Average number of jobs in the system
Measures work-in-process inventory.
Backward scheduling
Starts with the due date for an order and works backward to determine the start date for each activity.
Capacity-constrained resources
Bottleneck caused by inefficient usage.
Due date
Time when the job is supposed to be finished.
Finite loading
Scheduling that loads work centers up to a predetermined amount of capacity.
Flow operations
Processes designed to handle high-volume, standard products.
Forward scheduling
Schedule that determines the earliest possible completion date for a job.
Gantt charts
Planning and control chart designed to graphically show workloads or to monitor job progress.
Global priority rules
Makes a priority decision based on information that includes the remaining work centers a job must pass through.
Infinite loading
Scheduling that calculates the capacity needed at work centers in the time period needed without regard to the capacity available to do the work.
Input/output control
A technique for monitoring the flow of jobs between work centers.
Internal resource constraint
A regular bottleneck.
Job flow time
Measurement of the time a job spends in the shop before it is finished.
Job lateness
Measures whether the job is done ahead of, on, or behind schedule.
Job tardiness
Measures how long after the due date the job is completed.
Johnson's rule
A technique for minimizing makespan in a two-stage, unidirectional process.
Load chart
A chart that visually shows the workload relative to the capacity at a resource.
Local priority rule
Makes a priority decision based on jobs currently at that work center.
Makespan
The amount of time it takes to finish a batch of jobs.
Market constraint
The condition that results when market demand is less than production capacity.
Nonbottlenecks
A work center with more capacity than demand.
Operation sequencing
A short-term plan of actual jobs to be run in each work center based on available capacity and priorities.
Optimized production technology (OPT)
A technique used to schedule bottleneck systems.
Policy constraint
The condition that results when a specific policy dictates the rate of production.
Priority rule
Determines the priority of jobs at a work center.
Process batch
The quantity produced at a resource before the resource is switched over to produce another product.
Progress chart
A chart that visually shows the planned schedule compared to actual performance.
Routings
Provides information about the operations to be performed, their sequence, the work centers, and the time standards.
Queues
Waiting line.
Slack
The amount of time a job can be delayed and still be finished by its due date.
Theory of constraints (TOC)
A management philosophy that extends the concepts of OPT.
Throughput
The quantity of finished goods that can be sold.
Transfer batch
The quantity of items moved at the same time from one resource to the next.