PMP Exam Prep 3 - Ways of Working for Technical Projects

0.0(0)
Studied by 0 people
call kaiCall Kai
Locked
learnLearn
examPractice Test
spaced repetitionSpaced Repetition
heart puzzleMatch
flashcardsFlashcards
GameKnowt Play
Card Sorting

1/114

encourage image

There's no tags or description

Looks like no tags are added yet.

Last updated 1:15 AM on 8/20/26
Name
Mastery
Learn
Test
Matching
Spaced
Call with Kai
Chat

No analytics yet

Send a link to your students to track their progress

115 Terms

1
New cards

A project manager is assigned to a new project before detailed planning has begun. The sponsor wants the project manager to begin assigning team members and using organizational resources. What document should be created first to formally authorize the project manager’s authority?

Project charter

2
New cards

A project team is defining what work is included in the project and what work is excluded. Which project management area is primarily being addressed?

Scope management

3
New cards

A project manager is developing a high-level document that includes the project purpose, high-level risks, summary milestone schedule, summary budget, and stakeholder list. Which document is being created?

Project charter

4
New cards

A stakeholder asks why the project exists and how the expected benefits will be tracked after delivery. Which two documents best support this discussion?

Business case and benefits management plan

5
New cards

A project is using predictive delivery. The team is developing detailed plans for scope, schedule, cost, resources, quality, risk, communication, procurement, and stakeholder engagement. Which process group is most closely represented?

Planning

6
New cards

A team is working in an adaptive environment. Although formal predictive process groups are not used, the team still performs early project activities such as charter creation, product box exercise, XP metaphor, and sprint planning. What does this illustrate?

Adaptive projects still initiate and plan work, even if not through formal predictive process groups

7
New cards

A project manager needs to determine whether a requirement has been fulfilled and trace it back to the stakeholder who requested it. Which artifact should be used?

Requirements traceability matrix

8
New cards

A customer states that the system must process transactions within two seconds and be available 99.9% of the time. What type of requirement is this?

Non-functional requirement

9
New cards

A business leader states that the project must increase customer retention and improve business value. What type of requirement is this?

Business requirement

10
New cards

During scope definition, the team produces the project scope statement, WBS, and WBS dictionary Together, these form which baseline?

Scope baseline

11
New cards

The team decomposes work packages into specific actions needed to produce project deliverables Which process is being performed?

Define activities

12
New cards

A project manager explains that work packages are typically nouns, while activities are typically verbs Why is this distinction useful?

It helps distinguish deliverables from actions required to produce them

13
New cards

An activity cannot begin until a required permit is received from a government agency What type of dependency is this?

External dependency

14
New cards

A team chooses to complete design reviews before development because it is a preferred best practice, although not legally or physically required What type of dependency is this?

Discretionary dependency

15
New cards

A successor activity is allowed to start before its predecessor is fully complete What scheduling concept is being used?

Lead

16
New cards

A project manager adds a waiting period between concrete pouring and inspection to allow the concrete to cure What scheduling concept is being applied?

Lag

17
New cards

A project manager needs to estimate activity duration using optimistic, most likely, and pessimistic values Which estimating technique is being used?

Three-point estimating

18
New cards

An activity has an optimistic estimate of 4 days, a most likely estimate of 7 days, and a pessimistic estimate of 13 days Using the PERT weighted average formula, what is the expected duration?

7.5 days

19
New cards

A project manager uses historical data from a similar past project to estimate a new project quickly Which estimating technique is being used?

Analogous estimating

20
New cards

A project manager estimates each individual work package in detail and then aggregates the estimates to calculate the total project estimate Which estimating technique is being used?

Bottom

21
New cards

A schedule network diagram shows several paths The project manager needs to determine the earliest the entire project can be completed What should the project manager identify?

The critical path

22
New cards

A project activity can be delayed without delaying the project’s overall completion date What is this called?

Total float

23
New cards

A project activity can be delayed without delaying the early start date of its earliest successor activity What is this called?

Free float

24
New cards

The project has an externally imposed finish date, but the current schedule shows that the project will miss that deadline What condition exists?

Negative project float

25
New cards

A project manager adjusts activities within available float so that resource demand does not exceed capacity while preserving the project end date and critical path Which technique is being used?

Resource smoothing

26
New cards

A project manager changes the schedule to resolve resource constraints, and the project end date may change Which technique is being used?

Resource leveling

27
New cards

A team identifies risks that may occur and sets aside funds to address them if they happen These funds are included in the cost baseline What are these funds called?

