Test 1 - PMGT 3640 - Procurement Cost & Procurement Management

0.0(0)
Studied by 0 people
call kaiCall Kai
Locked
learnLearn
examPractice Test
spaced repetitionSpaced Repetition
heart puzzleMatch
flashcardsFlashcards
GameKnowt Play
Card Sorting

1/31

flashcard set

Earn XP

Description and Tags

Vocabulary-style flashcards covering project management fundamentals, organizational structures, selection criteria, and PMI standards from Module 1.

Last updated 12:18 AM on 8/3/26
Name
Mastery
Learn
Test
Matching
Spaced
Call with Kai
Chat

No analytics yet

Send a link to your students to track their progress

32 Terms

1
New cards

Project

A temporary endeavour undertaken to create a unique product, service, or result.

2
New cards

Program

Related projects, subsidiary programs, and program activities that are managed in a coordinated manner to obtain benefits not available from managing them individually.

3
New cards

Portfolio

Projects, programs, subsidiary portfolios, and operations managed as a group to achieve strategic objectives.

4
New cards

Project Management

The application of knowledge, skills, tools, and techniques to project activities to meet project requirements.

5
New cards

Tailoring

The deliberate adaptation of approach, governance, and processes to make them more suitable for the given environment and the work at hand.

6
New cards

Value

Something of worth, importance or usefulness.

7
New cards

Digitization

The process of converting information from analog to digital computer files.

8
New cards

Digitalization

The use of digital data to simplify the way work is done; it is about the way business operations employ transformative digital technologies and information.

9
New cards

Digital Transformation

Changing the way business gets done and, in some cases, creating entirely new classes of businesses by revisiting internal systems and customer interactions.

10
New cards

PMI Talent Triangle

A triad of essential skills for project leaders consisting of technical project management, strategic and business management, and leadership.

11
New cards

Psychological Safety

A shared belief held by members of a team that the team is safe for interpersonal risk taking.

12
New cards

Servant Leadership

A leadership style that focuses on understanding and addressing the needs and development of project team members to enable the highest possible project team performance.

13
New cards

Project Performance Domain

A group of related activities that are critical for the effective delivery of project outcomes.

14
New cards

Payback Period

The time necessary to recover the cost invested in the project, calculated as: Payback Period=Cost of the ProjectAverage Annual Cash Inflows\text{Payback Period} = \frac{\text{Cost of the Project}}{\text{Average Annual Cash Inflows}}

15
New cards

Net Present Value (NPV)

The difference between the project’s current value of cash inflow and the current value of cash outflow, calculated as: NPV=Present Value (PV)Initial Investment\text{NPV} = \text{Present Value (PV)} - \text{Initial Investment}

16
New cards

Internal Rate of Return (IRR)

The interest rate at which the Net Present Value is zero; used to select projects with the best profitability.

17
New cards

Opportunity Cost

The cost that is given up when selecting another project during the selection process.

18
New cards

Multi-Weight Scoring Models

An objective technique where a committee lists relevant criteria, weighs them according to importance, and adds the weighted values to choose a project.

19
New cards

Functional Organization

The classic structure used to establish managerial hierarchy with the organization divided into traditional departments like accounting, engineering, and HR.

20
New cards

Projectized Organization

A business structure where staff members are grouped into workforces tasked with unique project objectives and project managers have a high level of authority.

21
New cards

Matrix Organization

A blend of functional and projectized structures where functional managers and project managers share authority over resources.

22
New cards

Project Charter

A document issued by the project initiator or sponsor that formally authorizes the existence of a project and provides the project manager with authority to apply organizational resources.

23
New cards

Project Management Plan

A global document that explains how project processes (scope, schedule, cost, risk, etc.) are defined, implemented, monitored, and controlled.

24
New cards

Product Scope

All required specifications defining a deliverable, usually derived from customer specifications, industry standards, or regulatory requirements.

25
New cards

Project Scope

All processes required to define, implement, monitor, control, and close project activities.

26
New cards

Work Breakdown Structure (WBS)

A hierarchical decomposition of project activities into smaller components to understand actual work at the work package level.

27
New cards

Work Package

The smallest component or lowest-level activity in a branch of the Work Breakdown Structure.

28
New cards

Scope Creep

Uncontrolled change where unapproved alterations are made to the project deliverable, often resulting in increased cost and schedule delays.

29
New cards

Salience Model

A stakeholder identification model based on three variables: Power to influence, Legitimacy of relationship, and Urgency of claim.

30
New cards

Predictive Life Cycle

A plan-driven development approach where requirements are analyzed at the beginning and the project is planned as much as possible before performing activities.

31
New cards

Adaptive Life Cycle

A development approach used when uncertainty exists, characterized by frequent requirement changes and iterative or incremental delivery.

32
New cards

Cadence

The timing and frequency of project deliveries, representing the rhythm of value creation.