Baseline project budgets are derived from time-phasing the work ________.
milestones
packages
products
resources
modules
packages
In monitoring project time (schedule) performance, actual performance should be compared to
previous status reports.
top management's targets.
project network schedule derived from the WBS/OBS.
budgets for the current year.
progress on similar past projects.
project network schedule derived from the WBS/OBS.
The first step in the project control process for measuring and evaluating project performance is to
determine the project deliverables.
determine the project objectives.
set a baseline plan.
review the project priority matrix.
analyze the project budget.
set a baseline plan.
A tool used to monitor past project schedule performance and current performance, and to estimate future schedule trends is a simple line chart known as a
PERT chart.
project control chart.
milestone chart.
Gantt chart.
network diagram.
project control chart.
Because of their easy-to-understand visual format, ________ charts are the most favored, used, and understandable tool used to report project schedule status.
Gantt
Cost/schedule
Network
Work breakdown structure
Burndown
Gantt
Which of the following methods of variance analysis is the best indicator of how far off the budget a project will be at completion?
EAC
VAC
TCPI
ETC
BAC
VAC
The value that tells you the planned value of work that has actually been completed is the
CV.
PV.
AC.
SV.
EV.
EV.
When someone familiar with each task estimates what percent of the task has been completed or how much of the task remains, they are creating a method for assigning costs to the baseline called the ____________ rule.
percent complete
estimation
estimated cost
estimation method
estimated completion
percent complete
A negative CV indicates the project is currently ________ budget.
over
ahead of
behind
on track with
under
over
A negative cost variance combined with a negative schedule variance is an indicator of
planned value exceeding earned value.
budget over-runs.
actual cost exceeding earned value.
All of these alternatives are correct.
behind schedule.
All of these alternatives are correct.
Given an EAC of $10,000 and a BAC of $15,000, the project is expected to be completed _________.
under budget
on budget
under budget but behind schedule
over budget but ahead of schedule
over budget
under budget
Which performance index is the most potentially misleading?
EV
CV
EAC
CPI
SV
SV
Given that the AC = 500, PV = 400 and EV = 300, this project is currently _________ budget and ______ schedule.
over, ahead of
under, behind
on, on
under, ahead of
over, behind
over, behind
A CPI index of 1.18 indicates that the project is currently ________ schedule.
behind
cannot be determined.
ahead of
over
under
cannot be determined
The indicator that tells you the amount each remaining dollar must earn for the project to stay within budget is the
SPI.
TCPI.
CPI.
PCIC.
VAC.
TCPI.
The _________ index measures the project percent complete in relation to the resources that were budgeted.
EAC
PCIB
TCPI
CPI
SPI
PCIB
Which of the following is NOT true regarding scope creep?
It wears down team motivation and cohesiveness.
It is frequently unnoticed until time delays or cost overruns are observed.
It commonly occurs late in projects.
Project suppliers resent frequent changes.
Scope changes can represent significant opportunity.
It commonly occurs late in projects.
Which of the following is not one of the four steps for measuring and evaluating project performance?
setting a baseline budget
setting a baseline plan
comparing plan against actual
taking action
measuring progress and performance
setting a baseline budget
Which of the following are required to assess the current status of a project using the earned-value cost/schedule system?
PV, EV, AC
CV, SV, BAC,
TCPI, EV, and PV
BAC, EAC, and ETC
VAC,EAC, and BAC
PV, EV, AC
A project manager just received the following information on her project: PV = 300, EV = 300, AC = 200. In terms of cost at completion,
the project will currently finish under budget, assuming the project continues to perform in this way.
the project will currently finish on budget, assuming the project continues to perform in this way.
the project will currently finish behind schedule, assuming the project continues to perform in this way.
the project will currently finish over budget, assuming the project continues to perform in this way.
there is insufficient information to draw conclusions
the project will currently finish under budget, assuming the project continues to perform in this way.
The indicator that tells you the planned time-phased value of the work that is scheduled is the _______________.
none of these
schedule variance (SV)
cost variance (CV)
planned value (PV)
earned value
planned value (PV)
The ________ variance is the difference between the earned value and the actual costs for the work completed to date.
time
budget
schedule
performance
cost
cost
A project can have a negative schedule variance and still be ahead of schedule when
progress on the critical path is faster than non-critical path tasks.
all budget targets have been achieved.
earned value exceeds planned value.
