PMP Exam

0.0(0)
Studied by 0 people
call kaiCall Kai
learnLearn
examPractice Test
spaced repetitionSpaced Repetition
heart puzzleMatch
flashcardsFlashcards
GameKnowt Play
Card Sorting

1/291

flashcard set

Earn XP

Description and Tags

studying for pmp exam

Last updated 3:07 AM on 6/28/26
Name
Mastery
Learn
Test
Matching
Spaced
Call with Kai

No analytics yet

Send a link to your students to track their progress

292 Terms

1
New cards

Ishikawa Diagram

• fishbone/cause and effect diagram

• used to identify cause of defect

<p>• fishbone/cause and effect diagram</p><p>• used to identify cause of defect</p>
2
New cards

Pareto Diagram

• histogram

• display frequency

• used for quality

<p>• histogram</p><p>• display frequency</p><p>• used for quality</p>
3
New cards

Scatter Diagram

shows degree + direction of trends

<p>shows degree + direction of trends</p>
4
New cards

Control Chart

• tells if a process is in control

• identifies rule of seven

<p>• tells if a process is in control</p><p>• identifies rule of seven</p>
5
New cards

Rule of Seven

must be 7 consecutive points above/below middle line for process to be out of control

6
New cards

Project

temporary endeavor that produces a unique product

7
New cards

Operation

things that never ends

8
New cards

Progressive Elaboration

as time is progressing things in a project become more elaborate

9
New cards

Project Management

• application of knowledge, skills, tools, and techniques to satisfy project requirements

• people management

10
New cards

Program Management

group of projects coordinated to obtain benefits not available managed individually

11
New cards

Program Manager

manages team of project managers

12
New cards

Project Management Office (PMO)

structure that standardizes processes and facilitates sharing of resources

13
New cards

Supportive PMO

supports PM, providing templates/lessons

14
New cards

Controlling PMO

determines framework and use of specific forms

15
New cards

Directive PMO

controls project, PM assigned and reports to PMO

16
New cards

Portfolio

collection of projects + programs managed as a group to achieve strategic objectives

17
New cards

Operation Management

deals with ongoing production (ex sales, IT, accounting)

18
New cards

Phase

collection of logically related project activities that culminates in the completion of deliverables

19
New cards

Life Cycle

representation of the phases that a project goes from start to finish

20
New cards

System

set of interacting and interdependent components that function as a unified whole

21
New cards

Authority

right to exercise power and control individuals

22
New cards

Leadership

motivate people toward common goal, inspire them to align individual efforts in favor of collect efforts

23
New cards

Leading KPI

predicts changes or trends

24
New cards

Lagging KPI

measure project deliverables, provide info after the fact

25
New cards

SMART

specific, meaningful, achievable, relevant, and timely

26
New cards

Enterprise Environmental Factors (EEF)

things that impact the project but are not part of the project itself

27
New cards

Organization Process Assets (OPA)

assets provided by business to help project

28
New cards

Project Management Plan

doc that defines how the project is executed, mc, and closed

29
New cards

PM Information System (PMIS)

automated system used to help PM optimize schedule + keep track of all docs and deliverables

30
New cards

Work Performance Data

raw data of status of work done

31
New cards

Work Performance Report

• overall status report

• work performance data compared against plan

32
New cards

Strong Matrix

full time PM and moderate to high control over resources

33
New cards

Weak/Functional Matrix

part time PM and resource availability controlled by the functional manager

34
New cards

Project-Oriented Structure

PM has high to complete control over resources

35
New cards

Hybrid Stucture

multiple structures of functional and project oriented PM

36
New cards

Project Charter

• doc formally authorize project

• outlines project objectives

• defines authority of PM

• includes business case, PM benefit plan, and agreements

37
New cards

Project Benefits Management Plan

describes main benefits the project will produce once completed and how to measure the benefits

38
New cards

Business Case

necessary info that determines whether or not project is worth investing

39
New cards

Assumption Log

list of things perceived to be true (assumptions) and things that might constrain the project

40
New cards

Stakeholder Grid

3D method to support mapping of stakeholder interest, power, and influence

<p>3D method to support mapping of stakeholder interest, power, and influence</p>
41
New cards

Salience Model

power, legitimacy, and urgency

<p>power, legitimacy, and urgency</p>
42
New cards

Stakeholder Register

contains contact info, role on project, communication requirements, expectation, affect, power influence level

43
New cards

Product Scope

features and functions that characterize a product/service

44
New cards

Project Scope

work needed to be accomplished to deliver a product with specified features and functions

45
New cards

Gold Plated

extra work not in scope

46
New cards

Scope Creep

unauthorized work added to scope

47
New cards

Scope Management Plan

how scope will be defined, developed, mc, and verified

48
New cards

Affinity Diagram

large ideas that are grouped together and sorted for further review and analysis

<p>large ideas that are grouped together and sorted for further review and analysis</p>
49
New cards

Context Diagrams

used to visually show how business process, other systems, and people interact

<p>used to visually show how business process, other systems, and people interact</p>
50
New cards

Requirement Traceability Matrix

once a requirement is created a table is created that will link requirement back to its source

<p>once a requirement is created a table is created that will link requirement back to its source</p>
51
New cards

Project Scope Statement

describes in detail project deliverables and work required to produce those deliverables

52
New cards

Work Breakdown Structure (WBS)

subdividing project deliverables and work into smaller more manageable components

