Which Control Parameter for MRP defines the scope?
Schedule Lines
MRP List
Purchase Requisitions
Processing Key
Processing Key
Independent Requirements are created for which material type?
Finished Goods
Trading Goods
Semi-finished Goods
Raw Materials
Finished Goods
Which of the following provide available capacity for manufacturing?
Production Versions
Work Centers
Bill of Materials
Routings
Work Centers
The document that tracks the value of the goods produced from production to finished goods inventory is the ______________.
Material Ledger document
CO document
Material Document
FI Accounting document
FI Accounting document
The complete structured list of the components that make up a product or assemble is known as the _______________.
Bill of Materials
Work Centers
Routings
Production Version
Bill of Materials
Which production method did we configure in this course?
Make-to-order
Make-to-stock, Process Manufacturing
Make-to-stock, Discrete Manufacturing
Make-to-stock, Repetitive Manufacturing
Make-to-stock, Discrete Manufacturing
The description of the operations that have to be accomplished to produce a material is the ____________.
Bill of Materials
Work Centers
Production Versions
Routings
Routings
What step did we configure that tells the SAP S/4HANA system where and how to look for required materials for a production order?
Accounting View
Availability check
Work Scheduling View
Material Type
Availability check
When a Goods Receipt is posted from a production order, at what value are those materials posted to the inventory account?
Standard Cost
Statistical Moving Average Price
Moving Average Price
Standard Price
Standard Price
Material costs posted directly to a production order are an example of _____________________.
Primary Costs
Allocated Costs
Secondary Costs
Statistical Costs
Primary Costs
Which of the following is not created as a result of a MRP run?
Scheduled Line
Purchase Requisition
Planned Order
Production Order
Production Order
It is possible to produce a finished good using different techniques. Which of the following is used to define these different techniques?
Work Centers
Production Versions
Bill of Materials
Routings
Production Versions
Which Material Type does not require Work Scheduling Views?
Raw Materials
Semi-finished Goods
Finished Goods
Raw Materials
During Product Cost Planning, which master record is used on a quantity and value base to plan material costs for that product?
Material
Bill of Materials
Work Center
Routing
Bill of Materials
When a production order is created, all of the following occur, EXCEPT _______________.
Creation of Purchase Requisitions
Planned Costs
Reservations for Materials
Reservations for Capacities
Creation of Purchase Requisitions
How are materials linked to the routing?
From Automatic Account Determination
Components in the Bill of Materials are assigned to Operations in the Routing
Material Master records are directly assigned to a Routing
Operations in the Routing are assigned to Work Centers
Components in the Bill of Materials are assigned to Operations in the Routing
Which of the following results in the creation of Dependent Requirements?
Demand Management
MRP
BOM creation
Routing creation
MRP
What view(s) for the material is required to allow for the planning of raw material and finished products?
Storage Views for Materials
Purchasing Views for Materials
Accounting Views for Materials
MRP Views for the Materials
MRP Views for the Materials
During Product Cost Planning, which master record is used on a quantity and value base to plan labor costs for that product?
Bill of Materials
Routing
Work Center
Material
Routing
During the manufacturing execution process, which steps results in the posting of labor costs to the production order?
Creating the order
Releasing the order
Confirmation
Goods Issue
Confirmation