PJM PT. 2

0.0(0)
studied byStudied by 0 people
0.0(0)
full-widthCall Kai
learnLearn
examPractice Test
spaced repetitionSpaced Repetition
heart puzzleMatch
flashcardsFlashcards
GameKnowt Play
Card Sorting

1/43

encourage image

There's no tags or description

Looks like no tags are added yet.

Study Analytics
Name
Mastery
Learn
Test
Matching
Spaced

No study sessions yet.

44 Terms

1
New cards

IPD Task:

Implementation documents

  • Finalize BIM and specifications

2
New cards

IPD Task:

Construction

  • Issue substantial completion and final completion documents

3
New cards

Essential for constructibility review:

  • Scope limitations

  • Site selection

  • Building systems

  • Local building conventions

4
New cards

Consultants considered informational consultants:

  • sustainability consultant

  • Code consultant

  • Cost estimator

  • Audio visual consultant

  • Lighting consultant

  • Acoustic consultant

AHPP chapter 10.2

5
New cards

Architect notices trades performing working unsafe manner in a project using AIA B101 agreement; how should Architect address this?

  • Informed general contractor of unsafe work conditions

  • Document situations in field report

6
New cards

During procurement phase, what are the duties Architect shall carry out per B101?

Assist with:

  • Establishing a list of prospective contractors

  • Obtaining competitive or negotiated bids

  • Confirm, confirming responsiveness of bids

  • Determining successful bid

  • Awarding contract

  • Preparing contract for construction

7
New cards

Typical elements of a pre-project collection of corporate knowledge:

  • Graphics

  • Typologies

  • Technologies

  • Morphologies

  • Space standards

AHPP chapter 12.2 page 824

8
New cards

Typical components of effective initial work plan:

  • Internal project budget

  • Project description and client requirements

  • Preliminary staffing needs

  • Profit plan

AHPP chapter 10.1

9
New cards

Main goal of process based systems:

  • Minimizing variation and human intervention

AHPP chapter 12.1 page 813

10
New cards

Variations of design bid build:

  • negotiated team select

    • Best for quality and cost

  • Cost to fix me

    • Best for scope

11
New cards

How long specifications are developed in what phase?

  • design development

12
New cards

Types of cost estimating:

Assemblies

  • More precise than order of magnitude; possible after early detailed information about project is defined during the design development

13
New cards

Types of cost estimating:

Unit price

  • Requires more/creator level of detail that is not defined by the signed development

14
New cards

Types of cost estimating:

Order of magnitude

Ballpark estimate of cost of project; using the early stages of project to determine feasibility

15
New cards

Appropriate method to ensure that elected contractor meets deadline:

  • contract provision for liquidated damages

16
New cards

Preliminary selection of major building systems and construction materials are noted at what stage/phase?

  • design development

17
New cards

Architects contracts sub consultant to help build a strategic plan invasion for a project; when in project schedule should sub consultant be first paid?

  • Schematic design

    • Road depends on scope, if I need to help schedule a plan then phase has to be early in timeline

18
New cards

How should I Architect addressing proper classification/admission on a space in early construction document phase?

  • Take corrective action to modify work plan of project

    • Architect take corrective action if Project is not performing to project work plan

    • First identify root cost of error and define path forward to resolve it prior to discussing it with owner

19
New cards

Bid Bond

  • Contractor supplies, bid bond to owner as a guarantee that they will enter contract if they are the winning bid/bidder

20
New cards

Costs (2) associated with prevention in quality management:

  • Education

  • Staff training

AHPP chapter 12.1 page 816

21
New cards

How long does Architect have to review submittals?

  • As stated in the substantial schedule provided by the contractor

    • Architect must approve submittal schedule

AIA A201 4.2.7

22
New cards

Construction change directive

  • Change in work without an agreed-upon price and schedule impact;

    • price determined by cost of labor, materials, transport, rental cost, bond, premium, and insurance change

    • Signed by owner and Architect

23
New cards

If procurement phase does not start within 90 days:

  • From completion of construction documents, owners cost of work must be adjusted due to changes in market

24
New cards

Who is responsible for damages, a subcontractor may cause:

  • General contractor

25
New cards

How consulting contractor with C401 should submit additional fee/service request proposal?

  • submit to Architect (who has contract with owner) and wait for authorization

26
New cards

Team members to use for conceptual design phase:

  • architecture

  • MEP engineers

  • Structural engineers

  • Geotechnical engineers

27
New cards

How Architect should keep Project within budget when Project phase is not performing well?

  • Use more experience staff to reduce hours for remainder of phase

    • Allow firm to reduce labor hours without sacrificing quality

28
New cards

Under IBC; signage is treated as a:

  • Trade permit

    • Excluded from Architect scope; jurisdiction approval for signage are considered separate from building.

    • Configuration of signage will rarely impact the building scope process

29
New cards

Typical construction detail is part of what phase?

  • Design development

30
New cards

Incorporating the design requirements of authority having jurisdiction is implemented at what stage?

  • construction documents

31
New cards

Contractor must pay and provide for:

  • Labor, materials, equipment, tools, water, heat, utilities, transport, facilities, and services

    • Texas also paid by general contractor

    • General contractor also secures and pays for building permit and other permits required by government agencies

32
New cards

If lowest bid is above the cost of work:

  • Architect must provide budget reconciliation services and no cost to owner, unless budget overage is due to market conditions

33
New cards

Doesn’t impact schedule or cost that can be ordered by Architect:

  • minor changes

    • General contractor must contact Architect before proceeding with any minor changes to the work

34
New cards

Architect checks submittals for:

  • Conformance to construction documents

    • architect no responsible for checking dimensions, quantities or methods

35
New cards

If parties don’t agree on E203, who is at risk?

  • They using party’s sole risk

36
New cards

Architect sees unsafe work conditions; how should he proceed?

  • Document unsafe working conditions in a memo to contractor and copy owner

37
New cards

Which phases have client review and approval activity?

  • Schematic design

  • Design development

  • Construction documents

38
New cards

RFI to consultants:

  • Receive RFI from contractor

  • Forward to consultant

  • Draft RFI response that incorporates consultants response/recommendations

39
New cards

Architect compensation per B101:

  • stipulating sum

  • Percentage basis

40
New cards

Factors to considering when a selecting consultants for a project:

  • firm size

  • Previous working relationship

  • Project expertise

  • Design process

AHPP chapter 10.2 page 606 - 609

41
New cards

Construction type overview:

Type IA

  • Fire resistance rating 2 to 3 hours

    • Highest level of fire resistance, noncombustible materials

    • Good for high-rise buildings

42
New cards

Construction type overview:

Type IB

  • slightly reduce fire resistance: 1 - 2 hours

    • Non-combustible materials

43
New cards

Construction type overview:

Type IIA

  • reduced fire resistance, compared to type I

    • Typically 1 hour

44
New cards

Construction type overview:

Type IV

  • Heavy timber construction; large mass timber elements; not used for high rises due to low fire resistance levels