How many days does contractor have to remediate unacceptable work by owner’s standards and what should the owner do?
contractor has 10 business days
Owner can hire another contractor to remedy the work
An allowance was provided for large format tiles for a project but ended up costing half the price; how should the contract sum be adjusted?
a credit of the left over money should be given to the owner
Building will be enclosed when:
openings have been installed
Thermal protection has been completed
Moisture protection has been completed
What is the last day the contractor can submit their question to the design team during bidding?
7 days prior to the bid date
Reasons why an architect should suggest conducting a performance mock up (PMU) ?
to pinpoint any areas of weakness as they pertain to water penetration
To ensure the safety and welfare of future occupants by checking for structural integrity
To validate the design
Architectural supplemental instructions (AIA G710) :
used by architect to send additional instructions or interpretations to the contractor that do not change the contract time or sum
Purpose of cement plaster coating on basement portion of a exterior wall:
damp proofing the basement
Contractor assumes responsibility for :
all subcontractors and suppliers
Low voltage deals with:
communications
Security
Audio
Video systems
coaxial cabling would fall under the low voltage consultant’s specifications (division 27)
Design build method streamlines :
submittals
builder and designer are under one contract which streamlines the submittal process therefore open communication to work out any issues
Facilities that will require an electrical power commissioning plan?
bank
Hospital
critical operations power systems (COPS) pertains to buildings that must maintain their ability to operate during an emergency per National Electrical Code (NEC) article 708
Information the architect should verify to ensure a design element meets quality and safety standards:
UL rating
UL rating confirms the that material was tested and deemed acceptable for use
Architect noticed precarious and unsafe conditions on site;
architect should inform superintendent immediately and the contractor along with the owner in writing
Single purpose entity documents:
C195
C196
C197
Multi party agreement:
C191
Transitional forms:
B195
A195
A295
Per SectionFormat, these are not considered submittals:
Mock up
Field sample
Responsible for signing change order in project using CM- adviser:
owner
Cm-a
Contractor
Architect
in CM-a , the CM prepares change orders and construction change directives
In project using CM-adviser; what tasks would architect and CM-a be responsible for? (4)
reviewing submittals
Reject work
Require inspections
Contract administration
G710 is:
architect’s supplemental instructions
In CM- adviser project, who would be the IDM?
architect
unless otherwise noted in contract - A232 ; 15.2
An allowance is:
an amount of money or quantity of materials identified by the bidders for work that is not completely defined in the procurement documents
A bid alternate is:
portion of the work defined in the procurement documents for which separate pricing is to be identified in bidders proposals
When would a post occupancy evaluation most likely occur?
6 months after substantial completion
should happens some time after building has been occupied
Who is responsible for signing certificate of substantial completion?
owner
Architect
Contractor
parties associated with contractors; insurance company
G714:
construction change directive
Architect discovers portion of the work for which a certificate of payment had been issued 3 weeks prior , does not conform with contract documents . What is the next course of action for architect?
the architect may nullify the certificate for payment previously issued that relates to the portion of the work
A201 section 9.5
What information should contractor submit promptly after being awarded a contract?
submittal schedule
Date of commencement of work
Time required for completion of each portion of the work
A201 section 3.10
Contracts used for Design build projects:
B143 - design builder and architect
A141 - owner and design builder
G711 :
site visit report