1/89
Looks like no tags are added yet.
Name | Mastery | Learn | Test | Matching | Spaced |
|---|
No study sessions yet.
The process of listing specific tasks in a sequence in which they will occur
Scheduling
Type of Schedule:
Simple and quick to produce
Easy to read and understand
Good for meetings
But does not show the interrelationships of the project
Bar Chart Schedule
Type of Schedule:
Best for repetitive work (Multiple floors)
Easily understood by non-technical people
Best used as a coordination tool in the field
But lacks detail on tasks
Matrix Schedule
Type of Schedule:
Follows the Critical Path method
Requires many resources
Shows interlationships from the project
Requires technical training to develop
Network Schedule
An activity that must be completed before another activity can take place
Predecessor
An activity that can only be completed after another activity has already taken place
Successor
Scheduling logic that involves a set of tasks that occur one after another
Sequential Logic
Scheduling logic that involves a set of tasks that occur at the same time, overlapping, thus saving time
Concurrent Logic
What are the 3 tasks/activities groups in scheduling?
1. Production Activities
2. Procurement Activities
3. Administrative Activities
Type of scheduling activity:
Directly related to the actual construction of the project on-site
Production Activities
Type of scheduling activity:
Purchasing and tracking of materials and equipment from the supplier to the site
Procuement activites
Type of scheduling activity:
Permits, inspections, approvals, and other government requirements
Administrative activities
The amount of time assigned to a specific task on the schedule
Duration
What are the phases of the 3-phase process of CPM scheduling
1. Planning
2. Scheduling
3. Monitoring and Controlling
Establishes the standard by which the project will be held up to
Baseline/Target
What is the baseline for the project cost?
Estimate
What is the baseline for the project duration/time?
Schedule
What is the baseline for the project quality
Plans and Specs
80% of the results are caused by 20% of the efforts
Pareto's Law
The process of accelerating activities to shorten the duration of the project. While leading to a decrease in indirect cost, it will lead to an increase in direct cost.
Crashing
Determines the most efficient project duration by analyzing the critical path
Minimum Cost Scheduling
How is "Units Completed" determined?
Amount of work actually done/Amount of work outlined by the schedule
How is "Incremental Milestone" determined?
Measured by how much something has been set up relative to the final product
Looking back at project cases for failures and successes, and using that to create a forecast
Trending
Provides information on the ultimate cost and completion date of a project. Includes cost to complete, cost at completion, and projected date of completion
Forecasting
Gathering and analyzing data from a project
Reporting
If you need to go to a dispute, what document do you need to refer to?
Contract
If somebody dies on the job site, how long do you have to notify OSHA?
8 hours
If somebody on the job site goes to the hospital, recieves an ampuation, or experieces loss of eyesight, how long do you have to notify OSHA?
24 hours
Instead of using the term "accident", what term does OSHA use?
Incident
Why is it critical to investigate all safety accidents, even close calls?
To identify the root cause/the why
Who determines whether or not a citation is issued after an OSHA inspection has been completed on a jobsite?
Area Director
If a citation is issued, how long does the employer have to take action?
15 days
What are the steps of the 3-phase inspection process?
1. Opening Conference
2. Walk around
3. Closing Conference
1st step of the planning process?
Review Historical Data for similar projects
2nd step of the planning process?
Review lessons learned from previous projects
3rd step of the planning process?
Review the contract for MILESTONES (Notice to proceed, completion date, etc.)
What 5 tasks must be done during planning and scheduling?
1. Review the plans and specs
2. Define specific tasks
3. Define relationships in tasks
4. Define the duration of tasks
5. Estimate required resources
Activities with zero float, which are monitored closely, since any delay on them could delay the entire schedule
Zero Float Activities
How much time can an activity be delayed without affecting the project schedule?
Float
An activity that falls on the critical path and is critical for adequate completion within the set time
Critical activity
Good project control reports show what?
Variances between the set baseline and the actual progress made
What theory is made up of the following steps:
1. Initial work plan
3. The work plan is used to initiate field operations
3. As work progresses, data is collected and compared with the baseline
4. Data is cost-engineered to provide recommendations
5. Management uses the data to adjust the plan
Basic control theory
Why should you use Minimum cost scheduling?
It determines the optimum duration for a project
How is cash flow managed on a project?
Before the project begins, a payment plan will have already been set in place for incremental payments as the project progresses.
Communicating, documenting, and keeping a permanent record of actions undertaken during the construction process. When done correctly, it tells the whole story of the project
Project Administration
A form that formalizes a request for clarification or information regarding the project, may pass through many hands before it is answered.