<p>subdividing project deliverables and work into smaller more manageable components</p>
53
New cards

Scope Baseline

3 components:

• project scope statement

• WBS

• WBS dictionary

54
New cards

WBS Dictionary

document detailing contents of the WBS, expanding info

55
New cards

Work Packages

broken down into activities

56
New cards

Activities

process of identifying and documenting specific actions to be performed to product deliverables

57
New cards

Rolling Wave Planning

near term work packages able to be defined in much great detail

58
New cards

Milestone List

key dates

59
New cards

Precedence Diagramming Method (PDM)

• graphical representation of all work needed to be performed

• represents flow of project

• what work packages tie into another work package

<p>• graphical representation of all work needed to be performed</p><p>• represents flow of project</p><p>• what work packages tie into another work package</p>
60
New cards

Finish to Start

• most commonly used

• start of successors work package depends upon completion of its predecessor work package

61
New cards

Finish to Finish

completion of successor work package depends on completion of the predecessor work package

62
New cards

Start to Start

Start of successor work package depends upon start of its predecessor work package

63
New cards

Start to Finish

Completion of successor works package depends upon start of its predecessor work package

64
New cards

Mandatory Dependencies

• hard logic

• tangible limitation of packages that are tied together

• one work package must be completed before subsequent begin

• ex turn on computed before writing code

65
New cards

Discretionary Dependencies

• soft logic

• work packages tied together but don't have physical limitations

• work in unison or tandem

• ex cook dessert and dinner at the same time

66
New cards

External Dependencies

• work package relationship between project and non project activities

• non project activities outside project team control

• ex gas stations receive gas before can fill up gas tank

67
New cards

Internal Dependencies

project activities within control of the team

68
New cards

Lead

• amount of time successor activity can be advanced with respect to predecessor activity

• ex windows installed 3 wks before siding installed

69
New cards

Lag

• delay in successor work

• ex windows can't be scheduled to be installed until walls have been installed

70
New cards

Project Schedule Network Diagrams

system wide drawings show entire project work packages from start to finish

<p>system wide drawings show entire project work packages from start to finish</p>
71
New cards

Analogous/Top Down Estimating

• rely on historical info to predict estimates for current project

• used when there is limit info

• costs less in time and money but gives least accuracy

72
New cards

Bottom Up Estimating

• takes a very long time to complete but highly accurate

• breaks down work to lowest levels and then aggregate work back up to find overall duration

73
New cards

Parametric

technique that uses statistical relationship between historical data and other variables to calculate estimate for activity parameters

74
New cards

Three Point Estimate

• calculates expected duration using weight avg 3 estimated optimistic, pessimistic, and most likely

• (O + P + 4M)/6

75
New cards

Basis of Estimates

how estimates were developed and their range

76
New cards

PERT

• scheduling tool that uses weighted average formula to predict length of activities and the project

• (optimistic + (4 x realistic) + pessimistic/6

<p>• scheduling tool that uses weighted average formula to predict length of activities and the project</p><p>• (optimistic + (4 x realistic) + pessimistic/6</p>
77
New cards

Standard Deviation

(pessimistic - optimistic)/ 6

78
New cards

Triangle Distribution

(optimistic + realistic + pessimistic)/3

79
New cards

Critical Chain Method

method of planning and managing projects that puts more emphasis on the resources required to execute project tasks developed

80
New cards

Crashing Schedule

adding resources to a project activity

81
New cards

Fast Tracking

activities performed in parallel

82
New cards

Critical Path Method

• Used to identify longest sequence of dependent tasks required to complete a project

• Determines minimum total time needed to complete project and pinpoint tasks that can't be delayed without impact final project

83
New cards

Calculate Float/Slack

Float = LS-ES or LF-EF

84
New cards

Forward Pass

ES + Duration - 1 = EF

85
New cards

Backward Pass

Critical Path (LF) - duration + 1 - LS

86
New cards

Free Float

• amount of time task can be delayed without delaying early start of its immediate successor

• ES of next activity - EF of current activity - 1

87
New cards

Total Float

amount of time task can be delayed without delaying overall project completion date

88
New cards

Float

LF - EF

89
New cards

Definitive Estimate

-5% to +10%

90
New cards

Budget Estimate

-10% to + 25%

91
New cards

Rough Order of Magnitude Estimate

-25% to +75%

92
New cards

RACI chart

Responsible, Accountable, Consulted, and Informed, and prevents bottlenecks by clearly defining task ownership

<p>Responsible, Accountable, Consulted, and Informed, and prevents bottlenecks by clearly defining task ownership</p>
93
New cards

Calculate Communication Channels

Channels = n(n-1)/2

n = number of people on the project

94
New cards

Negative Risks

threats

95
New cards

Positive Risks

Opportunities

96
New cards

Firm Fixed Price

Price stated in the agreement does not change, regardless of any type of environmental change.

97
New cards

Fixed Price Incentive Fee

Fixed-price contract with bonuses for meeting goals

98
New cards

Fixed Price Economic Price Adjustment

provides for upward and downward revision of the stated contract price upon the occurrence of specified contingencies

99
New cards

Time and Material Contract

• Time and material contract when buyer pays for both labor and material

• Buyer takes all the risk of cost overrun for both the labor and materials

• Should only be used when scope is high level

100
New cards

5 Levels of Stakeholder Engagement

unaware, resistant, neutral, supportive, and leading