Who breaks down work packages into activities, identifies dependencies, estimates durations, and finds the critical path?

the Project Manager

2
New cards

What characterizes adaptive schedule planning?

Uses time-boxed iterations or continuous flow; relies on backlog refinement and team collaboration

3
New cards

what are deviation limits that trigger corrective actions in a schedule plan?

control thresholds

4
New cards

Which estimation technique uses formulas with unit rates and the quantity of work?

Parametric Estimating

5
New cards

What is the PERT estimate formula?

(O+4M+P)/6

6
New cards

what is the std deviation formula in the three point estimates?

(P-O0/6

7
New cards

What is the triangular formula in the three point estimate?

(O+M+P)/3

8
New cards

Which technique uses summing detailed estimates for each activity? (It is the most accurate but time consuming)

Bottum Up Estimating

9
New cards

What is the most common precedence relationship?

Finish to Start (FS)

10
New cards

What is the delay between two activities?

Lag

11
New cards

What is the overlap between activities

Lead?

12
New cards

What does the critical path show?

The longest path through the project with zero float; Determines minimum project duration

13
New cards

What is it called when you add resources to shorten schedule at minimal costs?

crashing

14
New cards

what is a blackout time?

a period when no changes are allowed

15
New cards

What is the average amount of work a team completes per sprint?

Velocity

16
New cards

What is the criteria an item must meet before work begins?

Definition of Ready