Schedule Management

0.0(0)
studied byStudied by 0 people
learnLearn
examPractice Test
spaced repetitionSpaced Repetition
heart puzzleMatch
flashcardsFlashcards
Card Sorting

1/31

flashcard set

Earn XP

Description and Tags

Schedule/Time Managment (PMP)

Study Analytics
Name
Mastery
Learn
Test
Matching
Spaced

No study sessions yet.

32 Terms

1
New cards

Schedule Management

  • Process required to manage timely completion of the project.

  • This process is about creating the schedule baseline, project schedule, and ensuring the project stays on schedule.

  • 6 Processes:

    1. Plan Schedule Management (P)

    2. Define Activities (P)

    3. Sequence Activities (P)

    4. Estimate Activity Durations (P)

    5. Develo Schedule (P)

    6. Control Schedule (MC)

2
New cards

Schedule Management Plan

  • Main output of the Plan Schedule Managements

  • Documents the steps needed to conduct the other 5 processes.

    • how the project defines the activities

    • sequence the activities

    • estimates the resources

    • develop the schedule, and

    • controls the schedule

  • In addition, it states how to measure the schedule, and how to fix if there are variances from the scheduled baseline.

3
New cards

Define Activities (Planning Process)

  • Taking the work packages on the WBS and breaking them down (decomposition) into activities.

  • Specific work that needs to get done by the project team to create project deliverable.

  • More detailed than the work packages.

  • Each package has many activities.

  • Once decomposed, it can be stored into Activity List (main output).

  1. There it can be used to estimate the duration and cost of the project.

4
New cards

Decomposition

  • Breaking down work from the work packages in the WBS into specific activities.

  • Activities represent the work effort needed to accomplish the work package.

5
New cards

Rolling Wave Planning

  • Progressive Elaboration

  • Work packages happening now, will be decomposed into activity list.

    • Work packages happening later, will be decomposed later.

6
New cards

Activity List

  • List of all the scheduled activities on the project.

  • Detailed list of all the activities/work needed to complete each work package

  • Activity should include the identifier to identify each activity.

7
New cards

Activity Attributes

  • More detailed information about each activity.

  • It includes

    • resources needed to complete

    • location of the activity

    • cost

    • assumptions,

    • constraints

    • leads and lags

    • relationship to other activities

8
New cards

Milestone List

  • List of all the project or phase milestones.

  • Major accomplishment or event

  • Has no duration

9
New cards

Sequence Activities

  • Process where you take the list of activities and put them in order.

  • Main out put of this process is

    • Project Network Schedule Diagram (shows the order in which you will do each individual activity)

  • This process - shows relationships between each activity

    • Relationship or dependencies

10
New cards

Precedence Diagramming Method (PDM)

  • A technique that is build a sequence using the activities.

  • With this technique, can create the network diagram

    • PDM is a type of network diagram

  • One method of doing PDM is to use a Activity-On-Node (AON) precedence diagram.

  • Activities are related to each other using four different relationships.

    • Finish to start - most frequently used.

    • Finish to finish - activities finished simultaneously. Not necessarily start at the same time. B can finish, if A is Finished

    • Start to Start - A must start, so B can start

    • Start to finish - very rarely. B can not finish, until A has started

11
New cards

Dependencies Determination

  • Mandatory Dependencies= Hard logic. Have to finish certain activity before you start the next

  • Discretionary Dependencies = Soft Logic. Activities do not need to get done in certain order

  • External Dependencies = outside of project team control. Permit.

  • Internal Dependencies = dependent on activities within the control of the project team

12
New cards

Leads and Lags

Leads = Overlap

Lags = Delay

13
New cards

Project Schedule Network Diagram

  • Diagram shows all the activities and the order in which they are performed

14
New cards

Estimate Activity Duration

  • In this process you measure how long each activity will take to accomplish

  • 4 Estimation TT

    • Analogues

    • Parametric

    • PERT/ 3 Point Estimation

    • Bottoms Up

15
New cards

Analogous Estimating

  • Analogous Estimating = Top-Down Estimating

  • Relies on Historical information to assign current duration

  • Estimates based on limited information

  • Less accurate than other estimation techniques

16
New cards

Parametric Estimation

  • Uses mathematical algorithm to calculate cost

  • Calculation based on historical data and variables.

