1/71
Looks like no tags are added yet.
Name | Mastery | Learn | Test | Matching | Spaced |
---|
No study sessions yet.
Plate line capacity
the bucket volume contained
within the bucket when following the outline of the bucket
sides
Struck capacity
bucket capacity when the load is
struck off flush with the bucket sides
Water line capacity
assumes a level of material flush with the lowest edge of the
bucket (i.e., the material level corresponds to the water level
that would result if the bucket were filled with water)
Heaped volume
the maximum volume that can be placed
in the bucket without spillage based on a specified angle of
repose for the material in the bucket
Excavator
defined as a power-driven digging machine
crane shovel
family of cable-operated construction machines
Arms, extendible
Replaces the standard stick to provide
extra reach.
Auger
Drills holes for poles, posts, soil sampling, and
ground improvement.
hydraulic excavator
original and most common form of hydraulically powered excavator
backhoe
an
excavator designed primarily for excavation below grade. As
the name implies, it digs by pulling the dipper back toward
the machine
hydraulic shovel
digs with a combination of crowding force and breakout (or
prying) force
draglines
very versatile machine that has the longest
reach for digging and dumping of any member of the craneshovel family
clamshell
When the crane shovel is equipped with a crane boom and
clamshell bucket, it becomes an excavator known as
pipe jacking
involves forcing pipe horizontally through the soil.
horizontal earth boring
horizontal hole is created
mechanically or hydraulically with the pipe to be installed
serving as the casing for the hole. Some of the many installation methods used include auger boring, rod pushing
(thrust boring), rotational compaction boring, impact piercing, horizontal directional drilling, and fluid boring. A
Microtunneling or utility tunneling
similar to the
conventional tunneling except for the tunnel size and use
Pipe bursting
uses a high-powered hydraulic
or pneumatic piercing tool equipped with a special bursting
head to shatter the existing pipe and enlarge the opening
Cranes
are primarily used for lifting, lowering, and transporting loads. They move loads horizontally by swinging or
traveling.
Fixed time
represents those components of cycle time
other than travel time. It includes spot time (moving the
unit into position to begin loading), load time, maneuver
time, and dump time.
Variable time
epresents the travel time required for a
unit to haul material to the unloading site and return.
20 + 6(cm. penetration) [kg/ton]
40 + 30 (in. penetration) [lb/ton]
Rolling Resistance Factor Formula
10(grade in %) [kg/ton]
20(grade in %) [lb/ton]
Grade Resistance Factor
dozer or bulldozer
tractor equipped with a front-mounted earthmoving
blade is known as a; moves earth
by lowering the blade and cutting until a full blade load of material is obtained
Granular Admixtures
Soil blending with granular
material is often used to produce a well-graded mixture,
without excessive fines, which is suitable for compaction.
Portland cement
The effectiveness of portland cement
as an admixture diminishes rapidly as the soil's plasticity
index exceeds 15. The soil-cement mixture may need to be
placed in multiple lifts to obtain depths greater than about
8 in. (20 cm).
Lime
The use of quicklime results in much faster strength
gain than does hydrated lime. However, quicklime is hazardous to handle.
Asphalt
Asphalt admixtures are generally not effective in
soils having more than about 30% fines by weight or a plasticity index greater than about 10
Grading
the process of bringing earthwork to the desired
shape and elevation (or grade)
Finish grading, or simply
finishing
involves smoothing slopes, shaping ditches, and
bringing the earthwork to the elevation required by the plans
and specification.
prime coat
a coating of light bituminous material
applied to a porous unpaved surface. The purpose of the
prime coat is to seal the existing surface and to provide a
bond between the existing surface and the new bituminous
surface.
Tack Coat
a thin coating of light bituminous material
applied to a previously paved surface to act as a bonding
agent.
dust palliative
a substance applied to an unpaved
surface to reduce the amount of dust produced by vehicular
traffic and wind.
fog seal
light application of a slow-setting asphalt
emulsion diluted by one to three parts of water. It is used
to seal small cracks and voids and to rejuvenate old asphalt
emulsion slurry seal
composed of a mixture of
slow-setting asphalt emulsion, fine aggregate, mineral filler,
and water
sand seal
composed of a light application of a
medium-viscosity liquid asphalt covered with fine aggregates.
1. Sweep the existing surface.
2. Apply prime coat and cure, if required.
3. Apply binder at the specified rate.
4. Apply aggregate at the specified rate.
5. Roll the surface.
6. Sweep again to remove loose stone.
The sequence of operations involved in placing a single
surface treatment is as follows:
Penetration macadam,
as a pavement, is constructed using equipment and procedures very
similar to those employed for constructing aggregate surface
treatments.
