1B3 Chapter 4 Pressure Vessel and Piping Repairs

0.0(0)
Studied by 0 people
call kaiCall Kai
Locked
learnLearn
examPractice Test
spaced repetitionSpaced Repetition
heart puzzleMatch
flashcardsFlashcards
GameKnowt Play
Card Sorting

1/313

flashcard set

Earn XP

Description and Tags

1st Class Power Engineering

Last updated 10:33 AM on 8/23/26
Name
Mastery
Learn
Test
Matching
Spaced
Call with Kai
Chat

No analytics yet

Send a link to your students to track their progress

314 Terms

1
New cards

What is the main responsibility of individuals or organizations that own or operate pressure vessels and piping?

To comply with all rules and legislation of the municipal or provincial safety authority regarding their equipment.

2
New cards

What are the objectives for compliance with safety codes and regulations for pressure vessels?

To maintain equipment integrity, protect people and the environment, and sustain cost-effective operations.

3
New cards

What does the CSA Code B51-03 provide guidelines for?

It provides guidelines for the operation, maintenance, and repair of pressure vessels and pressure piping.

4
New cards

Which engineering codes are referenced in CSA B51-03 for pressure vessel repairs?

American Society of Mechanical Engineers (ASME), National Board Inspection Code (NBIC) NB-23, and ANSI/API 510 and 570.

5
New cards

What must a first-class power engineer understand regarding pressure vessel repairs?

The safety standards act and regulations of their province or territory.

6
New cards

What is the overall responsibility of the owner of a pressure vessel?

To ensure compliance with safety standards and regulations for the pressure vessel and piping system.

7
New cards

What is required for a pressure vessel to be constructed or operated in Canada?

It must have a Canadian Registration Number (CRN).

8
New cards

What are the key components of a quality assurance/quality control (QA/QC) program?

A detailed description of all requirements for a fully functional QA/QC program as outlined in NBIC NB-23.

9
New cards

What should a preventive maintenance program include?

Clearly defined procedures for maintenance of pressure vessels and piping.

10
New cards

What is the purpose of an inspection program for pressure vessels?

To track and trend the condition of pressure vessels and ensure compliance with safety standards.

11
New cards

Who is responsible for ensuring that inspections and repairs are conducted by qualified individuals?

The owner or plant manager.

12
New cards

What is the first step in the repair process for a pressure vessel?

Carrying out an initial inspection by a qualified person approved by the safety authority.

13
New cards

What must happen after a repair procedure is developed for a pressure vessel?

It must be documented and signed by a certified engineer or qualified individual.

14
New cards

What is required after a repair is completed on pressure equipment?

Post-repair testing procedures must be carried out as specified in the jurisdiction's codes.

15
New cards

What documentation is required after repairs to pressure vessels?

All required reports and documentation must be prepared and copies delivered to the appropriate safety authority.

16
New cards

What is the purpose of tracking and trending inspection data?

To respond to any issues and ensure ongoing compliance with safety standards.

17
New cards

What is the role of a certified inspector in the inspection process?

To perform various inspection processes for pressure vessels and piping according to established qualifications.

18
New cards

What is the significance of the Canadian Registration Number (CRN)?

It indicates that the pressure vessel is registered for construction and operation in Canada.

19
New cards

What must be ensured when choosing a consulting company for repairs?

The company must be approved by the appropriate regulating body or authority.

20
New cards

What is the importance of a clearly defined inspection program?

It helps ensure that inspections are thorough and compliant with safety standards.

21
New cards

What is a common problem area identified during pressure vessel inspections?

Cracks and corrosion.

22
New cards

What must be done before a pressure vessel can be returned to service after repairs?

Follow-up inspection, testing, documentation, and record keeping must be completed.

23
New cards

What is the role of the owner or plant manager in the maintenance of pressure vessels?

To develop, institute, and maintain continuous quality assurance and preventive maintenance programs.

24
New cards

What is the purpose of a preventive maintenance program?

To ensure the ongoing safe operation of pressure vessels and piping.

25
New cards

What is the role of the safety authority in the repair process?

To review and approve the repair procedure before it is implemented.

26
New cards

What type of testing may be required after repairs to pressure vessels?

Hydro-testing, radiography, or other non-destructive examination (NDE) testing.

27
New cards

What is the consequence of failing to comply with safety standards for pressure vessels?

Increased risk of equipment failure, safety hazards, and potential legal repercussions.

28
New cards

What may be required if a repair is significant or alters a pressure vessel?

A new CRN (Canadian Registration Number) and/or a new nameplate.

29
New cards

What is required for a repair company to manage and perform repairs on pressure vessels in most provinces?

