Phase II Homebuilding Sequence & Trades

0.0(0)
Studied by 0 people
call kaiCall Kai
Locked
learnLearn
examPractice Test
spaced repetitionSpaced Repetition
heart puzzleMatch
flashcardsFlashcards
GameKnowt Play
Card Sorting

1/26

flashcard set

Earn XP

Description and Tags

Sheetrock-Warranty

Last updated 6:21 PM on 9/16/26
Name
Mastery
Learn
Test
Matching
Spaced
Call with Kai
Chat

No analytics yet

Send a link to your students to track their progress

27 Terms

1
New cards

Sheetrock

(Estimated)

Step: 1

Trade: Drywall Hangers

Materials You'll Order: Drywall sheets, screws, corner bead

What Happens: Hangers cut and screw drywall panels onto studs/ceiling joists over the completed framing and MEP rough-in.

2
New cards

Tape and Float

(Estimated)

Step: 2—after drywall is hung (sheetrock)

Trade: Drywall finishers/tapers

Materials You'll Order: Joint compound (mud), paper or mesh tape

What Happens: Finishers tape and mud every seam/corner in multiple coats, sanding between each, to create a seamless surface.

3
New cards

Texture

(Estimated)

Step: 3—comes after tape and float

Trade: texture crew, often same as drywall company

Materials You'll Order: Sprayable texture mud, sometimes bundled primer

What Happens: Crew sprays and knocks down texture across walls/ceilings to hide imperfections and match the builder standard.

4
New cards

Interior Paint (Prime and 1st Coat)

(Estimated)

Step: 4—comes after texture

Trade: Painters

Materials You'll Order: Primer, wall paint (eggshell/flat), ceiling flat white

What Happens: Painters prime and apply early coats to walls/ceilings before trim goes in, so trim doesn't get overpainted.

5
New cards

Trim/Millwork

(Estimated)

Step: 5—comes after painters

Trade: finish carpenters

Materials You'll Order: Baseboard, casing, crown, door jambs, window sills, nails/adhesive

What Happens: Carpenters install base, casing, crown, and set the door jambs throughout the house.

6
New cards

Interior Doors

(Estimated)

Step: 6—comes after/with trim/millwork

Trade: finish carpenters

Materials You'll Order: Pre-hung or slab doors, hinges, knobs/levers, stops

What Happens: Slabs get hung into the jambs set during trim, and hardware is installed.

7
New cards

Cabinets

(Estimated)

Step: 7—after interior doors

Trade: cabinet installers

Materials You'll Order: Cabinet boxes, shims, fasteners, hardware

What Happens:Installers set and level upper/lower cabinets in kitchen, baths, and laundry per plan.

8
New cards

Counter Template→Countertop install

(Estimated)

Step: 8—after cabinets

Trade: stone/quartz fabricator

Materials You'll Order: Slab (selected earlier), sink cutout specs, edge profile, sealant

What Happens: Fabricator templates cabinets on-site, fabricates off-site, then returns to install the finished slab.

9
New cards

Paint Touchup/final coat

(Estimated)

Step: 9—after countertops

Trade: Painters

Materials You'll Order: Touch-up paint, caulk, filler

What Happens: Trim gets painted/caulked and nail holes filled after carpentry and cabinets are in.

10
New cards

Tile-floor tile and backsplash

(Estimated)

Step: 10—after painters touch ups/final coat

Trade: Tile setters

Materials You'll Order: Tile, thinset, grout, backer board, spacers

What Happens: Setters tile wet-area floors and backsplashes — backsplash specifically waits on countertops being set.

11
New cards

Flooring (Wood/LVP/carpet)—carpet last

(Estimated)

Step: 11—after tile and backsplash

Trade: Flooring installers

Materials You'll Order: Engineered wood/LVP, carpet + pad, transition strips

What Happens: Hard surfaces go down first; carpet goes in dead last to avoid trade damage.

