EST (Forward Pass)
Maximum {EFT value of all immediate predecessors}
2
New cards
EFT (Forward Pass)
EST + Activity Time
3
New cards
LFT (Backward Pass)
Minimum {LST of all immediate following activities}
4
New cards
LST (Backward Pass)
LFT - Activity Time
5
New cards
Slack
LST - EST

OR

LFT - EFT
6
New cards
a
optimistic time
7
New cards
m
most likely time
8
New cards
b
pessimistic time
9
New cards
expected activity time (t)
t = (a + 4m + b) / 6
10
New cards
variance of activity completion time
\[ (b-a) / 6 \]^2
11
New cards
standard deviation
(b-a)/6

OR sq root variance
12
New cards
Project Variance
the sum of all variances of activities on the critical path
13
New cards
Z
(target completion time - expected completion time)/ project standard deviation
14
New cards
determining project completion time for a GIVEN probability
Target completion time = Expected completion time + Z x Project standard deviation
15
New cards
value of work completed
percentage of work completed x activity budget
16
New cards
cost difference
actual cost - value of work completed
17
New cards
crash cost per period
(Crash Cost - Standard Cost)

\-------------------------------

(Standard Time - Crash Time)
18
New cards
Ti
Time at which activity i starts
19
New cards
Ci
Number of periods (weeks, in this case) by which activity i is crashed