How is Initial Site Assessment important to site planning and equipment?
CM’s must consider the Topography, soil conditions, environmental considerations, access points, and contextual concerns
How is Zoning and functional zones important to site planning and equipment?
CM’s must analyze and divide the site into “Zones”
Materials storage and delivery, equipment staging, work zones and temp facilities
How is Optimal Space Utilization important to site planning and equipment?
CM’s must analyze site into zones, Create circulation and pathways for people, cars and delivery, Equipment location for both permanent and temporary equipment.
How is Access Circulation important to site planning and equipment?
CM’s must consider the gate location, traffic patterns, delivery staging. parking for employees and visitors or union vs non union workers
How is Safety and Compliance important to site planning and equipment?
CM’s must consider temp fences/ protection, site safety meetings, in-house inspections, first aid, and OSHA certifications (OSHA 10, 30 and Hazmat)
What does OSHA stand for?
Occupational Safety and Health Administration
How is Material Management important to site planning and equipment?
CM’s must consider the materials and bulk sizing they come in, the stick stock, indoor/ outdoor considerations and if the length of their stay
How is Temporary Facilities important to site planning and equipment?
CM’s must analyze and divide the site into “Zones”, create circulation/ pathways, equipment location, utilities and the signage
How is Environmental Considerations important to site planning and equipment
CM’s must consider storm water runoff/ erosion control, construction entrance, demo dust activates control and blasting protection
How is Governmental Considerations important to site planning and equipment?
Cm’s must consider the department of labor and industry (Labor employment issues), Environmental protection agency, department of agriculture and the Army Corp of engineers
What does Site Planning Identify?
Identify environmental constraints and mitigation strategies on a construction site plan. These may include erosion control measures, stormwater management plans, and guidelines for protecting any sensitive areas. Proper environmental planning helps mitigate impacts on the surrounding area and ensures compliance with environmental regulations.
AIA Contract Documents are divided into ___alphanumeric series by document use or purpose. Write them out by series and purpose
A‐Series: Owner/Contractor Agreements
B‐Series: Owner/Architect Agreements
C‐Series: Other Agreements
D‐Series: Miscellaneous Documents
E‐Series: Exhibits
G‐Series: Contract Administration and Project Management Forms
What is in a Project Manual?
Front End (Boiler Plate)
IVTB
Bid Form
Instructions to Bidders
Supplemental Instructions
Non-Collusion Affidavit
Non-Tech Sections
Tech Specifications (Materials)
Divisions
What Drawings are included in Site Planning and equipment
Civil
Architectural
Mechanical
Electrical
Plumbing
Fire Protection
FF&E
Shop Drawings
Submittals
Bulletin Sketches
What type of funding is included in privately funded projects?
Owner funded, Owner PG’s (Through a bank), Bank funded
What type of funding is included in Publicly funded projects?
Public Body as owner (Federal, state municipal)
Public Body as partial/ Full funding service
Public Body as grantee
Private Owner as grantee
Issuing Bonds
What is the process of a Owner funded project?
Owner has cash
Project goes under construction
Owner owns the building
What is the process of a Owner PG’s (Bank funded) project?
Owner writes a personal guarantee
Bank gives the owner cash (Owner borrows money from bank if needed)
Project goes under construction
Bank owns the building (If money is needed
Owner owns the building once its paid off
What is the process of a Bank Funded project?
Bank supplies cash for a project
Project goes under construction
Bank owns the building
Owner pays back bank and owns the building
What is the process of a Publicly Funded project?
Municipal body has cash
Project goes under construction
Municipal body owns the building
What is the process of a Public Body an Grantee Funded project?
Entity applies for a grant
Entity receives grant through public body
Project goes under construction (owner supplements grants if more money is needed through private financing and bank funds)
Owner/Bank owns the building
Project Procurement of a Single Prime Contract Form
Who is held liable?
Owner hires a General contractor
General Contractor hires subcontractors to do the work
GC is liable for all subcontractors that he hires
Project Procurement of a Multiple Prime Contract Form
Who is held liable?