Contingency reserves

28
New cards

A sponsor sets aside funds for unforeseen risks that were not identified during planning These funds are not included in the cost baseline and require senior management approval What are these funds called?

Management reserves

29
New cards

A project manager rolls up cost estimates from activities to work packages and then to higher WBS levels to develop the overall budget What technique is being used?

Cost aggregation

30
New cards

A project’s approved budget, excluding management reserves, is used to measure actual cost performance What is this called?

Cost baseline

31
New cards

A PMP exam scenario asks the project manager to choose the best action when cost, risk, stakeholder expectations, and value delivery are all involved What should the candidate focus on most?

Selecting the most appropriate action for the project environment and stakeholder value

32
New cards

A project manager is working on a hybrid project The team must follow regulatory compliance requirements while also using agile practices for product delivery What should the project manager do?

Tailor the approach to combine appropriate predictive and adaptive practices

33
New cards

A stakeholder requests a change to the approved schedule baseline in a predictive project What should the project manager do?

Follow formal change control

34
New cards

A project manager is comparing actual schedule progress against the approved version of the schedule model Which artifact is being used?

Schedule baseline

35
New cards

A project manager is preparing a student for the PMP exam and explains that the Process domain includes predictive, adaptive, and hybrid practices What is the best study implication?

Practice applying concepts across predictive, adaptive, and hybrid environments

36
New cards

A project team is executing work when a stakeholder asks the team to add a new reporting feature The feature seems simple and the team believes it can complete it without affecting the schedule What should the project manager do first?

Submit and evaluate a change request through formal change control

37
New cards

During execution, a supplier delivery delay has already occurred and is affecting project work Which project artifact should the project manager update first?

Issue log

38
New cards

A project manager receives raw measurements from the team, including hours worked, defects found, and tasks completed What are these measurements called before analysis?

Work performance data

39
New cards

A team reviews project results and identifies what worked well, what did not work well, and what should be done differently in future iterations What is the best PMP aligned action?

Capture and share lessons learned throughout the project

40
New cards

A project manager wants to confirm that the team is following approved quality standards and procedures Which activity best fits this need?

Quality audit

41
New cards

A planned risk response is implemented, but it creates a new risk that could affect future work What is this new risk called?

Secondary risk

42
New cards

A known risk occurs, and the project manager activates the response that was planned in advance What type of plan is being used?

Contingency plan

43
New cards

A planned contingency response does not work as expected What should the project manager consider next?

Fallback plan

44
New cards

The project team identifies an uncertain event that may provide a benefit if it occurs How should the project manager classify it?

Opportunity risk

45
New cards

Which statement best describes the difference between an issue and a risk?

An issue is current, while a risk is uncertain and may occur in the future

46
New cards

A project manager needs to estimate risk exposure A risk has a 40% probability of occurring and would cost $50,000 if it occurs What is the expected monetary value?

$20,000

47
New cards

A project team wants to use historical templates, lessons learned, and previous project information to guide current work What should the project manager consult?

Organizational process assets

48
New cards

Which artifact is most associated with an adaptive project environment?

Product backlog

49
New cards

A procurement team is reviewing vendor responses against technical capability, pricing, past performance, and compliance requirements What procurement activity is occurring?

Select seller

50
New cards

During vendor negotiations, who typically leads the negotiation while the project manager supports with subject matter expertise?

Procurement department

51
New cards

A project manager receives analyzed performance trends and variance explanations from the team What are these best described as?

Work performance information

52
New cards

A formal summary is prepared for stakeholders showing project status, forecasts, trends, and recommendations What is this output called?

Work performance report

53
New cards

A team member asks where to document the owner, cause, impact, recommendation, and resolution for a problem that is currently affecting the project What should the project manager recommend?

Issue log

54
New cards

A risk remains after planned risk responses have been implemented What is this called?

Residual risk

55
New cards

What is the primary purpose of Manage Quality?

To ensure project work follows quality processes and supports continuous improvement

56
New cards

A project manager wants to ensure project artifacts are reliable throughout the project Which set of actions is most appropriate?

Keep artifacts accurate, current, accessible, protected, version-controlled, and archived appropriately

57
New cards

Which statement best reflects the PMP mindset during execution?

Communicate, collaborate, document, follow governance, and act proactively but formally

58
New cards

A warning sign appears that suggests a risk may occur soon What is this called?

Risk trigger

59
New cards

A project manager is working with a vendor after contract award Which action is most appropriate?

Update schedules, resources, budgets, communications, risks, and stakeholder engagement as needed

60
New cards

Which reserve is most appropriate for risks that were identified and planned for?

