All of the following are typical objectives of resource management EXCEPT ____________________
increase product demand
All of the following are true about aggregate planning EXCEPT that aggregate
plans define output levels over a planning horizon of one to two week
___________________________ specifies more-detailed plans for the creation of individual goods and services or the allocation of capacity to specific time periods.
disaggregation
_______________________ resource planning integrates all aspects of a business into a unified information system.
Enterprise
When assessing aggregate planning variables, pricing strategies is an example of ____________________________ and subcontracting is an example of a(n) ________________________ option
demand management; production rate
When assessing aggregate planning variables, acquisition and training costs are examples of implications of the ____________________ options
workforce
When calculating the production level in an aggregate production plan, if you know the ___________________________ and ______________________________ for each period, the ending inventory is easily determined
production; demand
A(n) ___________________ production strategy plans for the same production rate in each time period. A(n) ____________________ production strategy sets the production rate equal to the demand in each time period.
level; chase demand
Product mix models seek to determine quantities of different products to produce and sell in order to maximize contribution to __________________
profit
All of the following are true about process selection models EXCEPT ____________________________________________________________.
the objective is usually to meet demand requirements
_______________________________________________________________________________ best describes a master production schedule.
A statement of how many finished items are to be produced and when they are to be produced
A bill of __________________ defines the hierarchical relationships between all items that comprise a finished good. A bill of ________________ is a hierarchical record that defines work inputs necessary to create a good or service.
materials; labor
All of the following are basic concepts of MRP EXCEPT __________________________
inventory management to minimize downtime
The equation Setup time (S i ) + Processing time (P i ) × Order size (Q i ) measures:
a. Maximum output (M i )
b. Control limitations (C i )
c. Capacity required (C i )
d. Demand rate (D i )
c. Capacity required (C i )
___________________________________________________________________________________ best defines capacity resource planning.
the process of determining the amount of labor and machine resources required to complete the tasks of production on a more detailed level