Construction Law

0.0(0)
Studied by 0 people
call kaiCall Kai
learnLearn
examPractice Test
spaced repetitionSpaced Repetition
heart puzzleMatch
flashcardsFlashcards
GameKnowt Play
Card Sorting

1/53

encourage image

There's no tags or description

Looks like no tags are added yet.

Last updated 8:51 AM on 5/25/26
Name
Mastery
Learn
Test
Matching
Spaced
Call with Kai

No analytics yet

Send a link to your students to track their progress

54 Terms

1
New cards

Cardinal Change

a change that is substantially different than the original project

2
New cards

Constructive Change

an owner’s actions that require extra work to be performed that would’ve otherwise been a change order

3
New cards

Implied Warranty of Fitness

owner does their best to provide reasonable and accurate plans and specifications

4
New cards

Promissory Estoppel

one who justifiably relies on another’s promise should not suffer consequences caused by the other party failing to make good on their end

5
New cards

Spearin Doctrine

the owner has a responsibility to ensure plans given to the contractor are as accurate as possible, or contractor can profit through change-orders

6
New cards

“Time is of the Essence”

this phrase contractually punishes the contractor for late completion

7
New cards

Liquidated Damages

A good faith estimate of losses per diem of late completed, and must be proven even in “time is of the essence” clauses

8
New cards

Excusable Delay

Extreme and out of contractors control; force majeure, omission from owner, designer authorized delay, unnatural weather, infrastructure failure

9
New cards

Compensable Delay

A delay that results in more money to the contractor, due to actions owner/designer

10
New cards

Constructive Acceleration

Owner denies a change order request, leading to an accelerated schedule at the contractor’s expense

11
New cards

No-Damages for Delay Clause

Protects the owner from having to pay for causing delays if done in good-faith

12
New cards

To avoid unexpected damages resulting from delayed construction, a contractor should ensure

The contract includes a list of compensatory and incompensatory events

13
New cards

Course of Performance

Observed actions of both parties that can indicate their intents

14
New cards

Course of Dealing

Observed previous actions of party with similar language

15
New cards

Usage of Trade

Any widely accepted trade custom or practice

16
New cards

Precedence Clause

Indicate if specifications take priority over drawings; otherwise courts assume harmony

17
New cards

Order of Precedence

Specific language takes precedent over boilerplate, regardless of document type

18
New cards

Patent Ambiguity

Obvious conflict between documents that the contractor must in good faith submit an RFI to clarify

19
New cards

Latent Ambiguity

Conflicts only apparent in the field, and are basis for compensation

20
New cards

Contra Proferentem

When courts cannot reasonably solve an issue, it is levied against the party that wrote the contract

21
New cards

Spearin doctrine does not protect the contractor is a design was more expensive than intially anticipated, however it does

protect contractors against fault plans or a bad-faith owner

22
New cards

Prescriptive Specification

Conveys explicit workmanship quality and materials

23
New cards

Proprietary Specification

Lays out specific brands or supplier, contractor is entitled to compensation if they are impossible to obtain

24
New cards

An “or equal” clause must be

Approved by the designer beforehand

25
New cards

Testing the performance of a material or product is the

Responsibility of the contractor

26
New cards

Output Specifications

Convey qualitative and quantitative criteria that can be tested by the contractor

27
New cards

General Conditions

Boilerplate document that includes various clauses and suggestions

28
New cards

Failed Conditions can result in

Postponement, modification waiver, or recession, but can NEVER breach a contract

29
New cards

Materials Breaches

Evidenced by substantial failure perform a contract, excuses innocent party of their performance

30
New cards

Suspension by Owner for Cause

Stop work notice is issued when contractor repeatedly fails to perform in accordance with contractor documents

31
New cards

Termination by Contractor for Cause

Allows not at fault contractor to terminate when work stoppage is above 30 days for specified contract reasons, can only occur if Owner is at fault

32
New cards

Termination by Owner for Cause

Allows Owner to terminate when Contractor disregards law, is guilty of a material breach, or fails to pay subcontractor

33
New cards

Consequential Damages

Secondary costs after actual damages are incurred

34
New cards

Patent Defect

Ordinarily defective performance revealed in a normal inspection

35
New cards

Latent Defect

Significant act or omission not encountered during inspection

36
New cards

Warranty Work

When a contractor must correct work that did not meet implied or expressed warranty

37
New cards

Material breaches can no longer be claimed once

a project reaches substantial completion

38
New cards

At Final Completion, the contractor is

paid entire amount and retainage is released

39
New cards

After a Final Completion, a contractor still remains liable for

latent defects and frauds after acceptance

40
New cards

In California, the statutes of limitations for patent defects are

4 years after substantial completion, must have court action within 1 year of incident

41
New cards

In California, the statutes of limitations for latent defects are

10 years after substantial completion; however injury or death has no time-limit

42
New cards

Owner must notify contractor of a defect in writing within

1-year; contractor must reimburse owner’s cost

43
New cards

Project Neutral

Set of Construction Experts that hold regular meetings that avoid or settle disputes before they become disruptive

44
New cards

Mini-Trial

Non-binding dispute resolution that focuses on executives and mediator; usually with intention to settle

45
New cards

Summary Jury Trial

Non-binding and invention of federal courts; lawyers of each side are present and the goal is to guage strength and weakness before real litigation

46
New cards

Mediation

Private informal process where neutral third party helps facilitate a settlement

47
New cards

If mediation cannot reach a settlement that makes each side “equally unhappy”, then

Arbitration occurs, which picks one side as a clear winner

48
New cards

Arbitration

Binding dispute resolution where arbitrator conducts a hearing and makes a decision that courts will enforce

49
New cards

Litigation

A lawsuit with a court having legal jurisdiction; involves discovery, interrogation, entry to land, and general evidence gathering

50
New cards

Deposition

record of live testimony by someone knowledgeable about the case to establish facts

51
New cards

A responsive bidder must

Comply with all material requirements of a solicitation with no deviation

52
New cards

A responsive bidder should NOT

Insert their own clarification or substitution that can be considered material

53
New cards

A responsible bidder has

Necessary character, experience, performance, and financial resources necessary to do the job

54
New cards

Performance evaluations are recorded by the

Federal Government, which help determine bid selection