This set covers essential PMP formulas from Chapter 16 including Earned Value Management, PERT distributions, and communication channel calculations.
Name | Mastery | Learn | Test | Matching | Spaced | Call with Kai | Chat |
|---|
No analytics yet
Send a link to your students to track their progress
Budget at Completion (BAC)
The original budget of the project; has no special formula.
Planned Value (PV)
PV=Planned % Complete×BAC
Earned Value (EV)
EV=Actual % Complete×BAC
Actual Cost (AC)
The total amount of money already spent on the project.
Cost Variance (CV)
CV=EV−AC
Cost Performance Index (CPI)
CPI=ACEV; identified as one of the most popular formulas on the exam.
Schedule Variance (SV)
SV=EV−PV
Schedule Performance Index (SPI)
SPI=PVEV; identified as one of the most popular formulas on the exam.
Estimate at Completion (EAC)
EAC=CPIBAC
Estimate to Completion (ETC)
ETC=EAC−AC
Variance at Completion (VAC)
VAC=BAC−EAC
To-Complete Performance Index (TCPI)
TCPI=BAC−ACBAC−EV
PERT - Beta
6Optimistic+4×Realistic+Pessimistic
PERT - Standard Deviation
6Pessimistic−Optimistic
PERT - Triangular Distribution
3Optimistic+Realistic+Pessimistic
Communications Channels
2N(N−1)