Project
Have a definite beginning and end.
Can be any length of time.
Process and result are unique.
People, Internal Groups & Organizations can be involved.
Require a Purpose.
Project Purposes
Market Demand
Business Need
Technical Breakthrough
Customer Orders
Legal Requirement
Project Results
New Product
New Service
Product Enhancement
Improved Service
New Business Asset
Justifying a New Initiative
Business Case
Value Creation
Business Case
Made by proving the results of a project will fulfill one or more needs.
Value Creation
Dependent on how well it meets needs relative to the costs incurred.
Project Value Types - 8
Financial
Strategic
Social Good
Quality/Resilience
Organizational Empowerment
Customer Satisfaction
Technological Innovation
Intellectual Property
Project Management
Utilization of many different skills, resources, tools, techniques, and accumulated wisdom in order to effectively coordinate project activities and achieve goals.
Project Manager
Must be a good communicator.
Solve Problems
Make Decisions
Share Ideas
Reach Agreements
Resolve Conflicts
Move Forward with Project Work
4 Project Manager Key Activities
Manage Project Requirements
Address Stakeholder Needs
Maintain Communication
Balance Resource Constraints
Project Constraints
Limited resources are present in every project environment.
Effective project managers work to balance constraints and priorities.
Changes to any aspect of a project will impact other aspects where constraints are involved.
6 Key Areas of Project Constraint
Scope
Schedule
Risk
Budget
Quality
Resources
Balance Resource Constraints
Identifying and understanding constraints allows for effective management to take place.
Critical to understand what makes the initiative valuable, and what work most directly leads to this value.
Project Roles and Responsibilities
Clear roles and objectives empower teams to succeed.
Ideal team size and structure will vary based on project goals, scope and methodology.
Teams often change in size as the project life cycle progresses.
Key Project Role Types
Core
Extended
Functional
Operational
Core Team Members
Focused on project-related responsibilities full-time
Extended Team Members
Participate part-time in project activities, predominantly when their expertise is most valuable.
Functional Team Members
Contribute directly to fulfillment of project requirements and value creation.
Operational Team Members
Facilitate the work of functional team members via administrative support.
Key Project Roles
Leader
Facilitator
Sponsor
Product Owner
Business Analyst
Domain SME
Developers & Engineers
Testers & QA Specialists
Customers
End User
PMO
Governance Body
Leader
May be knows as project manager, coordinator, scrum master or by other titles
Primary person responsible for ensuring objectives are met and outcomes are satisfactory
Facilitator
An dditional role often fulfilled by project leader
Responsible for helping team members achieve goals by combating challenges and facilitating progress
Sponsor
Individual or entity responsible for committing organizational resources, providing funding, and certifying project objectives.
Often selects the project leader and other key roles.
Product Owner
The additional role often fulfilled by the project sponsor
Prioritizes requirements for ongoing work based on an understanding of value, risk, and activity dependencies.
Business Analyst
Performs gap analysis, elicits information from stakeholders and defines requirements
Works alongside the project leadership to define goals and explain context
Doman SME
(Subject Matter Expert)
Typically associated with the project for only a portion of its total duration
Provide useful insight in specifying requirements and may assist in implementation activities
Developers & Engineers
Accomplish much of the frontline work in completing requirements and generating new value for customers
Serve as an important resource in gauging resource requirements and identifying activity precedences.
Testers & QA Specialists
Ensure what is created aligns with requirements and meets expectations
May evaluate work using both functional and non-functional requirements.