12
New cards

Plumbing fixtures—faucets/toilets/sinks/tub/showers

(Estimated)

Step: 12—after flooring installers

Trade: Finish plumbers

Materials You'll Order: Faucets, toilets, sinks, tub/shower trim kits

What Happens: Plumbers install all visible fixtures and connect them to the rough-in lines.

13
New cards

Electrical finish

(Estimated)

Step:13—after plumbing fixtures

Trade: Electricians

Materials You'll Order: Switches, outlets, plates, light fixtures, fans, smoke detectors

What Happens: Electricians install devices and fixtures, then test and energize circuits.

14
New cards

HVAC finish

(Estimated)

Step:14—after electrical finish

Trade: HVAC techs

Materials You'll Order: Registers/grilles, thermostats, filters

What Happens: Techs install visible HVAC components, then balance and test the system.

15
New cards

Appliances

(Estimated)

Step:15—after HVAC finish

Trade: Appliance installers

Materials You'll Order: Range, dishwasher, microwave, fridge (if included)

What Happens: Appliances are delivered, set, and connected to gas/electric/water.

16
New cards

Garage Door

(Estimated)

Step: 16—after appliances

Trade: Garage door installers

Materials You'll Order: Door panels, opener, tracks, springs, remotes

What Happens: Crew installs the door and opener, then tests safety sensors.

17
New cards

Mirrors

(Estimated)

Step:17— after garage door

Trade: Glass/mirror installer

Materials You'll Order: Cut bathroom mirrors, mastic/clips

What Happens:Vanity mirrors are mounted with adhesive or mounting clips.

18
New cards

Shower glass

(Estimated)

Step:18—after mirrors

Trade: Glass installer

Materials You'll Order: Tempered glass panels/doors, hinges, hardware

What Happens: Shower enclosures go in after tile has fully cured.

19
New cards

Exterior Paint

(Estimated)

Step: 19—after shower glass

Trade: Exterior painters

Materials You'll Order: Primer, body/trim paint, exterior caulk

What Happens: Siding, trim, and exterior doors get primed and painted for weatherproofing. (Note: often runs parallel/earlier on Perry's actual schedule — confirm with your CTS.)

20
New cards

landscaping

(Estimated)

Step: 20—after exterior paint

Trade: Landscape crew

Materials You'll Order: Sod, plants, mulch, irrigation heads, topsoil

What Happens: Crew grades the yard and installs irrigation, sod, and plantings.

21
New cards

fencing

(Estimated)

Step: 21—after landscaping

Trade: Fence installers

Materials You'll Order: Fence panels/posts, concrete, gates

What Happens: Posts are set and fencing/gates installed per the plat/HOA plan.

22
New cards

Final Construction/trade touch ups

(Estimated)

Step: 22—after fencing

Trade: Super coordinating multiple trades

Materials You'll Order: Misc. caulk, paint, hardware

What Happens: Super sends trades back through to finish leftover items before formal punch.

23
New cards

Punch list

(Estimated)

Step: 23—after final construction touchups

Trade: Super/QA + trades as needed

Materials You'll Order: Whatever each item requires

What Happens: Home is walked, every defect is logged, and trades are dispatched to fix each one.

24
New cards

Final clean

(Estimated)

Step: 24

Trade: Final clean crew

Materials You'll Order: Cleaning supplies, window cleaner

What Happens: Crew deep-cleans the entire home to move-in condition.

25
New cards

Final Inspections

(Estimated)

Step: 25

Trade: City inspector + builder QA

Materials you’ll order: N/A

What Happens: Inspector verifies code compliance for the Certificate of Occupancy.

26
New cards

Home Completion/Closing

(Estimated)

Step: 26

Trade: Sales/closing coordinator

Materials You'll Order: N/A

What Happens: Home is certified 100% complete for the homeowner's final walk and closing.

27
New cards

Warranty Period

(Estimated)

Step: 27

Trade: Builder's warranty/service techs

Materials You'll Order: Whatever the repair needs

What Happens: Warranty team resolves homeowner-reported issues during the contractual warranty period.