1/5
Also Included: NMP-ES-035-003 Hot Work Instruction & NMP-ES-035-014 Fleet Transient Combustible Controls
Name | Mastery | Learn | Test | Matching | Spaced |
---|
No study sessions yet.
Procedures covered by FPS:
B-GEN-ENG-008 Fire Equipment Functionality and Fire Protection Impairments
NMP-ES-035-003 Fleet Hot Work Instruction
NMP-ES-035-007 Fleet Fire Watch Instruction
NMP-ES-035-014 Fleet Transient Combustible Controls
Conflict with TS Personnel requirement?
FB members shall NOT be used to fill TS composition requirements
(Safe Shutdown Operator)
Hot Work Permit
Validity length?
Post-work requirement?
Permits valid for 24hrs
Fire watch for 30min after work complete
Hourly Fire Watch
Grace?
Dedication?
Notification requirements?
Once per 60 minutes ±15min, shall not exceed 75min
CAN perform concurrent duties
Notify Operations: established, turnover, secure watch
Continuous Roving Fire Watch
Time to cover ALL locations: ≤15min
MUST be in same fire area
B-GEN-ENG-008
FPS Requirements
>358,691gal (30’ or 75%) per tank
Seismic Standpipe: PCCWST aligned to FPS header >92.7%