Customers
May also serve as the product owner depending on the nature of the project
Represents the primary beneficiary of project work, defines values and verifies deliverables are acceptable
End User
May or may not be the same as the customer
Will be most directly impacted by the project's implementation and is an important source of perspective in planning and validating work
PMO (project management office)
Provides support, resources, and access to best practices to many project teams within the enterprise
Level of authority and oversight of project work may vary significantly depending on organizational norms
Governance Body
May be internal to the team or organization or may be an external regulatory authority
Ensures project work and results are in compliance and may provide approval in cases of formal review
Program Management
Optimizes the allocation of resources and talents and the prioritization of several projects to achieve a set of related goals
Programs unlock benefits not available by managing projects individually
Focus on project interdependencies, finding optimal combined approach to accomplishing several projects
Portfolio Management
Optimizes resources throughout the enterprise, coordination efforts across programs and projects to achieve strategic goals and organizational vision
Maximizes value across programs and projects
Aligns programs and projects to top-level organizational objectives
Sets organization-wide policies, procedures and resource allocations
The Project Management Lifecycle
May contain programs with many projects as well as individual projects not associated with a program.
Operations
top layer across the organization that takes care of accounting, human resources, the legal department, facility maintenance, etc.
Project Manager Skill Types
Business Skills
Technical Skills
Leadership Skills
Difference between Project Management & Project Leadership Skills
Not synonymous, but both essential to project success
Management involves directing team members to accomplish activities in order to meet objectives
Leadership involves guiding and influencing team members and stakeholders to meet objectives.
Project Leadership
Must develop consensus and build support for change initiatives to succeed - ability to communicate why it's important.
Incorporation of stakeholder perspective is central - their Motivations, Needs & Capabilities
Taking these into account affects how we Disseminate Information, Allocate Resources & Prioritize Actions
Leadership Goals
Gain stakeholder trust & respect
Develop a reputation for ethical behavior and fairness
Accomplish work on schedule and in line with expectations
Consistently deliver high-value, quality results
Adapt to changing circumstances and organizational needs
Core Project Management Skills
Leadership Skills
Communication Skills
Facilitation Skills
Political Skills
Analytical Skills
Technical Skills
Business Skills
Leadership & Communication Skills
Set the basis for any project management to take place
Facilitation Skills
helping others to accomplish the work they've been tasked with by providing the resources, confidence, support and detail necessary for them to accomplish their roles effectively
Political Skills
Necessary for effective leaders, need to understand perspective of others, build coalitions in support of the change we are orchestrating
Analytical Skills
Essential to our ability to know how the work is progressing, if we are on schedule, maintaining budget, and if we have met the criteria of the requirements themselves, do we perform at the level we expected or do we need to refine our work in order to achieve higher level objectives
Technical Skills
Must have sufficient context to understand perspectives of our SMEs. Don't need to code better than team members but do need to understand, difficulty levels, time requirements, what are practical requests, what are the limitations and challenges faced.
Business Skills
Accounting
Create Effective Presentations
Marshall resources into a meeting, facilitated toward a set agenda to share and generate information
Emotional Intelligence
Self Awareness
Social Awareness
Self Management
Self Awareness
Understanding our own emotional state at any given time, the stress that we might be under as we bring all these people together and the ways we present that stress to others
Social Awareness
Understanding the context of stakeholders. Be aware of transition period, training necessary and no downtime. Provide indisputable value
Self Management
Understanding our own emotional state as well as others allows us to understand what the best approach is to our own emotional presentation should be.
Relationship Management
Curate the relationship between ourselves and others, and between others and the project itself. Convincing all to work together in good faith toward a set of shared goals that benefits everyone.
