred for each order placed.

18
New cards

Shortage costs

Costs associated with the loss of customer goodwill, back-order handling, and lost sales.

19
New cards

ABC inventory classification

A method for determining the level of control and frequency of review of inventory items based on a Pareto analysis of annual dollar volume.

20
New cards

A Items

Inventory items that typically represent 20%20\% of the items but account for 80%80\% of the inventory value.

21
New cards

B Items

Inventory items that typically represent an additional 30%30\% of items and account for 15%15\% of the inventory value.

22
New cards

C Items

Inventory items that typically represent the remaining 50%50\% of items and account for only 5%5\% of the inventory value.

23
New cards

Continuous review system

An inventory system that updates inventory balances after each inventory transaction.

24
New cards

Periodic review system

An inventory system that requires regular periodic reviews of the on-hand quantity to determine the size of the replenishment order.

25
New cards

Two-bin system

A system where one bin with enough stock to satisfy demand during replenishment time is kept in the storeroom while the other is on the manufacturing floor.

26
New cards

Lead time

The time elapsed from order placement to order receipt.

27
New cards

Periodic counting

A method where physical inventory is taken periodically, usually annually, involving counting, verifying, and reconciling.

28
New cards

Cycle counting

A method of daily counting of pre-specified items to allow for timely detection and correction of inaccurate records.

29
New cards

Stock-keeping unit (SKU)

An inventory item at a particular geographic location.

30
New cards

Lot-for-lot

An ordering approach where the amount ordered is exactly what is needed.

31
New cards

Fixed-order quantity

An ordering approach where a predetermined amount is ordered each time an order is placed.

32
New cards

Min-max system

An ordering approach where an order is placed to reach a predetermined maximum level when on-hand inventory falls below a predetermined minimum.

33
New cards

Economic Order Quantity (EOQ)

An optimizing method used for determining order quantity and reorder points based on known and constant demand and lead time.

34
New cards

Economic Production Quantity (EPQ)

A model used for determining order quantities where inventory arrives in increments rather than a single shipment.

35
New cards

Quantity discount model

A modification of the EOQ process used to consider cases where the unit price depends on the quantity ordered.

36
New cards

Single-period inventory model

A model designed for products sold at regular prices for only one period, where demand is highly variable and salvage value is less than original cost.

37
New cards

Safety stock (SS)

Inventory added to the reorder point calculation to protect against uncertain demand or lead time, calculated as: SS=zσdLSS = z\sigma_{dL}

38
New cards

Order-cycle service level

The probability that demand during lead time will not exceed on-hand inventory.

39
New cards

Targeted inventory level (TI)

The level to which inventory is replenished in a periodic review system, calculated as: TI=d(RP+L)+SSTI = d(RP + L) + SS

40
New cards

Project

Any unique endeavor with specific objectives, multiple activities, defined precedent relationships, and a specific time period for completion.

41
New cards

Concept Phase

The first phase of the project life cycle where the need for the project is identified.

42
New cards

Feasibility analysis or study

A phase in the project life-cycle used to evaluate costs, benefits, and risks associated with a project.

43
New cards

Planning Phase

The phase of a project life cycle where it is decided who does what, how long it should take, and what resources are needed.

44
New cards

Execution Phase

The phase of the project life cycle where the actual work of the project is performed.

45
New cards

Termination Phase

The final phase of the project life cycle where the project is ended.

46
New cards

Program evaluation and review technique (PERT)

A network planning technique developed for the Polaris missile project used to determine a project’s planned completion date and identify the critical path using probabilistic time estimates.

47
New cards

Critical path method (CPM)

A network planning technique developed for the chemical industry that uses deterministic times to determine the completion date and critical path.

48
New cards

Activity-on-node

A network diagramming notation that places activities in nodes and uses arrows to signify precedence relationships.

49
New cards

Critical path

The longest sequential path through the network diagram.

50
New cards

Probabilistic Time Estimates

A process that uses optimistic, most likely, and pessimistic time estimates, typically used when there is uncertainty about activity duration.

51
New cards

Deterministic Time Estimates

Relies on the assumption that activity duration is known with certainty, used when reliable estimates from similar past activities are available.

52
New cards

Slack

A measure of how long activities can be delayed without delaying the project; calculated as the activity’s late finish minus its early finish (LFEFLF - EF) or late start minus its early start (LSESLS - ES).

53
New cards

Earliest start (ES)

The earliest possible time an activity can begin, which is equal to the earliest finish of the immediately preceding activity.

54
New cards

Earliest finish (EF)

The earliest start (ESES) plus the total activity time.

55
New cards

Latest Start (LS)

The latest an activity can start without delaying the project completion.

56
New cards

Latest Finish (LF)

The latest an activity can be completed without delaying the project completion.

57
New cards

Beta probability distribution

A distribution used to represent likely outcomes for project activities, including definite endpoints and a weighted average.

58
New cards

Optimistic time estimate (o)

The shortest time period in which an activity can be completed.

59
New cards

Most likely time estimate (m)

The normal time that an activity is expected to take.

