1/181
Looks like no tags are added yet.
Name | Mastery | Learn | Test | Matching | Spaced | Call with Kai |
|---|
No analytics yet
Send a link to your students to track their progress
scope
all the work involved in creating the products of the project and the processes used to create them
deliverable
a product produced as part of a project
project scope management
the process involved in defining and controlling what work is or is not included in a project; Collecting requirements, defining scope, creating the WBS, verifying scope, controlling scope
Requirement
A condition or capability that must be met or prossessed by a system, product, service,result, or component to satisfy a contract, standard, specification, or other formal document
Requirements management plan
Describes how project requirements will be analyzed, documented, and managed
Requirements traceability matrix
The table that lists requirements, various attributes of each requirement, in the status of the requirements to ensure that all requirements are addressed
Work breakdown structure
A deliverable-oriented grouping of the work involved in the project that defines the total scope of the project
Decomposition
Subdividing project deliverables into smaller pieces
Work package
A task and have the lowest level of the WBS
Analogy approach
Using a similar project's WBS as a starting point
Top-down approach
Start with the largest items of the project and break them down into their subordinate items
Bottom-up approach
The aggregation and organization of specific tasks into summary tasks, creating higher levels of a WBS
Approaches to developing workbreakdown structures
Using guidelines, analogy approach, the top-down and bottom-up approaches, and mind mapping
WBS dictionary
The document that describes detailed information about each WBS item
Scope baseline
the approved project scope statement and its associated WBS and WBS dictionary.
Scope creep
The tendency for project scope to keep getting bigger and bigger
Scope verification
Formal acceptance of the completed project scope by the stakeholders
Variance
The difference between planned and actual performance
Prototyping
Developing a working replica of the system or some aspect of the system
Use case modeling
The process for identifying and modeling business events, who initiated them, and how the system should respond to them
Joint application design
Use is highly organized an intensive workshops to bring together project stakeholders to jointly define and design information systems
activity
an element of work, normally found on the WBS, that has an expected duration and cost, and expected resource requirements: also called a task
activity attributes
information about each activity, such as predecessors, successors, logical relationships, leads and lags, resource requirements, constraints, imposed dates, and assumptions related to the activity
activity list
a tabulation of activities to be included on a project schedule
activity-on-arrow
a network diagramming technique in which activities are represented by arrows and connected at points called nodes to illustrate the sequence of activities; also called arrow diagramming method
arrow diagramming method
a network diagramming technique in which activities are represented by arrows and connected at points called nodes to illustrate the sequence of activities; also called activity-on-arrow
backward pass
a project network diagramming technique that determines the late start and late finish dates for each activity in a similar fashion
baseline dates
the planned schedule dates for activities in a Tracking Gantt chart
buffer
additional time to complete a task, added to an estimate to account for various factors
burst
when a single node is followed by two or more activities on a network diagram
crashing
a technique for making cost and schedule trade-offs to obtain the greatest amount of schedule compression for the least incremental cost
critical chain scheduling
a method of scheduling that takes limited resources into account when creating a project schedule and includes buffers to protect the project completion date
critical path
the series of activities in a network diagram that determines the earliest completion of the project; it is the longest path through the network diagram and has the least amount of slack or float
critical path method
a project network analysis technique used to predict total project duration
dependency
the sequencing of project activities to tasks
discretionary dependencies
sequencing of project activities or tasks defined by the project team and used with care since they may limit later scheduling options
dummy activities
activities with no duration and no resources used to show a logical relationship between two activities in the arrow diagramming method of project network diagrams
duration
the actual amount of time worked on an activity plus elapsed time
early finish date
the earliest possible time an activity can finish based on project network logic
early start date
the earliest possible time an activity can start based on project network logic
effort
the number of workdays or work hours required to complete a task
external dependencies
sequencing of project activities or tasks that involve relationships between project and non-project activities
fast tracking
a schedule compression technique in which you do activities in parallel that you would normally do in sequence
feeding buffers
additional time added before tasks on the critical path that are preceded by non-critical-path tasks
finish-to-finish dependency
a relationship on a project network diagram where the "from" activity must be finished before the "to" activity can be finished
finish-to-start dependency
the relationship on a project network diagram where the "from" activity must be finished before the "to" activity can be started
float