The company must be certified and hold an R Stamp from the NBIC or an ASME repair code stamp.

30
New cards

What must non-certified owners or repair companies do when performing repairs?

Repairs must conform to the same rules and regulations governing ASME or NBIC certified shops.

31
New cards

Who reviews and approves the details of repairs before they commence?

The regional safety manager under whose jurisdiction the equipment resides.

32
New cards

What is the purpose of evaluating and inspecting pressure vessels and piping?

To ensure long-term operational integrity.

33
New cards

What document provides guidelines for Fitness for Service in pressure equipment?

API 579.

34
New cards

Which industries specifically use the API 579 standard?

Oil and gas, and petrochemical industries.

35
New cards

What do the codes and standards for pressure vessels cover?

Original engineering, design, and construction processes.

36
New cards

What does Fitness for Service help owners and users to do?

Make risk-based decisions about the existing integrity of pressure equipment.

37
New cards

What are the key components of a Fitness for Service program?

Standardization, outlining objectives, auditing methods, follow-up methods, and feedback systems.

38
New cards

What is included in the baseline data for a Fitness for Service program?

Detailed design, installation, construction data, and equipment specifications.

39
New cards

What does MAWP stand for?

Maximum Allowable Working Pressure.

40
New cards

What should the inspection requirements matrix be based on?

Levels of risk, original designs, current operating parameters, environmental conditions, historical data, and accepted engineering practices.

41
New cards

What is the purpose of a response matrix in a Fitness for Service program?

To identify minimum allowable wall thickness and trends indicating high risk.

42
New cards

What should be standardized in a Fitness for Service program?

Timing of inspections, NDE evaluation methods, and areas to be inspected.

43
New cards

What does NDE stand for?

Non-Destructive Examination.

44
New cards

What is the goal of quantifying corrosion and damage in pressure vessels?

To objectively analyze and interpret the results for maintenance decisions.

45
New cards

What is the significance of historical data in a Fitness for Service program?

It helps in assessing the condition and trends of the equipment over time.

46
New cards

What should be included in the action plan activation system?

Components that identify minimum allowable wall thickness and trends indicating high risk.

47
New cards

What is a critical aspect of maintaining a Fitness for Service program?

Implementing a systematic method of feedback and program enhancement.

48
New cards

What does the term 'fitness for service' refer to?

The ability of pressure equipment to operate safely and effectively under specified conditions.

49
New cards

What is the role of the American Petroleum Institute in pressure vessel safety?

To issue standards like API 579 for Fitness for Service.

50
New cards

What is the importance of site-specific knowledge in a Fitness for Service program?

It ensures the program addresses unique issues related to the facility and equipment.

51
New cards

What does the acronym ASME stand for?

American Society of Mechanical Engineers.

52
New cards

What does the term 'corrosion allowance' refer to?

The extra thickness of material included in the design to account for expected corrosion.

53
New cards

Why is it important to standardize methods for tracking and trending inspection data?

To ensure consistency and reliability in data analysis and decision-making.

54
New cards

What is the objective of an inspection program for pressure vessels?

To identify wear, metal or material loss, corrosion or erosion, and any thermal, mechanical, or chemical actions that may compromise integrity.

55
New cards

What are the key components of a repair strategy for pressure vessels?

Quality control program, flow chart for tracking repairs, accepted repair practices and standards, testing methodology post-repair, and management of change program.

56
New cards

What is the importance of visual inspection in pressure vessel maintenance?

It allows for quick identification of patterns and trends, covering internal and external surfaces effectively.

57
New cards

What are the two stages of visual inspection?

Stage one: Inspect for leaks and potential issues without disturbance. Stage two: Inspect cleaned surfaces for specific discontinuities.

58
New cards

What does Magnetic Particle Testing (MPT) detect?

Surface discontinuities such as cracks by using magnetic fields to attract particles to defects.

59
New cards

How does Liquid Penetrant Testing (LPT) work?

A colored penetrant is applied to the surface, allowed to seep into voids, then a developer highlights discontinuities.

60
New cards

What is the purpose of a management of change program in equipment repairs?

To manage changes to equipment, processes, or operating parameters associated with repairs.

61
New cards

What is the significance of ASME Section V in inspection programs?

It provides detailed information on non-destructive examination (NDE) practices and qualifications for inspectors.

62
New cards

What does API 570 and 510 detail?

Inspection methods and practices for pressure piping and pressure vessels, respectively.

63
New cards

What is the role of documentation in an inspection program?

To record data in a standardized format that is clear, easy to understand, and can be tracked and trended.