Road mixes or mixed-in-place construction
re produced by mixing binder with aggregate directly on the
roadway
Warm-mix asphalt
produced at a temperature 50-100°F
(10-38°C) lower than usual hot-mix temperatures of
300-350°F (149-177°C
Resurfacing
involve surface treatments or overlays of
asphalt or concrete
Restoration and rehabilitation
broad
terms that include any of the work required to return the
highway to an acceptable condition
Recycling
consists of the demolition
of old pavement, recrushing of the pavement material, and
reusing it in new asphalt or concrete mixes
1. A settlement of 0.25 in. (6.35 mm) on the net settlement
vs. load curve.
2. The load determined by the tangent method previously
described.
3. The load that corresponds to the point on the net settlement vs. load curve where the slope equals 0.01 in.
per ton (0.28 mm/t).
A procedure used by the U.S. Army Corps of Engineers determines
ultimate pile capacity as the average of the following three
values:
pier
simply a column, usually of reinforced concrete,
constructed below the ground surface. It performs much the
same function as a pile. That is, it transfers the load of a
structure down to a stronger rock or soil layer.
shoring
Lateral support for the sides of an excavation is usually provided
Timber Shoring
employs vertical timber
uprights placed against the sides of the excavation, either in a
continuous fashion or at intervals.
Aluminum hydraulic shoring
employs prefabricated vertical rails as uprights with attached hydraulic
cylinder crossbraces.
Lagging
nothing more than sheeting placed horizontally
Sheet piling
sheeting of concrete, steel, or timber that
is designed to be driven by a pile driver.
Vacuum Wells
wellpoints that are
sealed at the surface by placing a ring of bentonite or clay
around the well casing.
Electroosmosis
the process of accelerating the flow of water through a soil by the application of a
direct current
Grouting or pressure grouting
process of injecting a
grouting agent into soil or rock to increase its strength or stability, protect foundations, or reduce groundwater flow.
Curtain grouting
produces a linear deep, narrow zone
of grout that may extend to a depth of 100 ft (30 m) or more.
It is commonly employed to form a deep barrier to water
flow under a dam.
Hardwood
produced from
deciduous (leaf-shedding) trees.
Softwood
comes from
conifers (trees having needlelike or scalelike leaves), which are
primarily evergreens
Timber
broadly classified as
lumber having a smallest dimension of at least 5 in. (12.7 cm).
Glulam
is composed
of layers of wood 2 in. (5 cm) or less in thickness which are
glued together to form a solid structural member.
Plywood
a wood structural material formed by gluing
three or more thin layers of wood (veneers) together with
the grain of alternate layers running perpendicular to each
other.
Particleboard
produced in sheets by bonding wood
chips together with resin
Waferboard
similar to particleboard except that it is
manufactured from larger wood chips.
Consolidation
the process of removing air voids in concrete as it is placed.
Finishing
the process of bringing the surface of concrete to
its final position and imparting the desired surface texture.
Screeding
the process of striking off the
concrete in order to bring the concrete surface to the
required grade
Floating
smooths and compacts the surface while embedding aggregate particles
Troweling
with a steel trowel follows
floating when a smooth dense surface is desired
Curing
The process of providing the required
water and maintaining a favorable temperature for a period of
time after placing concrete is referred to
Vacuum dewatering
may be employed to reduce the
amount of free water present in plastic concrete after the
concrete has been placed and screeded
Structural Concrete
1. Unstable form bracing and poor form alignment evidenced by form bulging, spreading, or inaccurately
aligned members.
2. Poor alignment of reinforcing steel and exceeding prescribed tolerances.
3. Obvious cold joints in walls.
4. Excessively honeycombed wall areas.
5. Belated form tie removal, form stripping, and patching.
6. Inadequate compaction (mechanical vibration, rodding,
or spading).
Concrete Slabs on Grade
1. Poor compaction of subgrade evidenced by slab
settlement.
2. Saturation and damage to subgrade caused by water
standing around foundation walls and/or inadequate
storm drainage.
3. Uneven floor slab finishes.
4. Inadequate curing of floor slabs.
A review by the U.S. Army Corps of
Engineers has produced the following ist of repetitive deficiencies observed in concrete construction:
course
horizontal layer of brick in
the plane of the wall
wythe
vertical section one brick thick
Headjoints
vertical mortar joints between
brick ends
Masonry grout
luid mixture of cement, sand, and
water or cement and water