Owner hires Sub contractors
Owner is liable for all work
Project Procurement of a Multiple Prime Contract Form with CM as “Advisor”
Who is held liable?
Owner acts as multiple prime form, but the owner hires a CM to help read and write contracts
Project Procurement of a Multiple Contract form w/ CM at “Risk”
Who is held liable?
Owner hires a CM/PM
CM writes contracts with sub contractors to complete work
The CM is liable
What is the definition of Procurement
Procurement: refers to the process of acquiring materials, equipment or services needed to complete a project
On small projects, a __________ typically oversees and coordinates the procurement process. On larger projects, like commercial or public jobs, contractors often employ a procurement manager whose sole responsibility is coordinating the process.
project manager
On larger projects, like commercial or public jobs, contractors often employ a procurement manager whose sole responsibility is coordinating the process. Megaprojects may employ an _____________ with a fully integrated team dedicated to the procurement of materials and equipment.
Engineering, Procurement and Construction (EPC) Contractor
Though “purchasing” and “procurement” are sometimes used interchangeably, _____________
purchasing is actually just one step in the procurement process.
_________ technically refers to the financial transaction — exchanging money for materials.
Purchasing
___________ includes selection and purchasing, but also encompasses logistics, approval, and strategy, among many other steps.
Procurement
What are the 9 groups in Project Procurement of Materials & Labor
Design Team creates Specifications
Contractors bid project
Owner / Contractor agree to terms
Contractors solicit bids / prices from suppliers
Contractors plan procurement sequence
Design Team review submittals
Contractors finalize purchase with suppliers
Suppliers deliver materials to jobsite
Contractor work / materials pass inspection
Design Team creates Specifications
The design phase of a project sets the stage for the entire procurement process.
On most projects in the US, the spec book is ____________, making it easy for specialty contractors to reference the sections that are applicable to their scope of work and communicate material requirements to their suppliers.
organized using CSI divisions
If the owner issues an ITB or RFP to solicit bids, general contractors will need to ________ to prepare their proposal.
estimate the job
The specialty contractors will, in turn, use the project specifications to_________________
secure price quotes from their pool of material suppliers or fabricators.
After the designs are complete, the owner __________, selects the contractors and awards the contract. The GC then signs subcontracts with the specialty contractors.
compares bids
With traditional ____________, that means the majority of the procurement can’t begin until the designs are completed. With some other models, such as a design-build or construction manager at risk, the GC is involved earlier in the process and can begin procurement as soon as specifications for that portion of the job are complete.
design-bid-build projects
To reduce their own risk, contractors often seek to________
include an escalation clause in their contracts.
This type of clause stipulates that, if______ rise beyond a certain amount, the owner is responsible for the cost increase.
material prices
Cost can be the primary driver during the evaluation phase, but there are other factors that can also come into play, such as_________.
availability, quality, experience of the suppliers, or sustainability of the materials
Before purchasing begins, the GC moves to _____
the submittals process.
Once the items are selected, contractors issue _________ to their suppliers, enabling them to begin fabrication or ship standard items. Specialty contractors rarely pay for materials upfront.
purchase orders
Successful procurement requires coordination of not just material delivery schedules, _________. For example, electrical components must be on site and ready for installation when the electrical contractor arrives.
but also contractor schedules
Receiving procured materials could involve arranging for________
specialty equipment for unloading and handling
During project closeout, _________ are the last step in the procurement process. All work requires approval from the owner, designers, and government officials that all components were acquired and installed according to both project specifications and building regulations.
final inspections
Advantages of Submittals
1. Clarity is increased.
2. The construction contract is more orderly.
3. Both the contractor’s project management and the design professional’s and CM’s construction contract administration become more efficient.
4. During the design stage, design professionals may more-readily observe the omission of a necessary submittal from the list of required submittals and, conversely, can more-easily identify which submittals, if any, are unnecessary for the project.
5. During construction, project participants have greater understanding of each submittal’s purpose and, to a certain extent, when the submittal must be furnished by the contractor.