60
New cards

Pessimistic time estimate (p)

The longest time period in which an activity will be completed if issues arise.

61
New cards

Expected time (ET)

The weighted average of the three time estimates, calculated using the formula from the beta distribution.

62
New cards

Variance of activity

A calculation used to determine the uncertainty of activity duration, defined as: [(pessimisticoptimistic)/6]2[(\text{pessimistic} - \text{optimistic}) / 6]^2.

63
New cards

Crashing

The process of reducing a project's completion time by shortening the duration of activities on the critical path.

64
New cards

Crash cost

The cost per unit of time to shorten an activity, calculated as: (crash costnormal cost)/(normal timecrash time)(\text{crash cost} - \text{normal cost}) / (\text{normal time} - \text{crash time}).

65
New cards

Critical Chain Approach

A management approach based on the theory of constraints that focuses on the project due date and manages safety time using buffers.

66
New cards

Project buffer

Safety time placed specifically at the end of the critical path to protect the project's final due date.

67
New cards

Feeder buffers

Time buffers placed between bottlenecks and noncritical paths to protect the critical path from delays.

68
New cards

Work System Design

A component of operations strategy that provides structure for company productivity and includes job design, work measurements, and worker compensation.

69
New cards

Job Design

The specification of work activities for an individual or group, identifying the purpose, location, and required skills for a job.

70
New cards

Technical Feasibility

A job design factor ensuring the job is physically and mentally doable for the worker.

71
New cards

Economic Feasibility

A job design factor where the cost of performing the job is less than the value it adds.

72
New cards

Behavioral Feasibility

The degree to which a job is intrinsically satisfying to the employee.

73
New cards

Labor Specialization

The degree to which an employee’s scope of expertise is narrowed via high levels of specialization or widened through lower levels of specialization.

74
New cards

Job Enlargement

The horizontal expansion of a job through increasing the scope of work assigned to instill pride.

75
New cards

Job Enrichment

The vertical expansion of a job through increased worker responsibility, such as adding work planning or inspection to a routine task.

76
New cards

Job Rotation

The shifting of cross-trained workers to different tasks to broaden understanding and reduce fatigue.

77
New cards

Problem-solving Teams

Small groups trained in problem-solving techniques used to identify, analyze, and propose solutions to workplace problems.

78
New cards

Special-purpose Teams

Highly focused, short-term, and often cross-functional teams with a focused agenda.

79
New cards

Self-directed (SD) Teams

Teams where members work through consensus to plan and control work flow, with goals defined by the team.

80
New cards

Self-managed (SM) Teams

Teams where members work through consensus to plan and control work flow, with goals defined by others.

81
New cards

Alternative Workplace

An approach that brings work to the worker rather than the worker to the workplace, facilitated by technologies like video conferencing and e-networks.

82
New cards

OSHA

The act passed by Congress in 1970 to mandate specific safety conditions in the work environment.

83
New cards

Method Analysis

A process for evaluating and improving operations by charting steps, talking with employees, and revising existing operations for continuous improvement.

84
New cards

Work Measurement

The process of determining how long it should take a qualified worker, using appropriate tools and processes, to complete a specific job.

85
New cards

Standard Time

The length of time to complete a job, including allowances for personal fatigue and unavoidable delays, used for costing and scheduling.

86
New cards

Time Study

A procedure to determine standard time involving the observation of work elements to calculate the mean and standard deviation of task duration.

87
New cards

nn

The number of observations of an element needed for a time study.

88
New cards

zz

The number of normal standard deviations needed for the desired confidence level in a study.

89
New cards

Performance Rating Factor (PRF)

A subjective estimate of a worker's pace relative to a normal work pace.

90
New cards

Frequency of Occurrence (F)

How often an element must be done during each work cycle.

91
New cards

Normal Time (NT)

The computation of mean observed time (MOT) multiplied by the performance rating factor (PRF) and the frequency of occurrence (F): MOT×PRF×FMOT \times PRF \times F.

92
New cards

Allowance Factor (AF)

The amount of time added to normal time to account for personal time, fatigue, and unavoidable delays.

93
New cards

Standard Time Formula

Normal Time×AF\text{Normal Time} \times AF

94
New cards

Elemental Time Data

Standards established based on previously completed time studies stored in an organization’s database.

95
New cards

Predetermined Time Data (MTM)

Published databases of elemental time data, such as methods-time measurement, used for actions like reach, grasp, and move.

96
New cards

Work Sampling

A technique for estimating the proportion of time a worker or machine spends on a given activity through random observations.

97
New cards

Learning Curve Theory

The theory that the time required to complete a task decreases each additional time it is performed by the same employee.

98
New cards

Learning Curve Calculation

The formula T×LnT \times L^n where TT is the initial time, LL is the rate of learning, and nn is the number of times the task has doubled.

99
New cards

Time-based Compensation

A system where pay is based on the number of hours worked.

100
New cards

Output-based (Incentive) Systems

A system where pay is based on the number of units completed.