Chapter 11 PERT/CPM

0.0(0)
studied byStudied by 9 people
learnLearn
examPractice Test
spaced repetitionSpaced Repetition
heart puzzleMatch
flashcardsFlashcards
Card Sorting

1/15

encourage image

There's no tags or description

Looks like no tags are added yet.

Study Analytics
Name
Mastery
Learn
Test
Matching
Spaced

No study sessions yet.

16 Terms

1
New cards

Network models such as PERT and CPM are used

to plan large, complex projects.

to schedule large, complex projects.

to monitor large, complex projects.

to control large, complex projects.

for all of the above.

for all of the above.

2
New cards

The primary difference between PERT and CPM is that

PERT uses one time estimate.

CPM has three time estimates.

PERT has three time estimates.

with CPM, it is assumed that all activities can be performed at the same time.

PERT has three time estimates.

3
New cards

The earliest start time for an activity is equal to

the largest EF of the immediate predecessors.

the smallest EF of the immediate predecessors.

the largest ES of the immediate predecessors.

the smallest ES of the immediate predecessors.

the largest EF of the immediate predecessors.

4
New cards

The latest finish time for an activity is found during the backward pass through the network. The latest finish time is equal to

the largest LF of the activities for which it is an immediate predecessor.

the smallest LF of the activities for which it is an immediate predecessor.

the largest LS of the activities for which it is an immediate predecessor.

the smallest LS of the activities for which it is an immediate predecessor.

the smallest LS of the activities for which it is an immediate predecessor.

5
New cards

When PERT is used and probabilities are found, one of the assumptions that is made is that

all activities are on the critical path.

activity times are independent.

all activities have the same variance.

the project variance is equal to the sum of the variances of all activities in the project.

all of the above.

activity times are independent.

6
New cards

In PERT, the time estimate b represents

the most optimistic time.

the most likely time.

the most pessimistic time.

the expected time.

none of the above.

the most pessimistic time.

7
New cards

In PERT, slack time equals

ES+𝑡

LS−ES

0

EF−ES

none of the above.

LS−ES

8
New cards

The standard deviation for the PERT project is approximately

the square root of the sum of the variances along the critical path.

the sum of the critical path activity standard deviations.

the square root of the sum of the variances of the project activities.

all of the above.

none of the above.

the square root of the sum of the variances along the critical path.

9
New cards

The critical path is

the shortest path in a network.

the longest path in a network.

the path with the smallest variance.

the path with the largest variance.

none of the above.

the longest path in a network.

10
New cards

If the project completion time is normally distributed and the due date for the project is greater than the expected completion time, then the probability that the project will be finished by the due date is

less than 0.50.

greater than 0.50.

equal to 0.50.

not determinable without more information.

greater than 0.50.

11
New cards

If activity A is not on the critical path, then the slack for A will equal

LF−EF

EF−ES

0

all of the above.

LF−EF

12
New cards

activities are those that will delay the entire project if they are late or delayed.

Critical path (or critical)

13
New cards

PERT stands for .

program evaluation and review technique

14
New cards

PERT can use three estimates for activity time. These three estimates are ,

optimistic, most likely, pessimistic

15
New cards

The latest start time minus the earliest start time is called the time for any activity

slack

16
New cards

The percent of project completed, value of work completed, and actual activity costs are used to projects.

monitor and control