Project management

0.0(0)
studied byStudied by 0 people
learnLearn
examPractice Test
spaced repetitionSpaced Repetition
heart puzzleMatch
flashcardsFlashcards
Card Sorting

1/68

encourage image

There's no tags or description

Looks like no tags are added yet.

Study Analytics
Name
Mastery
Learn
Test
Matching
Spaced

No study sessions yet.

69 Terms

1
New cards

What is scope creep in project management?

When the project's scope increases beyond the original plan during execution. It often results from customer or team changes and must be controlled through change management.

2
New cards

What are the four steps of the change management process?

1) Identify the change, 2) Evaluate impact on time/cost, 3) Sponsor decision, 4) Communicate to the team.

3
New cards

What marks the beginning of the closing phase in the project lifecycle?

The sponsor approves the completed deliverables.

4
New cards

What are lessons learned, and when are they documented?

Insights into what went well or didn’t during the project, documented in the closing phase to help future projects.

5
New cards

What is the main function of the Monitoring and Controlling process group?

To identify and respond to issues like scope creep, interpersonal problems, and risk during project execution.

6
New cards

Which process groups are iterative, and why?

Planning, Executing, and Monitoring & Controlling. They repeat as needed to address changes or issues.

7
New cards

What does a RACI chart represent?

It shows who is Responsible, Accountable, Consulted, and Informed for each task in the WBS.

8
New cards

What are the three categories of project risks?

Organizational, External, and Technical.

9
New cards

Define risk appetite.

The degree of risk an organization is willing to accept in pursuit of value.

10
New cards

Define risk tolerance.

The level of risk an organization can handle before it becomes unacceptable.

11
New cards

What is a risk threshold?

A specific point at which the organization takes action based on the level of risk (e.g., $10K cost).

12
New cards

What are the four risk responses?

Avoid, Accept, Mitigate, Transfer.

13
New cards

What is a risk register, and when is it created?

A document listing identified risks, their scores, responses, and responsible parties

14
New cards

created during planning.

15
New cards

What is ratio estimating?

Using per-unit costs from past projects (e.g., $35 per sq ft) to estimate current project costs.

16
New cards

What is apportion estimating?

Dividing total cost into portions by project area or function based on percentage estimates.

17
New cards

When is top-down estimating used?

In early project phases

18
New cards

SMEs provide high-level estimates from experience.

19
New cards

What is bottom-up estimating?

Detailed cost estimation done after the WBS is created, adding up all task-level costs.

20
New cards

Difference between contingency and management reserve?

Contingency: For known risks. Management: For unknown risks.

21
New cards

What is a calendarized budget?

A budget that maps spending across a timeline (e.g., months or weeks).

22
New cards

What is the 0-100 rule for reporting work?

Report 0% until a task is 100% complete.

23
New cards

What is the 50-50 rule for reporting work?

Report 50% when started, 100% when complete.

24
New cards

What is triangular distribution for estimating?

(Optimistic + Most Likely + Pessimistic) / 3

25
New cards

What is beta distribution for estimating?

(Optimistic + 4×Most Likely + Pessimistic) / 6

26
New cards

What does the learning curve concept describe?

Repetition improves task performance efficiency.

27
New cards

What is the 8/80 rule in WBS?

Tasks should be no less than 8 hours and no more than 80 hours.

28
New cards

What are the four task dependency types?

Finish-to-Start (most common), Finish-to-Finish, Start-to-Start, Start-to-Finish (least common).

29
New cards

What is the critical path in a project?

The longest duration path

30
New cards

any delay delays the entire project.

31
New cards

Name the three schedule compression strategies.

Crashing, Fast Tracking, Scope Reduction.

32
New cards

What are the three aspects of quality management?

Quality Management (define quality), Quality Assurance (build-in quality), Quality Control (test for defects).

33
New cards

What is Earned Value (EV)?

The value of the work completed to date.

34
New cards

What is Planned Value (PV)?

The value of the work planned to be completed at a point in time.

35
New cards

What is Actual Cost (AC)?

The amount spent on the project so far.

36
New cards

How do you interpret CV and SV in EVM?

Positive = good (under budget, ahead of schedule)

37
New cards

Negative = bad (over budget, behind schedule).

38
New cards

What do CPI and SPI values indicate in EVM?

1 = good, <1 = bad, =1 = on target (for cost or schedule).

39
New cards

What defines a project?

A temporary effort with a clear start and end, aimed at delivering a unique outcome.

40
New cards

What is a program in project management?

A group of related projects managed in a coordinated way.

41
New cards

What is a portfolio?

A group of programs and projects managed to meet strategic objectives.

42
New cards

What are the triple constraints in project management?

Scope, Time (Schedule), Cost (Budget).

43
New cards

What are the four lifecycle phases of a project?

Defining, Planning, Executing, Closing.

44
New cards

What are the five process groups?

Initiating, Planning, Executing, Monitoring and Controlling, Closing.

45
New cards

What is the purpose of a PMO?

To support project managers through best practices, lessons learned, and project reporting.

46
New cards

What is the purpose of project lifecycle phases?

To outline the sequential progression of a project from beginning to end.

47
New cards

What is the purpose of project process groups?

To manage and control different aspects of a project throughout its life.

48
New cards

Which process group is not part of the lifecycle phases?

Monitoring and Controlling.

49
New cards

What makes Planning, Executing, and Monitoring & Controlling iterative?

They are repeated whenever changes or issues arise.

50
New cards

Why are Initiating and Closing not iterative?

They occur only once at the start and end of a project.

51
New cards

How is scope creep managed?

Through the change management process.

52
New cards

What does the change management process control besides scope creep?

Any formal project change including budget, time, or deliverables.

53
New cards

Why is scope shown as one of the triple constraints?

Because it affects both budget and schedule.

54
New cards

What is the function of a project baseline?

To serve as a frozen reference for scope, cost, and time for comparison.

55
New cards

What does the term 'frozen baseline' mean?

It refers to locking the scope, schedule, and cost after planning.

56
New cards

What is the purpose of risk scoring in a risk register?

To prioritize risks based on probability and severity.

57
New cards

What does the risk threshold determine?

Whether a planned response is triggered based on magnitude.

58
New cards

What’s the difference between known and unknown risks?

Known risks are identified and planned for

59
New cards

unknown risks are not.

60
New cards

What is the purpose of estimating in project management?

To forecast time, cost, or resources needed to complete tasks.

61
New cards

Why is bottom-up estimating the most detailed?

Because it calculates the cost of every single activity or work package.

62
New cards

When is a calendarized budget useful?

For tracking planned spending over weeks or months.

63
New cards

How is a Work Breakdown Structure (WBS) used?

To break the project scope into smaller, manageable tasks.

64
New cards

Why does the 8/80 rule exist?

To ensure tasks are neither too small to manage nor too large to control.

65
New cards

What is float in project scheduling?

The amount of time a task can be delayed without affecting the project end date.

66
New cards

What does it mean when a task has zero float?

It’s on the critical path and delays will delay the whole project.

67
New cards

Why is fast-tracking risky?

Because overlapping dependent tasks can cause rework or errors.

68
New cards

Why does crashing increase project cost?

It usually involves adding resources to accelerate task completion.

69
New cards

What is the goal of scope reduction?

To reduce project duration by eliminating or reducing deliverables