64
New cards

What is the first step in a visual inspection process?

Inspect for leaks, potential flow patterns, and visual stress areas before any disturbance.

65
New cards

What is the purpose of a flow chart in a repair strategy?

To track the repair process from problem identification to final documentation.

66
New cards

What type of issues can be identified through visual inspections?

Leaks, corrosion, erosion, and stress areas.

67
New cards

What is the main advantage of having the same inspector for visual inspections each year?

The inspector becomes trained to recognize patterns and trends specific to that equipment.

68
New cards

What does the term 'non-destructive examination' (NDE) refer to?

Inspection methods that do not damage the equipment being tested.

69
New cards

What is the significance of a quality control and assurance program in repairs?

To ensure that repairs meet established standards and practices.

70
New cards

What is the purpose of testing methodology after repairs?

To prove the integrity of the equipment before it is reinstated for service.

71
New cards

What is the role of the chief engineer during inspections?

To oversee the inspection process and ensure all potential issues are addressed.

72
New cards

What is the benefit of using a variety of NDE processes?

To best suit the metallurgy and processes being inspected.

73
New cards

What is the typical outcome of a well-executed inspection program?

Enhanced integrity of pressure vessels and reduced associated risk levels.

74
New cards

What is the purpose of the developer in Liquid Penetrant Testing?

To draw the penetrant from surface discontinuities, highlighting problem areas.

75
New cards

What does the term 'accepted repair practices' refer to?

The codes and standards that must be followed during repairs.

76
New cards

What is the main focus of Radiographic Testing?

To detect discontinuities in materials and inspect welds for defects.

77
New cards

What is the importance of a standardized inspection process?

To ensure consistency and reliability in evaluating the condition of pressure vessels.

78
New cards

What is the role of visual stress areas in inspections?

They indicate potential points of failure or concern in the pressure vessel.

79
New cards

How does the inspection program contribute to facility safety?

By identifying issues that could compromise the operation and integrity of pressure vessels.

80
New cards

What is the significance of tracking and trending inspection data?

To identify patterns over time and improve maintenance strategies.

81
New cards

What is the purpose of radiographic testing?

To inspect the integrity of materials by using gamma rays or x-rays to reveal flaws.

82
New cards

How does radiographic testing reveal discontinuities?

Discontinuities appear as dark lines or overexposed spots on the film due to varying ray penetration.

83
New cards

What is required to compare the integrity of a weld during radiographic testing?

A reference piece of metal of the same thickness and metallurgy as the vessel wall.

84
New cards

What is the retention period for exposed films from inspections?

From 5 years to the life of the facility, depending on codes and regulations.

85
New cards

What does ultrasonic testing (UT) use to detect flaws?

High frequency sound waves that bounce back upon hitting a surface or discontinuity.

86
New cards

What is the role of a calibration block in ultrasonic testing?

To check the accuracy of the UT device after a specific number of tests.

87
New cards

What does metallographic testing evaluate?

The condition of the metal microstructure after polishing and etching the surface.

88
New cards

What is the purpose of acoustic emission testing?

To collect transient acoustic emissions generated by energy release from localized sources.

89
New cards

How does eddy current testing (ECT) work?

It uses magnetic fields generated by AC currents to detect discontinuities and material loss.

90
New cards

What is a critical requirement for effective eddy current testing?

There must be prior knowledge of what is being tested for specific results.

91
New cards

What is one function of a deaerator in pressure vessels?

To remove undesirable gases like oxygen and carbon dioxide from feedwater.

92
New cards

What environmental conditions can affect deaerators?

Hot, damp environments with external vibrations and airborne contaminants.

93
New cards

What type of corrosion can occur in deaerators due to hydrogen ions?

Hydrogen embrittlement and hydrogen cracking.

94
New cards

What is the impact of fluctuating temperature and pressure on deaerators?

It promotes vibration and cyclic action on the metal and its components.

95
New cards

What can cause underdeposit corrosion in deaerators?

Concentration of chemicals in various places within the vessel.

96
New cards

What is the effect of changing fluid flow rates in a deaerator?

Increased potential for washing and channeling of fluids.

97
New cards

What is the significance of a high-powered field microscope in metallographic testing?

It allows for detailed evaluation of the metal's microstructure.

98
New cards

What is the relationship between the intensity of rays and the darkness of the film in radiographic testing?

The darkness of the film is directly proportional to the volume or intensity of rays that pass through.

99
New cards

What is the primary advantage of ultrasonic testing?

It provides highly accurate detection of flaws beneath the surface.

100
New cards

What must be done before performing ultrasonic testing?

The surface must be cleaned and usually a gel is applied.