Project Management Methodologies
Waterfall
Agile
Choosing a Project Methodology
Predictive
Iterative
Adaptive
Predictive Methodology
Clearly different work takes place in each phase
Major changes to team composition often take place at project milestones
Preferred when deliverable is well understood, based on established practices, and lacks value until fully complete
Iterative Methodology
Develop a product through series of repeated cycles
Incremental development process with careful change management
Helpful when objectives and scope are subject to change
Adaptive Methodologies
Similar to iterative model, but on a faster pace, often of 2-4 week cycles
Ideal in rapidly changing environments when scope is hard to define fully in advance
Often used when partially completed products offer value to stakeholders as development continues
Methodology Choice Factors
Budget and schedule constraints may influence methodology selection
Formal bid/proposal processes may necessitate a more predictive approach
Uncertainty about requirements may necessitate a more agile approach
Predictive (Waterfall)
Work best when requirements are known, or can be developed, with reasonable certainty
Steps are followed in a mostly linear order from chartering through completion
May be used in projects where all delivery occurs at the end or when major phases can offer value
Allows for high efficiency and for efforts to be replicated when requirements are fixed in nature
Can and must still adapt to change when value to customer exceeds costs to implement
Progressively elaborating plans as new information becomes available and greater detail becomes necessary buys any project initiative time to respond to change
Predictive (Waterfall) Steps
Gather Requirements
Generate Plans for Action
Execute on Project Plans
Monitor and Control Work
Maintain Change Controls
Deliver and Support Results
Gather Requirements
Meet with customer to document project requirements thoroughly and reach agreement on project outcomes
Design
Layout
Needs
Schedule
Delivery Date
Generate Plans for Action
Determine how, and in what sequence, project requirements should be implemented to meet objectives
Resource Constraints
Scheduling windows
Sequence
Respect Prerequisites
Execute on Project Plans
Implement work according to plans, deviating minimally at all times
Monitor and Control Work
Ensure plans are being followed and that completed work meets objectives
Maintain Change Controls
Ensure any deviations to plans are understood, communicated, approved and appended to project plans
Deliver and Support Results
Turn over completed work to customer all at once or at phase gates where validation results in acceptance
Progressive Elaboration
The iterative process of increasing the level of detail in a project management plan as greater amounts of information and more accurate estimates become available
Iterative Project Managment
Iterative approaches focus on delivering value incrementally through a process of refinement and expansion over time
Iterative projects may continue their work until marginal benefit is exceeded by marginal cost
Agile Project Management
Heavy focus on adaptability
Encourages change as a strategic benefit
Team organically self-organizes
Provides user value incrementally
Agile Key Principles
Individuals & Interactions > Processes & Tools
Working Software > Comprehensive documentation
Customer Collaboration > Contract Negotiation
Responding to Change > Following a plan
Individuals & Interactions
No detailed processes governing operations
No roles for team members strictly defined
Nurturing more organic relationships and work methods leads to innovations
Working Software (Product)
Time spent creating documentation is better spent creating simpler interfaces and generating new value
Documentation should follow functionality to minimize risk of rework as requirements change
Customer Collaboration
Change initiatives create value for customers
Deep and continuously updated understanding of what offers customers value should drive work
Responding to change
Needs and environmental factors may shift considerably during change initiatives
Just-in-time planning ensures minimal wasted work and optimal strategic alignment
Agile Assumptions
Changes always welcome
Problem definable as addressable needs
Team Continuity
Colocation - collaboration tools necessary
Engaged customers and empowered SMEs
Multidisciplinary team members
Continuous improvement
Delivery of value
Cadence of Delivery
Common interval: 2-4 weeks
or
Time to create substantial new value for customers on a sustainable basis
Questions for determining iteration interval or cadence of delivery
Are we delivering a similar amount of work on a consistent basis?
Is our delivery cadence sustainable?
Can we maintain high quality outcomes at this pace?
