1/26
Sheetrock-Warranty
Name | Mastery | Learn | Test | Matching | Spaced | Call with Kai | Chat |
|---|
No analytics yet
Send a link to your students to track their progress
Sheetrock
(Estimated)
Step: 1
Trade: Drywall Hangers
Materials You'll Order: Drywall sheets, screws, corner bead
What Happens: Hangers cut and screw drywall panels onto studs/ceiling joists over the completed framing and MEP rough-in.
Tape and Float
(Estimated)
Step: 2—after drywall is hung (sheetrock)
Trade: Drywall finishers/tapers
Materials You'll Order: Joint compound (mud), paper or mesh tape
What Happens: Finishers tape and mud every seam/corner in multiple coats, sanding between each, to create a seamless surface.
Texture
(Estimated)
Step: 3—comes after tape and float
Trade: texture crew, often same as drywall company
Materials You'll Order: Sprayable texture mud, sometimes bundled primer
What Happens: Crew sprays and knocks down texture across walls/ceilings to hide imperfections and match the builder standard.
Interior Paint (Prime and 1st Coat)
(Estimated)
Step: 4—comes after texture
Trade: Painters
Materials You'll Order: Primer, wall paint (eggshell/flat), ceiling flat white
What Happens: Painters prime and apply early coats to walls/ceilings before trim goes in, so trim doesn't get overpainted.
Trim/Millwork
(Estimated)
Step: 5—comes after painters
Trade: finish carpenters
Materials You'll Order: Baseboard, casing, crown, door jambs, window sills, nails/adhesive
What Happens: Carpenters install base, casing, crown, and set the door jambs throughout the house.
Interior Doors
(Estimated)
Step: 6—comes after/with trim/millwork
Trade: finish carpenters
Materials You'll Order: Pre-hung or slab doors, hinges, knobs/levers, stops
What Happens: Slabs get hung into the jambs set during trim, and hardware is installed.
Cabinets
(Estimated)
Step: 7—after interior doors
Trade: cabinet installers
Materials You'll Order: Cabinet boxes, shims, fasteners, hardware
What Happens:Installers set and level upper/lower cabinets in kitchen, baths, and laundry per plan.
Counter Template→Countertop install
(Estimated)
Step: 8—after cabinets
Trade: stone/quartz fabricator
Materials You'll Order: Slab (selected earlier), sink cutout specs, edge profile, sealant
What Happens: Fabricator templates cabinets on-site, fabricates off-site, then returns to install the finished slab.
Paint Touchup/final coat
(Estimated)
Step: 9—after countertops
Trade: Painters
Materials You'll Order: Touch-up paint, caulk, filler
What Happens: Trim gets painted/caulked and nail holes filled after carpentry and cabinets are in.
Tile-floor tile and backsplash
(Estimated)
Step: 10—after painters touch ups/final coat
Trade: Tile setters
Materials You'll Order: Tile, thinset, grout, backer board, spacers
What Happens: Setters tile wet-area floors and backsplashes — backsplash specifically waits on countertops being set.
Flooring (Wood/LVP/carpet)—carpet last
(Estimated)
Step: 11—after tile and backsplash
Trade: Flooring installers
Materials You'll Order: Engineered wood/LVP, carpet + pad, transition strips
What Happens: Hard surfaces go down first; carpet goes in dead last to avoid trade damage.
Plumbing fixtures—faucets/toilets/sinks/tub/showers
(Estimated)
Step: 12—after flooring installers
Trade: Finish plumbers
Materials You'll Order: Faucets, toilets, sinks, tub/shower trim kits
What Happens: Plumbers install all visible fixtures and connect them to the rough-in lines.
Electrical finish
(Estimated)
Step:13—after plumbing fixtures
Trade: Electricians
Materials You'll Order: Switches, outlets, plates, light fixtures, fans, smoke detectors
What Happens: Electricians install devices and fixtures, then test and energize circuits.
HVAC finish
(Estimated)
Step:14—after electrical finish
Trade: HVAC techs
Materials You'll Order: Registers/grilles, thermostats, filters
What Happens: Techs install visible HVAC components, then balance and test the system.
Appliances
(Estimated)
Step:15—after HVAC finish
Trade: Appliance installers
Materials You'll Order: Range, dishwasher, microwave, fridge (if included)
What Happens: Appliances are delivered, set, and connected to gas/electric/water.
Garage Door
(Estimated)
Step: 16—after appliances
Trade: Garage door installers
Materials You'll Order: Door panels, opener, tracks, springs, remotes
What Happens: Crew installs the door and opener, then tests safety sensors.
Mirrors
(Estimated)
Step:17— after garage door
Trade: Glass/mirror installer
Materials You'll Order: Cut bathroom mirrors, mastic/clips
What Happens:Vanity mirrors are mounted with adhesive or mounting clips.
Shower glass
(Estimated)
Step:18—after mirrors
Trade: Glass installer
Materials You'll Order: Tempered glass panels/doors, hinges, hardware
What Happens: Shower enclosures go in after tile has fully cured.
Exterior Paint
(Estimated)
Step: 19—after shower glass
Trade: Exterior painters
Materials You'll Order: Primer, body/trim paint, exterior caulk
What Happens: Siding, trim, and exterior doors get primed and painted for weatherproofing. (Note: often runs parallel/earlier on Perry's actual schedule — confirm with your CTS.)
landscaping
(Estimated)
Step: 20—after exterior paint
Trade: Landscape crew
Materials You'll Order: Sod, plants, mulch, irrigation heads, topsoil
What Happens: Crew grades the yard and installs irrigation, sod, and plantings.
fencing
(Estimated)
Step: 21—after landscaping
Trade: Fence installers
Materials You'll Order: Fence panels/posts, concrete, gates
What Happens: Posts are set and fencing/gates installed per the plat/HOA plan.
Final Construction/trade touch ups
(Estimated)
Step: 22—after fencing
Trade: Super coordinating multiple trades
Materials You'll Order: Misc. caulk, paint, hardware
What Happens: Super sends trades back through to finish leftover items before formal punch.
Punch list
(Estimated)
Step: 23—after final construction touchups
Trade: Super/QA + trades as needed
Materials You'll Order: Whatever each item requires
What Happens: Home is walked, every defect is logged, and trades are dispatched to fix each one.
Final clean
(Estimated)
Step: 24
Trade: Final clean crew
Materials You'll Order: Cleaning supplies, window cleaner
What Happens: Crew deep-cleans the entire home to move-in condition.
Final Inspections
(Estimated)
Step: 25
Trade: City inspector + builder QA
Materials you’ll order: N/A
What Happens: Inspector verifies code compliance for the Certificate of Occupancy.
Home Completion/Closing
(Estimated)
Step: 26
Trade: Sales/closing coordinator
Materials You'll Order: N/A
What Happens: Home is certified 100% complete for the homeowner's final walk and closing.
Warranty Period
(Estimated)
Step: 27
Trade: Builder's warranty/service techs
Materials You'll Order: Whatever the repair needs
What Happens: Warranty team resolves homeowner-reported issues during the contractual warranty period.