the amount of time a project activity may be delayed without delaying a succeeding activity or the project finish date; also called slack
forward pass
a network diagramming technique that determines the early start and early finish dates for each activity
free float (free slack)
the amount of time an activity can be delayed without delaying the early start of any immediately following activities
Gantt chart
a standard format of displaying project schedule information by listing project activities and their corresponding start and finish dates in a calendar format
late finish date
the latest possible time an activity can be completed without delaying the project finish date
late start date
the latest possible time an activity may begin without delaying the project finish date
mandatory dependencies
sequencing of project activities or tasks that are inherent in the nature of the work begin done on the project
merge
when two or more nodes precede a single node on a network diagram
milestone
a significant event that normally has no duration on a project: serves as a marker to help in identifying necessary activities, setting schedule goals, and monitoring progress
multitasking
when a resource works on more than one task as a time
Murphy's Law
principle that if something can go wrong, it will
network diagram
a schematic display of the logical relationships or sequencing of project activities
node
the starting and ending point of an activity on a activity-on- arrows diagram
Parkinson's Law
principle that work expands to fill the time allotted
PERT weighted average
(optimistic time + 4*most likely time + pessimistic time)/ 6
Precedence Diagramming Method
a network diagramming technique in which boxes represent activities
probabilistic time estimates
duration estimates based on using optimistic, most likely, and pessimistic estimates of activity duration instead of using one specific or discrete estimate
Program Evaluation and Review Technique
a project network analysis technique used to estimate project duration when there is a high degree of uncertainty with the individual activity duration estimates
project buffer
additional time added before the project's due date
project time management
the process required to ensure timely completion of a project
relationship
the sequencing of project activities or tasks; also called dependency
resource breakdown structure
a hierarchical structure that identifies the project's resources by category and type
resources
people, equipment, and materials
schedule baseline
the approved planned schedule for the project
slack
the amount of time a project activity may be delayed without delaying a succeeding activity or the project finish date: also called float
slipped milestones
a milestone activity that is completed later than planned
SMART criteria
guidelines to help define milestones that are specific, measurable, assignable, realistic, and time-framed
start-to-finish dependency
a relationship on a project network diagram where the "from" activity cannot start before the "to" activity is finished
start-to-start dependency
a relationship on a project network diagram where the "from" activity cannot start before the "to" activity starts
task
an element of work, normally found on the WBS, that has an expected duration and cost, and expected resource requirements: also called an activity
Theory of Constraints
a management philosophy that states that any complex system at any point in time often has only one aspect or constraint that is limiting its ability to achieve more of its goal
three-point estimate
an estimate that includes an optimistic, most likely, and pessimistic estimate
total slack (total float)
the amount of time an activity may be delayed from its early start without delaying the planned project finish date
Tracking Gantt chart
a Gantt chart that compares planned and actual project schedule information
actual cost
the total of direct and indirect costs incurred in accomplishing work on a activity during a given period
analogous estimates
a cost estimate technique that uses the actual cost of a previous, similar project as the basis for estimating the cost of the current project, also called top-down estimates
baseline
the original project plan plus approved changes
bottom-up estimates
a cost estimating technique based on estimating individual work items and summing them to get a project total
budget at completion
the original total budget for a project
budgetary estimate
a cost estimate used to allocate money into an organization's budget
cash flow analysis
a method for determining the estimated annual costs and benefits for a project
contingency reserves
dollars included in a cost estimate to allow for future situations that may be partially planned for and are included in the project cost baseline
controlling costs
controlling changes to the project budget
cost baseline
a time-phased budget that project managers use to measure and monitor cost performance
cost management plan
a document that describes how cost variances will be managed on the project
cost performance index
the ratio of earned value to actual cost; can be used to estimate the projected cost to complete the project
cost variance
the earned value minus the actual cost
definitive estimate
a cost estimate that provides an accurate estimate of project costs
determining the budget
allocating the overall cost estimate to individual work items to establish a baseline for measuring performance
direct costs
costs that can be easily related to producing the products and services of the project
earned value
an estimate of the value of the physical work actually completed
earned value management
a project performance measurement technique that integrates scope, time, and cost data
estimate at completion
an estimate of what it will cost to complete the project based on performance to date
estimating costs
developing an approximation or estimate of the costs tof the resources needed to compete the project