PROJECT MANAGEMENT:budgeting

0.0(0)
Studied by 0 people
call kaiCall Kai
Locked
learnLearn
examPractice Test
spaced repetitionSpaced Repetition
heart puzzleMatch
flashcardsFlashcards
GameKnowt Play
Card Sorting

1/24

encourage image

There's no tags or description

Looks like no tags are added yet.

Last updated 11:03 AM on 8/29/26
Name
Mastery
Learn
Test
Matching
Spaced
Call with Kai
Chat

No analytics yet

Send a link to your students to track their progress

25 Terms

1
New cards

PV — Planned Value

Formula: PV = BAC × planned % complete. The portion of the total budget that should have been spent by now, based on the original schedule — a measure of what work SHOULD have been done.

2
New cards

EV — Earned Value

Formula: EV = BAC × actual % complete. The portion of the total budget associated with the work genuinely completed so far — a measure of what work HAS actually been done.

3
New cards

AC — Actual Cost

The real amount of money that has actually been spent on the project up to this point in time.

4
New cards

BAC — Budget at Completion

The total approved budget for the entire project, agreed before work begins.

5
New cards

SV — Schedule Variance

Formula: SV = EV − PV. The gap, in money, between work completed and work planned. Positive = ahead of schedule. Negative = behind schedule.

6
New cards

CV — Cost Variance

Formula: CV = EV − AC. The gap, in money, between the value of work completed and the money spent on it. Positive = under budget. Negative = over budget.

7
New cards

SPI — Schedule Performance Index

Formula: SPI = EV ÷ PV. A ratio showing how much work is being completed relative to what was planned. Above 1 = ahead of schedule. Below 1 = behind schedule.

8
New cards

CPI — Cost Performance Index

Formula: CPI = EV ÷ AC. A ratio showing how efficiently money is being converted into completed work. Above 1 = cost-efficient. Below 1 = cost-inefficient.

9
New cards

CSI — Cost Schedule Index

Formula: CSI = SPI × CPI. A single combined score for overall time-and-cost performance. Limitation: because it multiplies two ratios, strong performance in one can mask poor performance in the other, so it should not replace checking SPI and CPI individually.

10
New cards

EAC (Method 1 — based on progress to date)

Formula: EAC = BAC ÷ CPI. Forecasts total project cost assuming the team continues working at its CURRENT cost-efficiency for the rest of the project.

11
New cards

EAC (Method 2 — based on original estimation)

Formula: EAC = AC + (BAC − EV). Forecasts total project cost assuming the REMAINING work will go exactly to the original plan, regardless of past performance.

12
New cards

EAC (Method 3 — based on remaining work and performance)

Formula: EAC = AC + (BAC − EV) ÷ CSI. Forecasts total project cost assuming the remaining work is affected by BOTH current cost and schedule efficiency combined.

13
New cards

ETC — Estimate to Complete

Formula: ETC = EAC − AC. The additional money still expected to be needed to finish the remaining work, based on a chosen EAC.

14
New cards

VAC — Variance at Completion

Formula: VAC = BAC − EAC. The expected gap between the original total budget and the forecast final cost. Positive = expected underspend. Negative = expected overspend.

15
New cards

TCPI-BAC — To-Complete Performance Index (vs original budget)

Formula: TCPI-BAC = (BAC − EV) ÷ (BAC − AC). The cost-efficiency the team must achieve on remaining work to finish within the ORIGINAL approved budget.

16
New cards

TCPI-EAC — To-Complete Performance Index (vs revised forecast)

Formula: TCPI-EAC = (BAC − EV) ÷ (EAC − AC). The cost-efficiency the team must achieve on remaining work to hit a REVISED forecast (EAC). Note: if EAC was calculated using BAC ÷ CPI, this value will always come out equal to the current CPI — it just confirms the assumption already baked into that EAC.

17
New cards

PMB — Performance Measurement Baseline (cost baseline)

The approved, time-phased spread of the total budget over the life of the project — the "plan" curve that PV is drawn from at any point in time. BAC is the value of this baseline at project completion.

18
New cards

Contingency Reserve

Extra budget set aside for risks that have already been IDENTIFIED and estimated. Sits inside the cost baseline (PMB) and is controlled by the Project Manager.

19
New cards

Management Reserve

Extra budget set aside for risks that have NOT been identified in advance (unknown-unknowns). Sits outside the cost baseline, set as a fixed percentage based on organisational risk appetite, and is not controlled by the Project Manager.

20
New cards

KPI — Key Performance Indicator

A measurable indicator used to track progress toward a specific project objective. A good KPI is directly and precisely linked to that objective (e.g. "average waiting time" rather than the vague "customer happiness" for a delay-reduction objective).

21
New cards

Triple Bottom Line

A way of judging project success across three dimensions — People, Planet and Profit — rather than financial performance alone. A project can be financially successful yet still perform poorly here (e.g. harming staff wellbeing or the environment).

22
New cards

Data-Driven Management — Pros

Makes performance visible; supports evidence-based decisions; helps identify trends early; can justify corrective action; helps communicate project status clearly to stakeholders.

23
New cards

Data-Driven Management — Cons

Metrics can be misleading; poor-quality data creates false confidence; teams may "game" the metrics being tracked; numbers can hide real quality or user value; measures like % complete can be subjective.

24
New cards

Limitation of EVA

EVA depends on reliable measurement of % complete. If easier tasks are finished first, EV can exaggerate real progress — so the technique is only as trustworthy as the underlying progress data feeding it.

25
New cards

Why use an index (SPI/CPI) instead of just a variance (SV/CV)?

Variances (SV, CV) give an absolute £ gap, which means different things depending on project size. Indices (SPI, CPI) give a proportional rate, letting you judge severity fairly and compare across differently-sized projects — and it's the index form (CPI) that feeds directly into forecasting formulae like EAC.