Time Cost Tradeoff Analysis

0.0(0)
Studied by 0 people
call kaiCall Kai
Locked
learnLearn
examPractice Test
spaced repetitionSpaced Repetition
heart puzzleMatch
flashcardsFlashcards
GameKnowt Play
Card Sorting

1/16

flashcard set

Earn XP

Description and Tags

This set of vocabulary flashcards covers project cost structures, cash flow analysis, S-Curves, and the mechanics of time-cost tradeoff and simple compression methods in construction management.

Last updated 3:32 AM on 8/6/26
Name
Mastery
Learn
Test
Matching
Spaced
Call with Kai
Chat

No analytics yet

Send a link to your students to track their progress

17 Terms

1
New cards

Cash flow analysis

The study of the disbursement and receipt of funds involving labor, materials, equipment, subcontractors, and contract provisions.

2
New cards

S-Curve

A graphic representation of cumulative funds where the abscissa represents project duration and the ordinate represents cumulative fund flow.

3
New cards

Abscissa

The horizontal (xx) axis of an S-Curve, which represents the project duration.

4
New cards

Ordinate

The vertical (yy) axis of an S-Curve, which represents the cumulative fund flow.

5
New cards

Retainage

A portion of the contract funds held back from the contractor, typically released upon project completion.

6
New cards

Direct costs

Costs readily identified as related to putting facility components in place, such as material cost, equipment cost, and labor cost.

7
New cards

Job Overhead

Costs not specifically associated with a particular work item, incurred whether or not productive work is accomplished, including site superintendents and temporary facilities.

8
New cards

Company Overhead

Costs not associated with a specific project, such as corporate personnel, office services, group supplies, and administration.

9
New cards

Profit

The part of the return on investment or services earned by the company over its total cost.

10
New cards

Indirect Cost

The total sum of Overhead (Job + Company) and Profit.

11
New cards

All Normal schedule

The original project schedule before any adjustments are made to activity durations.

12
New cards

Least Cost schedule

The project schedule associated with the minimum total project cost.

13
New cards

Least Time schedule

The schedule achieved when all critical activities are shortened to their minimum duration.

14
New cards

All Crashed schedule

The schedule where every activity in the project is reduced to its shortest possible duration.

15
New cards

Simple Compression Method

A process of determining least cost schedules by identifying network critical paths and crashing activities with the least additional cost per day.

16
New cards

Critical activity

An activity on the critical path whose duration must be decreased to reduce the overall project duration.

17
New cards

Cost per Day (to shorten)

The additional direct cost incurred for every day an activity's duration is reduced (crashed), calculated as the difference between crash cost and normal cost divided by the days shortened.