Who breaks down work packages into activities, identifies dependencies, estimates durations, and finds the critical path?
the Project Manager
What characterizes adaptive schedule planning?
Uses time-boxed iterations or continuous flow; relies on backlog refinement and team collaboration
what are deviation limits that trigger corrective actions in a schedule plan?
control thresholds
Which estimation technique uses formulas with unit rates and the quantity of work?
Parametric Estimating
What is the PERT estimate formula?
(O+4M+P)/6
what is the std deviation formula in the three point estimates?
(P-O0/6
What is the triangular formula in the three point estimate?
(O+M+P)/3
Which technique uses summing detailed estimates for each activity? (It is the most accurate but time consuming)
Bottum Up Estimating
What is the most common precedence relationship?
Finish to Start (FS)
What is the delay between two activities?
Lag
What is the overlap between activities
Lead?
What does the critical path show?
The longest path through the project with zero float; Determines minimum project duration
What is it called when you add resources to shorten schedule at minimal costs?
crashing
what is a blackout time?
a period when no changes are allowed
What is the average amount of work a team completes per sprint?
Velocity
What is the criteria an item must meet before work begins?
Definition of Ready