Request for Information (RFI)
Form used when certain information about the plans or specs is required to be submitted to the design professional for review and approval
Submittal
A record of the day-to-day activities and conditions on the job site
Daily Report
Should be action-oriented and kept for all meetings, especially ones involving job progress. Should include: Project name, project number, date of meeting, people in attendance, and a brief summary of the items discussed
Meeting Minutes
Partial payments made to the contractor from the owner as the project moves on
Progress Payment
Allows someone who provides labor or materials for a project to hold back the project's real estate if no payments are made
Lien
The trade partner gives up the right to place a lien on the project, protecting the owner by ensuring that the general contractor pays all partners and material suppliers
Lien Waiver
A change in the project scope, money, or time after the contract has already been signed. If approved, it becomes part of the contract
Change Order
Used when there is not enough time for an official change order, since there is an urgent need for a change. Allows work to proceed with temporary instructions while final scope and details from the change are determined
Construction Change Directive
Value and amounts of the work associated with the progress payments for each activity or work element
Schedule of Values
- Shop Drawings
- Product literature/data
- Product samples
- Reports from testing agencies
- O&M manuels
- Product warranty information
Types of Submittals
What is the process of reviewing and approving submittals?
Before submittals are sent to design professionals, the general contractor reviews each one to ensure it meets the plans and specs. The design professional then revises and approves or disapproves the submittal
What is the process of submitting, reviewing, and approving contractor progress payment requests
The general contractor reviews and submits a payment request, along with a schedule of values. The owner/design professional reviews the request and ensures it matches the schedule of values. If so, it is approved
1. Submit a change order form
2. Review the form for scope and pricing
3. If approved, the change becomes part of the signed contract
Change Order Process
- Owner changed project scope
- Owner changed materials
- Unforeseen conditions
- Discovery of unknown HAZMAT on the jobsite
- Errors/Missed items on Construction Documents
Reasons for a Change Order
How do construction change directives (CCD) differ from change orders?
Construction Change Directives do not become part of the contract but instead are a set of temporary instructions, allowing work to proceed while final cost and scope details are determined. Used when time does not permit a change order
An agreement establishing rules between two or more parties, usually in written form. Must be consistent with a common set of legal principles.
Contract
1st step of creating a contract between parties, does not have to be in writing and does not to to state what it is. "I will do X for you, if you provide Y for me."
Offer
A contract can be formed unless the receiving party does this; it can be done verbally, in writing, or by conduct indicating this
Acceptance of the offer
Contract Element:
Something of value is being exchanged on both sides of the transaction, usually money, but it does not have to be necessarily so
Consideration
Contract element:
1. Must be of legal age (18) and of sound mind
2. In a corporate party, the contract must be authorized by an officer on the board of directors
Capacity
Attempts to proactively prevent disputes, fostering a culture of cooperation and open communication, so issues are addressed before they become disputes.
Partnering
Type of Dispute Resolution:
Occurs before arbitration, a neutral mediator facilitates a negotiation to help parties reach a mutual agreement. No binding result
Mediation
Type of dispute resolution:
Parties agree to have disputes heard with a final decision having a legally binding effect on parties, whether they like the result or not (Same as a judge or jury)
Arbitration
Last resort for disputes, complicated, time-consuming, expensive, and rarely results in a "real winner."
Litigation
The government develops and adopts statutes and regulations at the federal, state, and local levels
The role of government
They interpret and enforce statutes and regulations and apply common law principles to resolve disputes
Role of courts
You have an unresolved conflict with the owner on your construction project. Which document would you reference to find out how to move forward?
Contract
What are the 4 elements of a contract?
1. Offer
2. Acceptance of offer
3. Consideration
4. Capacity
Damages related to a building or structure, consisting of the actual cost of repair
Direct damages
Indirect damages caused by a breach of contract, such as lost profits, lost opportunities, and negative publicity
Consequential damages
Pre-agree daily damages payable by the contractor in cases of a contractor-caused delay. Loss of money is usually due to a lack of daily production
Liquidated Damages
Penalties given to an injured party over and above actual damages due to committed actions deemed willful, malicious, or reckless
Punitive damages
- Cost of medical transportation (Ambulance)
- Cost of the healthcare provider
- Cost of hospital
- Cost of medications
- Cost of medical equipment
Direct Costs of Accidents
- Lost productivity
- Lower morale
- Training replacements
- Increase in insurance rates
- Negative publicity
- Lost contracts
- Potential legal fees
- OSHA investigations and fines
Indirect Costs of Accidents
Used to price workers' compensation insurance premiums, acts like a credit score for safety. If less than 1, then considered safer than most, but if more than 1, then it results in higher insurance premiums and negatively impacts profitability
Experience Modification Rating (EMR)
What does OSHA stand for?
Occupational Safety and Health Administration
OSHA officer explains why OSHA is inspecting the workplace and describes the scope of the inspection. A company representative is elected
Opening Conference
OSHA officer talks privately with owners, discussing safety, injuries, PPE provided, and training provided
Walkthrough
Walkthrough findings are discussed along with possible corrective procedures and reasonable timelines for correction
Closing Conference
Why does a company's Experience Modification Rating matter
It directly impacts insurance worker compensation premiums, increasing the overall cost
3 Primary causes of accidents on a job site
1. Falls
2. Struck-By incidents
3. Electrocutions
Role of the Occupational Safety and Health Administration (OSHA)
Ensure a safe and healthy work environment by setting and enforcing safety standards, providing training, and offering assistance to employers to prevent accidents and injuries
What 3 things can be used to manage safety on the job site
Safety meetings, making sure PPE is being worn, and injury prevention measures