1/25
Looks like no tags are added yet.
Name | Mastery | Learn | Test | Matching | Spaced | Call with Kai |
|---|
No analytics yet
Send a link to your students to track their progress
Why do schedules matter
because delivering on time is one of the biggest challenges and main cause of problems in projects, time is the least flexible attribute but overall there is other issues like individual work styles and cultural differences that can also cause conflicts to schedule.
what is the six schedule process
Plan Schedule management
Define activities
Sequence activities
Estimate activity durations
develop schedule
control schedule
what is the project schedule model development rules when to make a schedule
determine level of accuracy
provide units of measures
controls thresholds
provide rules for performance measurement
reports formats
make process descriptions
make it informal or formal
what is an activity (task)
element of work normally found on the work breakdown structure (WBS) that has an expected duration, cost and resource requirements.
what is activity list
tabulation of activities to be included on project schedule like: activity name, identifier/number and brief description
what is activity attributes
provides more information such as predecessors, successors, logical relationships, leads and lags, resource requirements, constraints, imposed dates and assumptions related to activity.
what is milestones
a significant event that normally has no duration. a useful tool for setting schedule goals and monitoring progress and important to include early in Gantt chart, start small and frequent, then all-encompassing, then once binary (complete or incomplete) monitor the critical path.
what is sequencing activites
reviewing activities and determining dependencies
what is a dependency and the three types of dependencies
dependency: relationship of sequencing project activities/tasks
mandatory dependency: inherent work being performed on project, AKA hard logic
discretionary dependency: defined by project team; AKA soft logic and should be used with care since this limits later scheduling options
external dependency: involves relationships between projects and non-project activities.
what is a network diagram
schematic display of logical relationships among, or sequencing of, project activites
what is the arrow diagramming method (ADM)
network diagram where activities are represented by arrows, nodes/circles are starting and ending points of activities and can only show finish-to-start dependency
what is the precedence diagramming method (PDM)
network diagramming technique where boxes represent activities
what are the 4 types of task dependency
finish-to-start: relationship where from activity or predecessor must finish before to activity or successor CAN START.
start-to-start: relationship where from activity CANNOT START until to activity or successor is started
finish-to-finish: relationship where from activity must finish before to activity FINISHES
start-to-finish: relationship where from activity MUST START before to activity finishes
what are the important issues in estimating resources
how difficult it is to do specific activities on this project
what is the organization’s history in doing similar activities
are the resources avaliable?
what is the resource breakdown structure
hierarchical structure that identifies project’s resources by category and type
what is duration & effort
duration: actual amount of time worked on activity plus elapsed time
effort: number of workdays/hours required to complete task (does not equal duration)
what is the three-point estimate
optimistic (best-case)
pessimistic (worst-case)
most likely (expected scenario)
this is the basis for PERT probabilistic time estimates
what is Gantt charts
standard format for displaying project schedule information by listing project activities and their corresponding start and finish dates in a calendar format. (diamond = milestone, black bar = summary task, light bar = duration, arrow = dependency)
what is the SMART criteria for milestones
(S)pecific
(M)easurable
(A)ssignable
(R)ealistic
(T)ime-framed
what is critical path & the critical path method (CPM)
critical path: series of activities that determines earliest time when project can be completed, longest path in network diagram
CPM: network diagramming technique used to predict total project duration
what is slack/float along with its two other types
slack: amount of time activity might be delayed without delayed a succeeding activity or project finish date
total slack: amount of time activity may be delayed from early start without delaying the planned project finish date
free slack: amount of time activity can be delayed without delaying early start of any following activities
what is forward and backward pass
forward pass: through the network diagram determines early start and finish date
backwards pass: determines last start and finish dates
what are the three main techniques for shortening schedules
shortening durations of critical activities by adding more resources or changing scope
crashing activities by obtaining greatest amount of schedule compression for least incremental cost
fast tracking activities by doing them in parallel or overlapping them
what is critical chain scheduling
method of scheduling that considers limited resources when creating project schedule and includes buffers to protect project completion date
what is buffer and its two types
buffer: additional time to complete task
project buffer: additional time added before project due date
feeding buffer: additional time added before tasks on critical path
what is PERT
network analysis technique used to estimate project duration when there is high degree of uncertainty about individual activity duration estimates, this is related to three-point estimate