None of these alternatives is correct.
actual cost exceeds earned value.
progress on the critical path is faster than non-critical path tasks.
The schedule variance for a project is calculated by:
EV-PV
AC-SV
CV-EV
PV-EV
EV-AC
EV-PV
A program financial accountant learns that a project is currently earning $1.15 for each dollar actually spent. The accountant is able to determine this by looking at the
bac
SV
SPI
EV
CPI
CPI
Which of the following methods will measure the scheduling efficiency of the work accomplished to date?
EV/PV
AC/CV
SV/CV
EV/AC
AC/SV
EV/PV
The ________ rule assumes credit is earned for having performed the work once it is completed. This rule is usually used for work packages having very short durations.
50/50
one-to-ten
0/100
one-to-one
50/100
0/100
Conditions or scope can change during execution, which, in turn, will require a change to the __________ plan to recognize the new information.
overall
project
budget
schedule
baseline
baseline
The project network schedule is derived from the _______ and it serves as the baseline to compare against actual performance.
Organization Breakdown Structure
Risk Breakdown Structure
Gantt Chart
Work Breakdown Structure
Risk Register
Work Breakdown Structure
Taking action in the four steps for measuring and evaluating project performance can only happen after _________.
setting a baseline plan.
comparing plan against actual.
measuring progress and performance.
writing a progress and performance report.
setting a baseline budget.
comparing plan against actual.
The second step in the project control process for measuring and evaluating project performance is to
review spending with team members.
measure progress and performance.
review the baseline plan with top management.
analyze inputs to control system.
compare plan against actual.
measure progress and performance.
The start of a task may be moved on a tracking Gantt due to
All of these alternatives are correct.
increase in earned value.
Both an increase in earned value and a lack of an updated control chart.
a predecessor task starting late.
lack of an updated control chart.
a predecessor task starting late.
When a predecessor task starts late, any slack can be used up very quickly and could move the start of another task.
A ___________ Gantt chart is a simple and effective way to depict progress on a project.
tracking
variance
baseline
control
simple
tracking
The earned value of a project is the
percent of the original budget that has been earned by work that is completed.
the planned time-phased baseline of the value of work scheduled.
project cost to date adjusted for project scope changes.
cost incurred minus the planned cost.
total project cost to date.
percent of the original budget that has been earned by work that is completed.
________ is simply the percent complete times the original budget.
Actual cost
Cost Performance Index
Budget at Completion
Earned value
Schedule Performance Index
Earned value
A Cost/Schedule graph can be interpreted using ___________ for its vertical axis and _______ for its horizontal axis.
Earned Value; Schedule.
None of these alternatives is correct.
Dates; Actual Cost.
Dollar Amounts; Time.
Baseline; Deadline.
Dollar Amounts; Time.
Which of the following methods will measure the cost efficiency of the work accomplished to date?
EV/PV
SV/CV
AC/SV
EV/AC
AC/CV
EV/AC
A team leader tells the project manager that as of right now, $1.20 worth of work has been accomplished for each $1 worth of scheduled work. The team leader got this information from viewing the
SPI.
PCIB.
CPI.
TCPI.
SV.
SPI.
The third step in the project control process for measuring and evaluating project performance is to
analyze inputs to the control system.
measure both progress and performance.
compare the plan against actual performance.
review the baseline plan with top management.
review spending with team members.
compare the plan against actual performance.
A reason that the duration on a task may differ from an original duration on a tracking Gantt chart could be
the task has been cancelled.
a new budget cycle.
an unexpected delay.
new information on the task.
an expected delay.
new information on the task.
The chief financial officer receives the following information on a project: PV = 10,000, EV = 12,000, AC = 8,000, BAC = 20,000, EAC = 13,333. How is the project doing in terms of schedule?
There is not enough information to draw a conclusion
More work has been done than planned
The project has cost more than planned
Less work has been done than planned
The same amount of work has been done than planned
More work has been done than planned
A project manager receives the following information on his project: PV = 4,500, AC =4,000, EV = 5,000. How well is the project doing in terms of budget?