Name the types of submittals
Action Submittals
Informational Submittals
Closeout Submittals
Maintenance Materials Submittals
Action Submittals
Action Submittals are typically required prior to purchase and fabrication, and allow delivery of products to be incorporated into the permanent construction.
Each action submittal needs an express, written response from the design professional, who assigns each a disposition such as “approved,” “approved as noted,” “revise and resubmit,” and others.
Shop Drawings’ Product Data
Samples
Delegated Design Submittals
Design Specifications
Testing plans, procedures, and testing limitations
Informational Submittals
Information Submittals indicate other information about the subject work, typically in a manner that allows the design professional or other reviewer to determine whether the submittal clearly demonstrates full compliance with the contract documents.
Certificates
Delegated Design Shop Drawings
Contractor’s Test and Evaluation Reports
Supplier/Manufacturer Instructions and information
Source Quality Control Submittals
Quality control SUbmittaisl
Supplier Reports
Sustainable Design Submittals
Special Procedure Submittals
Qualification Submittals
Closeout Submittals
Closeout Submittals are, as their name implies, furnished at or near the end of the subject work to which they apply, or prior to completion of the entire construction. Whether a written response by the design professional or CMs is required is the same as discussed above for informational submittals.
Maintenance Contracts
Operations and Maintenance Data
Bonds
Warranty Documentation
Record Documentation
Sustainable Design Closeout Documentation
Software
Keys
Maintenance Materials Submittal
Maintenance Materials Submittals are documentation of the delivery to the owner or facility manager of spare parts, extra materials, and special tools required by the contract.
A specifications section’s list of required maintenance material submittals is typically the only location where the specific, required spare parts, extra materials, and tools are indicated for that section.
The, contract may require, or the contractor may request, written receipts from the owner or facility manager upon delivery of the physical items; such receipts are often the actual maintenance materials submittals furnished to the design professional or CMs.
Why are construction project meetings important?
Help ensure that all stakeholders are informed and aligned on project goals, timelines, and progress
Provide an opportunity to discuss and address issues before they become more significant problems
Facilitate collaboration and decision-making among team members and stakeholders
Provide a platform for risk identification and management
Help ensure that the project stays on track and within budget
Everyone has been to a meeting that could have been an email. In other words, a waste of time. Construction is no exception despite the critical role meetings play to level set on project planning and design, progress, and _______
construction project closeout.
What is a Preconstruction meeting?
A preconstruction meeting kicks off a project where key stakeholders review critical construction documents, meet the project team, and answer lingering questions to get everyone on the same page.
What is an Owner-Architect-Contractor (OAC) meeting?
These are regular meetings typically held by the project manager where the project progress is reviewed with the architect and owner. These often involve site visits to review project progress.
What are Site meetings and construction progress meetings?
Site meetings are typically weekly between various stakeholders completing work on the jobsite. These meetings help address project issues or blockers and improve communication across the site team.
What are Safety briefing and toolbox talks?
These meetings help reinforce safety on site. These are preventative conversations to identify and review safety hazards
What goes into a Pre-meeting Preparation?
Typically, whoever is slated to lead the meeting spends time leading up to it setting objectives, inviting essential participants, and establishing timelines and agendas. It’s their responsibility to make sure expectations are established and communicated for all meetings – whether they are virtual or in person.
If attendees understand the expectations and process for the new meeting style, they’ll be more inclined to engage and adapt to it.
What goes into Conducting a construction meeting?
The goals during the meeting include starting on time, staying on subject, encouraging participation, etc. Without a guide, though, meetings are less likely to stay on track and more likely to run over the allotted time.
Why are taking construction meeting minutes important?
Construction meeting minutes are an essential element of the process, as they create a record of what went on. While taking minutes isn’t new, it tends to get out of hand without tools to keep them on track.
People start to speak quickly, the agenda gets left behind, and the person taking the minutes gets distracted.
Why are Post-meeting follow-ups important?
After the meeting, it’s time to assign action items, review outcomes, and decisions, and send follow-up communications to stakeholders and their teams. Typically, this requires a lot of manual labor to get all the post-meeting ducks in a row. For that reason and others, having the right software on hand is best.