Contingency reserve

61
New cards

A project sponsor asks the project manager to add a feature that was not included in the approved scope baseline The team says the feature is easy to add and will not affect the schedule What should the project manager do first?

Submit and evaluate a change request through integrated change control

62
New cards

A project manager compares actual performance against the project management plan and discovers a variance from the cost baseline What should the project manager do next?

Analyze the variance and determine whether corrective action or a change request is needed

63
New cards

A customer formally accepts a completed deliverable Which process is most closely associated with this activity?

Validate Scope

64
New cards

The team adds extra features to a deliverable because they believe the customer will appreciate them, even though the features were not requested or approved What is this an example of?

Gold plating

65
New cards

A project manager discovers that the team has been completing work not included in the approved scope baseline What should the project manager focus on controlling?

Scope creep

66
New cards

A change request has been submitted What is the correct next step before implementation?

Record, evaluate impact, and submit it through integrated change control

67
New cards

A change is approved by the Change Control Board What should the project manager do next?

Communicate the decision and implement the approved change

68
New cards

Which document defines how project changes will be submitted, reviewed, approved, and managed?

Change management plan

69
New cards

Which plan focuses on controlling project artifacts, versions, and revisions?

Configuration management plan

70
New cards

Which type of change request is intended to bring project performance back in line with the plan?

Corrective action

71
New cards

Which type of change request is intended to reduce the chance of future project problems?

Preventive action

72
New cards

A deliverable does not conform to requirements and needs to be fixed What type of change request is most appropriate?

Defect repair

73
New cards

A project has EV = $60,000, PV = $75,000, and AC = $50,000 What is the schedule variance?

-15000

74
New cards

A project has EV = $80,000 and AC = $100,000 What does the CPI indicate?

The project is over budget

75
New cards

A project has EV = $90,000 and PV = $75,000 What does the SPI indicate?

The project is ahead of schedule

76
New cards

Which EVM formula calculates cost variance?

EV-AC

77
New cards

Which EVM formula calculates estimate at completion when current cost efficiency is expected to continue?

BAC / CPI

78
New cards

In EVM, which statement is true?

An index below 1 is unfavorable

79
New cards

A project manager wants to verify whether a deliverable meets requirements and identify defects Which process is most appropriate?

Control Quality

80
New cards

A project manager wants to improve process performance and prevent defects through audits and process improvement Which process is most appropriate?

Manage Quality

81
New cards

A team collects defect data in an organized form during inspection Which quality tool is being used?

Check sheet

82
New cards

A quality team wants to determine whether most defects are caused by a small number of sources Which tool should they use?

Pareto chart

83
New cards

A project manager observes seven consecutive points on one side of the mean in a control chart What does this suggest?

The process may be out of control

84
New cards

A team wants to identify the underlying reason a recurring defect occurs Which technique should be used?

Root cause analysis

85
New cards

A project manager identifies a new risk while monitoring the project What should the project manager do?

Update the risk register and analyze the risk

86
New cards

An unidentified risk occurs and the team creates an unplanned response What is this called?

Workaround

87
New cards

A project manager reviews whether contingency reserves are still adequate Which technique is being used?

Reserve analysis

88
New cards

In a predictive project, the project manager wants to evaluate whether the risk management process is effective Which activity is most appropriate?

Risk audit

89
New cards

In an adaptive project, the team wants to quickly learn from an iteration and improve the next one Which activity is most appropriate?

Retrospective

90
New cards

The buyer and seller disagree about whether a requested change is included in the contract What is this disagreement called?

Claim

91
New cards

A seller performs the contracted work while the buyer measures performance against requirements Which statement is correct?

The seller performs the contracted work and the buyer monitors seller performance

92
New cards

A contested procurement change arises What is generally the preferred first method for resolving the dispute?

Negotiation

93
New cards

A minor, non-material update is made to a contract What is this most likely called?

Administrative Change

94
New cards

A substantive change is made to contract terms What is this most likely called?

Contract modification

95
New cards

An informal change occurs because of action or inaction rather than a formal contract modification What is this called?

Constructive change

96
New cards

A project manager is conducting process audits to identify quality improvement opportunities. Which process is being performed?

Manage Quality

97
New cards

A team is testing completed software against acceptance criteria. Which process is being performed?

Control Quality

98
New cards

Which cost of quality category includes employee quality training?

Prevention Cost

99
New cards

Warranty claims resulting from product defects are examples of:

External Failure Costs

100
New cards

Which statement best describes verification?

Confirming deliverables meet specifications