Network Diagram
A graphical representation of project activities and their dependencies.
2
New cards
Precedence Diagram Method (PDM)
A technique used to construct a project schedule network diagram.
3
New cards
Activity
On a network diagram, a task that consumes time and resources.
4
New cards
Dependency
A logical relationship between two project activities.
5
New cards
Lead
Time that allows an acceleration of a successor activity.
6
New cards
Lag
Time delay between the start or finish of one activity and another.
7
New cards
Critical Path
The longest sequence of activities that must be completed on time for the project to finish on schedule.
8
New cards
Float (Slack)
The amount of time an activity can be delayed without delaying the project.
9
New cards
Early Start (ES)
The earliest time an activity can begin without delay.
10
New cards
Late Finish (LF)
The latest time an activity can finish without delaying the project.