1/53
Looks like no tags are added yet.
Name | Mastery | Learn | Test | Matching | Spaced | Call with Kai |
|---|
No analytics yet
Send a link to your students to track their progress
Cardinal Change
a change that is substantially different than the original project
Constructive Change
an owner’s actions that require extra work to be performed that would’ve otherwise been a change order
Implied Warranty of Fitness
owner does their best to provide reasonable and accurate plans and specifications
Promissory Estoppel
one who justifiably relies on another’s promise should not suffer consequences caused by the other party failing to make good on their end
Spearin Doctrine
the owner has a responsibility to ensure plans given to the contractor are as accurate as possible, or contractor can profit through change-orders
“Time is of the Essence”
this phrase contractually punishes the contractor for late completion
Liquidated Damages
A good faith estimate of losses per diem of late completed, and must be proven even in “time is of the essence” clauses
Excusable Delay
Extreme and out of contractors control; force majeure, omission from owner, designer authorized delay, unnatural weather, infrastructure failure
Compensable Delay
A delay that results in more money to the contractor, due to actions owner/designer
Constructive Acceleration
Owner denies a change order request, leading to an accelerated schedule at the contractor’s expense
No-Damages for Delay Clause
Protects the owner from having to pay for causing delays if done in good-faith
To avoid unexpected damages resulting from delayed construction, a contractor should ensure
The contract includes a list of compensatory and incompensatory events
Course of Performance
Observed actions of both parties that can indicate their intents
Course of Dealing
Observed previous actions of party with similar language
Usage of Trade
Any widely accepted trade custom or practice
Precedence Clause
Indicate if specifications take priority over drawings; otherwise courts assume harmony
Order of Precedence
Specific language takes precedent over boilerplate, regardless of document type
Patent Ambiguity
Obvious conflict between documents that the contractor must in good faith submit an RFI to clarify
Latent Ambiguity
Conflicts only apparent in the field, and are basis for compensation
Contra Proferentem
When courts cannot reasonably solve an issue, it is levied against the party that wrote the contract
Spearin doctrine does not protect the contractor is a design was more expensive than intially anticipated, however it does
protect contractors against fault plans or a bad-faith owner
Prescriptive Specification
Conveys explicit workmanship quality and materials
Proprietary Specification
Lays out specific brands or supplier, contractor is entitled to compensation if they are impossible to obtain
An “or equal” clause must be
Approved by the designer beforehand
Testing the performance of a material or product is the
Responsibility of the contractor
Output Specifications
Convey qualitative and quantitative criteria that can be tested by the contractor
General Conditions
Boilerplate document that includes various clauses and suggestions
Failed Conditions can result in
Postponement, modification waiver, or recession, but can NEVER breach a contract
Materials Breaches
Evidenced by substantial failure perform a contract, excuses innocent party of their performance
Suspension by Owner for Cause
Stop work notice is issued when contractor repeatedly fails to perform in accordance with contractor documents
Termination by Contractor for Cause
Allows not at fault contractor to terminate when work stoppage is above 30 days for specified contract reasons, can only occur if Owner is at fault
Termination by Owner for Cause
Allows Owner to terminate when Contractor disregards law, is guilty of a material breach, or fails to pay subcontractor
Consequential Damages
Secondary costs after actual damages are incurred
Patent Defect
Ordinarily defective performance revealed in a normal inspection
Latent Defect
Significant act or omission not encountered during inspection
Warranty Work
When a contractor must correct work that did not meet implied or expressed warranty
Material breaches can no longer be claimed once
a project reaches substantial completion
At Final Completion, the contractor is
paid entire amount and retainage is released
After a Final Completion, a contractor still remains liable for
latent defects and frauds after acceptance
In California, the statutes of limitations for patent defects are
4 years after substantial completion, must have court action within 1 year of incident
In California, the statutes of limitations for latent defects are
10 years after substantial completion; however injury or death has no time-limit
Owner must notify contractor of a defect in writing within
1-year; contractor must reimburse owner’s cost
Project Neutral
Set of Construction Experts that hold regular meetings that avoid or settle disputes before they become disruptive
Mini-Trial
Non-binding dispute resolution that focuses on executives and mediator; usually with intention to settle
Summary Jury Trial
Non-binding and invention of federal courts; lawyers of each side are present and the goal is to guage strength and weakness before real litigation
Mediation
Private informal process where neutral third party helps facilitate a settlement
If mediation cannot reach a settlement that makes each side “equally unhappy”, then
Arbitration occurs, which picks one side as a clear winner
Arbitration
Binding dispute resolution where arbitrator conducts a hearing and makes a decision that courts will enforce
Litigation
A lawsuit with a court having legal jurisdiction; involves discovery, interrogation, entry to land, and general evidence gathering
Deposition
record of live testimony by someone knowledgeable about the case to establish facts
A responsive bidder must
Comply with all material requirements of a solicitation with no deviation
A responsive bidder should NOT
Insert their own clarification or substitution that can be considered material
A responsible bidder has
Necessary character, experience, performance, and financial resources necessary to do the job
Performance evaluations are recorded by the
Federal Government, which help determine bid selection