1/38
Looks like no tags are added yet.
Name | Mastery | Learn | Test | Matching | Spaced |
|---|
No study sessions yet.
What type of consultant is less likely to be chosen based on geographical proximity to site?
structural engineer
Civil and traffic should be local/close
Geotechnical should be local/close
Landscape should be close
AHPP page 608
Scope creep:
scope of work being stretched out or expanded by ambiguities, events, or conduct
AHPP page 1031
Most frequent cited cause for communication claims by owner that Architect should consider?
lack of procedures to identify conflicts, errors, and emissions
AHPP page 1002
Under typical Architect - consultant agreement what should the consultants standard of care be?
At the same level as Architect standard of care since Architect has prime agreement
Per A201; preparing revised drawings for change order is:
An additional service
B101 methods of compensation mutually agreed between two parties:
Stipulated sum
Percentage of construction
AIA B101 article 11.1
According to A201, who is responsible for recording field changes?
Contractor
Records all changes in the field on a record set of drawings
How should Architect proceed if there is a discrepancy between number figures and amount described in words in a bid review?
Disregard numerical amount
In case of discrepancy, the amount written in words shall govern
AIA A701 article 4.1.3
According to A295 and B195 what is considered to be part of Architect additional services?
assistance to the initial decision maker, if other than Architect
Programming phase:
information gathering; not Design
When using traditional methods who typically has authority to reject work, not conforming to contract documents?
Architect and owner
When should a consultant be brought into Project?
As early as possible, specially, in large projects
What phase are typical construction details, diagrammatic, layout of building systems, outline specifications, developed for owner approval?
Design development
Schedule method for short duration projects with a few tasks:
milestone chart
Items to factor in when making schedule:
review times from AHJ
Time for owners consultants to complete their work
Project milestones
Time for owner review
AIA B101 section 3.1.2
Who is responsible for preparing certificate of substantial completion?
Architect
Architect and its sub consultant shall approach owner hired consultants omissions by:
sending owner additional service/coordination service to fix mistake by third-party
After recognizing the need for additional services, Architect must explain to owner and establish an agreement in writing with owner before proceeding with work
3 main levels of a work breakdown structure:
project name
Phase name
Task name
AHPP chapter 10.3 page 629
Benefits of using critical path method to schedule project:
Identify critical tasks that affect the Project schedule
Determining float time
Highlighting dependencies of related construction activities
large scale planning can be difficult to integrate with critical path method
AHPP page 685 - 686
When/what stage does Architect incorporate government design requirements of authority having jurisdiction over Project?
construction documents
Construction and services required by contract documents whether complete or partially complete referred to:
The work
A201 article 1.1.1
AHPP page 1088 to 1089
A133 and B133:
A133 - standard form of agreement - owner and construction manager as constructor
B133 - standard form of agreement - owner and Architect construction manager as constructor
Cost of work:
Total cost to owner to construct all elements of Project designed by Architect
Includes contractors general conditions, overhead and profit
Does not include Architect free, cost of land and contingencies
Architect does not provide warrant to cost
Umbrella or Keystone document reference by many other documents:
A201 general conditions
During bidding process modifications to the contract documents (prior to a warning contract) are made via:
Addendum
4 typical components of an effective work plan:
Statement of deliverables
Project directory
Responsibility matrix
Preliminary project schedule
Others are: project description & client requirements, team organization, preliminary staffing needs, internal project budget and profit plan
AHPP chapter 10.1
Period of time considered doing lifecycle analysis:
from final completion through a building’s useful lifetime
3 types of RFI’s:
Type I: graphic / confirm confirming RFI (2 hrs)
Type II: coordination / missing information (5 hrs)
Type III: code / contract information (8 hrs)
AHPP chapter 12.1 page 816
Design elements Architect needs to review as a result of a change of construction type:
Maximum floor area
Allow building height
Structural spans
AHPP chapter 13.1
According to B101 who is responsible to identify a representative on their behalf?
Owner
Architect
AIA B101 articles 2.3 and 5.3
Who is responsible for obtaining certificate of occupancy?
Owner
Change order - according to A201 general conditions of contract for construction:
Change in work
Change in contract time
Change to contract sum
Signed by owner, general contractor, and architect
A201 article 7.2
How many days does owner have to give contractor necessary information regarding mechanic lien rights?
within 15 days after receipt a written request
A201 article 2.1.2
When using AIA agreements who is responsible for contracting NTT’s providing utilities to the Project?
Architect
B101 article 3.1.5
4 phases of building commissioning:
Design phase
Construction phase
Acceptance phase
Post acceptance phase
AHPP chapter 10.10 page 737
Potential effects on extending the design phase of Project?
Overhead cost increase
Construction cost decrease
Higher quality Project
Risk factors when determining fee:
site
Schedule
Owner
AHPP chapter 15.2
Determining Architect new fee on new total construction:
Calculate total square footage
Calculate cost / square footage; if inflation account for percentage of inflation
Calculator total cost for construction
Determined Architect fee
Information / content that contractor can submit in order to perform work during construction administration?
shop drawings
Product data
Samples
Mock ups