  • Can be accurate if the assumptions are correct

17
New cards

Three-Point Estimating/PERT- BeST

  • PERT = Program Evaluation and Review Technique

  • Uses 3 values to calculate duration or cost

    • Optimistic= Best case for the activity, less time

    • Most Likely (Realistic) = likely to be completed, between optimistic and pessimistic

    • Pessimistic= worst case, longest time to complete

  • BeST

    • Beta Distribution = (O+RX4+P)/6. Normal PERT formula. Places weight on realistic estimates

    • Standard Distribution = (P-O)/6 = Range

    • Triangular Distribution = (O+R+P)/3= Average

18
New cards

Bottoms Up Estimating

  • Very accurate

  • Takes longer to complete

  • Breaking down the work into lowest level and then aggregating all the way up for the estimation

19
New cards

Reserve Analysis (Data Analysis)

  • Adding an extra time to an activity just in case if a risk arises.

  • Two types of reserves:

    • Contingency Reserves (Known unknown)

      • Included in the cost baseline

      • Within the control of the PM

    • Management Reserves (Unknown unknown)

      • Included by the Org/mgmt

      • Not included in the project cost baseline

      • Project will need approval to access these funds

20
New cards

Duration Estimates

  • Main output for Estimate Duration Activities

  • Duration Estimates for individual activities

  • Good to add range, like Plus Minus 3 days

21
New cards

Basis of Estimates

  • Shows how the estimates were developed

  • Captures - assumptions, constraints were considered while estimating

22
New cards

Develop Schedule

  • Process to create Project Schedule and Schedule Baseline

23
New cards

Critical Path Method

  • Longest path through a network diagram

  • Any delays on the critical path activities will delay the project.

  • Activities on critical path have no float/ slack.

    • Flot = refers to the amount of time a task can be delayed without impacting the project's overall completion date or the start of subsequent tasks

  • If there are two Critical paths, it increases risk on the project

  1. Early Start = Earliest start date, w/o delaying the project end date

  2. Late Start = latest start date, w/o delaying the project end date

  3. Early Finish = earliest finish date, w/o delaying the project end date

  4. Late Finish = latest finish date, w/o delaying the project end date

  • Slack= LF-EF or LS-ES

  • Forward Pass = It needs to be done first before the backward pass. Forward pass will find the EF and EF. On the convergence pass, use the highest number

  • Backward Pass = On the convergence pass, use the lowest number

24
New cards

Resource Optimization Technique

  • Resource Levelling:

    • Resources are over allocated

    • Rather than doing the activities simultaneously, extend the activities duration (start activities sequentially)

    • Extend the project schedule. Can extend the critical path

  • Resource Smoothing:

    • Time constraints. Have to finish the work in given period

    • Adjusting work, based on the available resources

    • Ensures no impact on the critical path activities.

    • Use free or total float. No slack time

25
New cards

Schedule Compression Techniques

Compressing schedule

  1. Crashing: Add more resources to complete the activity. Increases cost

  2. Fast-Tracking: Parallel activities (rather than simultaneously)

    Increases risk

26
New cards

Schedule Baseline

  • Baseline with start and end dates of the project

  • Requires approved change request to make changes

27
New cards

Project Schedule

  • Includes start and end date of all the activities on the project

  • Very detailed

  • May include the milestone chart or the project schedule network diagram

    1. Bar Chart/Gantt Charts -time phased graphical display

    2. Milestone Chart

    3. Project Schedule Network Diagram- Shows sequence of activities with the duration

28
New cards

Control Schedule

  • Controlling the project work to ensure the activities complete on the schedule baseline

29
New cards

Control Schedule- TT - Data Analysis

Earned Value Analysis

Iteration Burndown chart

Performance reviews

What if scenarios

30
New cards

Ways to size work/user stories

  • T-shirt sizing

  • Planning poker

31
New cards

Tools to help track the project progress*

  1. Cumulative Flow Diagram (CFD) = amount of work getting done on the project

  2. Team Velocity: How many points a team can get done in each iteration.

    1. Can use it as an estimate for next sprint work

  3. Burn charts: tracks overall progress on the project

    1. Burn-up: Shows how much work completed

    2. Burn-down: Shows how much work is remaining

32
New cards

Lead and Cycle Time

  • Lead Time =How long does it take to go through the entire process

  • Cycle Time = How long does it take to go through the part of the process.

    • Cycle time = (work in progress) / Throughput

  • Throughout = the amount of work that can get done in particular period of time