Agile Frameworks
DevOps
(XP) Extreme Programming
Kanban
(PRINCE2) Projects IN Controlled Environments
(SDLC) Software Development Life Cycle
(SAFe) Scaled Agile Framework
Scrum
DevOps
Method of integrating development and operations in a way that facilitates quick feedback and evolution for software-oriented projects
Removes barriers between "dev" and "ops" staff allowing for closer coordination and better learning
Variant term DevSecOps may be used when security and quality-related functions are also fully integrated into the team
Extreme Programming (XP)
Prescriptive methodology focused on adapting agile principles to certain software engineering settings
XP extols the virtues of communication, simplicity, feedback, courage and respect in agile development
Kanban
Translates to "signboard" or "signal" in English
Task board posted in a highly visible location or on a shared website
Provides at-a-glance updates on status of all work in progress
Allows for work in progress (WIP) limits to be set more easily
(PRINCE2) Projects IN Controlled Environments
Compatible with agile or predictive approaches
Focuses on a set of aspects and principles that relate to a set of tools and processes
PRINCE2 Agile tailors the framework for agile settings
(Can earn a certificate)
Software Development Life Cycle (SDLC)
Describes at a broad level the process software teams follow for the duration of a project initiative
Tasks in order:
Defining requirements
Design and prototyping
Development
Testing
Deployment
Operations and maintenance
(SAFe) Scaled Agile Framework
Facilitates agile transformation at an organizational level through a variety of principles and best practices
May be applied at several levels, encapsulating work at the team level, initiative level, portfolio level, or enterprise level
Scrum Framework
Iteration Planning
- Brief period to learn about and self-organize around tasks
Daily Stand-ups
-What was done yesterday?
-What gets done today?
-What are the obstacles?
Iteration Retrospectives
-Captures lessons learned that may be immediately applied
Impact of Environmental Factors
All methodologies must be tailored to project needs and environmental factors in order to be most effective
Factors are largely out of the team's control but materially impact how work may be undertaken
Factors may be internal or external to the organization
Recognizing the impact of these factors help leaders craft an optimal approach to project work
Leaders must remain aware of changes to factors
Internal Environmental Factors
Organizational
Geographic Dispersion
Infrastructure and Equipment
Tooling & Software
Resource Availability
Employee Capabilities
Organizational Factors
Structure of Organization
Formal authority reach as Project Manager
Resources available
Goals & Deadlines
Geographic Dispersion Factors
How dispersed are workers, locations, etc.
Warehouses, Fabrication centers, outsourced workers in other timezones
Tooling and Software Factors
Restricted to certain tool sets
Maybe you need to explain why other tools and equipment are needed
External Environmental Factors
Market Conditions
Cultural Influence
Legal Restrictions
Financial Limitations
Sources of Information
Research and Results
Standards and Best Practices
Physical Environment
Financing and Project Methodology
Financing is often tied to meeting certain objectives
Can impact Methodology or vice-versa
Agile $ either replenished at stages of development or may be continuous
Funding should be approved as part of the chartering process
Gap Analysis
Consider where we're at and what kind of future we want to create
Needs assessment
Find and recommend solutions
Document and Manage requirements
Plan and execute implementation
Business Case for Action
Describes the opportunity we seek to address and how we intend to take advantage of it
Composing Strong business cases leads to better decision-making and saves resources that might be wasted on more advanced chartering efforts
Allows disparate proposals to be evaluated on a more even basis
Typically templated in order to allow for easier comparison with other cases
-Defines Problem or opportunity
-Situation Analysis
-Recommended Action
-Conducting Evaluations
Develop Project Charter
Founding document that allows project work to begin
Should be created before significant work is completed
Explain the underlying need and why the project team has assembled
High-level requirements and milestones should be present
High-level budgetary and time restrictions
be signed off on by management with the authority to assign needed resources
May only be a page or two in length, but still critical to any serious project
-Statement of Works
-Business Case
-Contract
-Project Overview
-Project Approach
-Project Approval
Minimum Viable Product
The earliest version of our work that can offer some useful value
Benefiting from Existing Assets and Precedents
Make our work creating something new a little easier
Using Gap Analysis
-Analyze Stakeholders
-Conduct Business Analysis Activities
-Assess Environmental Factors
Ensure Requirements Traceability
Supporting the Business Case
-Payback Period = time until breakeven point
-Return on Investment = estimated net benefit divided by investment
-Internal Rate of Return = Estimated annual yield of project investment including ongoing costs
-Net Present Value = Sum of all expected future benefits with the time value of money taken into account
Project Overview
Background and Context; lays out business case
Outlines project scope and boundaries
Names key stakeholders and sponsor