Right on budget
500 over budget
500 under budget
1,000 over budget
1,000 under budget
1,000 under budget
A CPI or SPI value less than one indicates that the project is currently
under cost or behind schedule.
over cost or behind schedule.
over cost or ahead of schedule.
under cost or ahead of schedule.
on cost or on schedule.
over cost or behind schedule.
Although it is very difficult to measure, measuring ________ performance is as important as measuring schedule and cost performance.
risk
technical
human resources
procurement
stakeholder
technical
Baseline project budgets are derived from
The total direct, direct project overhead and G&A overhead costs.
Top management directions
The organization's overall budget
Time-phasing the work packages
The earned value system
Time-phasing the work packages
A project monitoring system involves all of the following EXCEPT
Adjusting the data
Determining what data to collect
Determining how, when, and who will collect the data
Reporting current progress
Analysis of the data
Adjusting the data
The first step in the project control process for measuring and evaluating project performance is to
Determine the project deliverables
Analyze the project budget
Review the project priority matrix
Determine the project objectives
Set a baseline plan
Set a baseline plan
A _________Gantt chart is a simple and effective way to depict progress on a The value that tells you how much work has been completed in dollars of value is
Planned value
Budgeted cost of work scheduled
Earned value
Baseline plan
Q cost
Earned value
The value that tells you the planned value of work that has actually been completed is the
AC
SV
CV
PV
EV
EV
he indicator that tells you the planned time-phased value of the work that is scheduled is the .
Cost variance (CV)
Earned value (EV)
Schedule variance (SV)
Planned value (PV)
None of these alternatives is correct
Planned value (PV)
Given that the AC = 500, PV = 400 and EV = 300, this project is currently budget and schedule.
On, on
Over, behind
Over, ahead of
Under, ahead of
Under, behind
Over, behind
The _______ variance is the difference between the earned value to date and the baseline schedule.
Schedule
Budget
Performance
Time
Cost
Schedule
A negative CV indicates the project is currently ________ budget.
Under
Behind
On track with
Ahead of
Over
Over
A project manager notices that $5,560 worth of work that was scheduled to be completed at this time has not been accomplished. She knows this by looking at the
PCIB
SV
TCPI
EV
EAC
SV
Which of the following methods will measure the scheduling efficiency of the work accomplished to date?
EV/PV
EV/AC
AC/CV
SV/CV
AC/SV
EV/PV
The earned value system starts with the time-phased costs that provide the project baseline, which is called the
planned budgeted value of work scheduled.
planned budgeted value of work completed.
scheduled value of work completed.
earned value of work scheduled.
scheduled value of work scheduled.
planned budgeted value of work scheduled.
The cost variance for a project is calculated by
EV-PV
CV-EV
PV-EV
AC-SV
EV-AC
EV-AC
The ________ variance is the difference between the earned value to date and the baseline schedule.
budget
schedule
cost
performance
time
schedule
Causes for scope creep can include
All of these alternatives are correct.
newly identified features.
users want more functionality.
incorrect design assumptions.
new technology.
All of these alternatives are correct.
Of the following costs, which are NOT included in baseline?
suppliers
labor
contractors
equipment
budget reserves
budget reserves
The final step in the project control process for measuring and evaluating project performance is to
take appropriate action.
prepare a report to top management.
review spending with team members.
measure progress and performance.
follow up on corrective action.
take appropriate action.
The value that tells you how much work has been completed in dollars of value is ___________.
actual cost
budgeted cost of work scheduled
baseline plan
planned value
earned value
earned value
Which of the following is not a benefit of Earned Value Management?
A.Provides for accountability over individual portions of the overall budget for each organization unit.
B.Measures accomplishments against plan and deliverables.
C.Enables the project manager to ascertain problem paths within the project network and when the critical path is underperforming.
D.Provides a method for tracking directly to a problem work package and organization unit responsible.
E.Alerts all stakeholders to early identification of problems and allows for quick, proactive corrective action.
C. Enables the project manager to ascertain problem paths within the project network and when the critical path is underperforming.