ACI Study Guide

0.0(0)
Studied by 0 people
call kaiCall Kai
Locked
learnLearn
examPractice Test
spaced repetitionSpaced Repetition
heart puzzleMatch
flashcardsFlashcards
GameKnowt Play
Card Sorting

1/44

encourage image

There's no tags or description

Looks like no tags are added yet.

Last updated 4:24 PM on 9/23/26
Name
Mastery
Learn
Test
Matching
Spaced
Call with Kai
Chat

No analytics yet

Send a link to your students to track their progress

45 Terms

1
New cards

Collecting a representative sample of concrete to bne tested is as important as executing the methods to obtain ________.

accurate results

2
New cards

This practice covers sampling from four types of equipment, which are ________, _______, _______, and _______.

stationary mixers, paving mixers, revolving truck mixers, continuous mixers

3
New cards

The elapsed time between obtaining the first and final portions of a composite sample shall not exceed __________.

15 minutes

4
New cards

Portions of a composite sample shall be thoroughly remixed before beginning tests on the sample? True or false?

true

5
New cards

Start tests for slump, temperature, and air content within _______ after fabricating the composite sample.

5 minutes

6
New cards

Start molding specimens for strength test within ________ after fabricating the composite sample.

15 minutes

7
New cards

The concrete sample must be protected from contamination and ____________.

evaporation (moisture loss)

8
New cards

The minimum size sample for making strength test specimens is ________.

1 ft³

9
New cards

When sampling from a stationary mixer, the batch must be sampled at ________ or more regularly spaced intervals during discharge of the middle portion of the batch.

two

10
New cards

When sampling from a paving mixer, obtain samples from at least _______ different portions of the pile and combine them into composite sample for test purposes.

five

11
New cards

When sampling from a revolving truck mixer, sample the concrete by collecting ________ or more portions taken at regularly spaced intervals during discharge of the middle protion of the batch.

two

12
New cards

Concrete samples from a truck mixer must obtained before any water or admixtures are added to the mixer at the job site.

false

13
New cards

When the concrete contains aggregate larger than the permitted for a particular test method, the sample of concrete must be _____________ before making the test.

wet screened

14
New cards

The stem of the thermometer is submerged a minimum of _______ into freshly mixed concrete.

3 inches

15
New cards

The thermometer shall be capable of accurately measuring the temperature of freshly mixed concrete to ______ throughout a range of ______.

+- 1 °F, 30 to 120 °F

16
New cards

The thermometer shall be verified within _____.

at least one year of its current use.

17
New cards

The temperature of concrete may be measured in a wheelbarrow. True or false?

true

18
New cards

The temperature of concrete may be measured in a wall form. True or false?

true

19
New cards

A composite sample of concrete is required even if the only purpose for obtaining the sample is to determine temperature. True or false?

false

20
New cards

What must be done to the concrete prior to sampling the concrete?

The sample container must be dampened with water prior to obtaining the sample.

21
New cards

What must be done to the concrete surrounding the thermometer after the device is submerged in the fresh concrete?

Fill the surrounding voids (if applicable) to ensure the stem of the thermometer is in full contact with the concrete.

22
New cards

How long must be the thermometer remain in the freshly mixed concrete?

2-5 minutes

23
New cards

After the temperature of the concrete is read, what is then required?

Record the temperature to the nearest 1°F.

24
New cards

The temperateure of the concrete is measured to the nearest ________.

1 degree

25
New cards

There is a specified maximum temperature of freshly mixed concrete. True or false?

false

26
New cards

The sample of concrete used for temperature determination must be rodded 25 times. True or false?

false

27
New cards

When the concrete contains aggregate larger than allowed for the slump test, the large aggregate must be ______.

wet screened over 1-1/2 in. [37.5 mm] sieve

28
New cards

The mold for making the slump test is in the shape of ______.

the frustum of a cone

29
New cards

The height of the slump mold is _____.

12 inches

30
New cards

The interior surface of the slump mold is allowed to have minor irregularities. True or false?

False

31
New cards

For use in the slump test, the tamping end or both ends of the tamping rod must be _______.

hemispherical

32
New cards

The slump mold should be in a dry condition before beginning the test. True or false?

False

33
New cards

The surface on which the slump mold will be placed must be ______.

flat, level, damp, nonabsorbent, and rigid

34
New cards

The slump mold is filled in ______ layers.

3

35
New cards

Each layer should fill approximately _______ the volume of the mold.

1/3

36
New cards

Rod each layer __ times uniformly over the cross section with the round end of the rod.

25

37
New cards

How deep should the tamping rod penetrate into each layer?

Throughout the current layer and 1 inch into the previous layer

38
New cards

What must be done if the concrete drops below the top of the slump mold while the top layer is being molded?

Additional concrete should be added to maintain excess concrete above the mold.

39
New cards

Prior to lifting the mold, concrete must be removed from ______.

the area surrounding the base of the mold

40
New cards

After the final rodding, the sides of the slump mold should be tapped lightly with the tamping rod. True or false?

False

41
New cards

When raising the slump mold, it should not be rotated or twisted. True or false?

True

42
New cards

How much time is allowed for lifting the slump mold?

5 +- 2 seconds

43
New cards

The measurement for slump is made from the top of the mold to what point of the concrete specimen?

The displaced original center of the top surface of the specimen.

44
New cards

The slump of concrete is measured and reported to the nearest ______.

¼ inch

45
New cards

How much time is allowed to conduct the slump test from beginning to completion?

2.5 minutes