6th Develop and Manage a Project Schedule

0.0(0)
Studied by 0 people
call kaiCall Kai
learnLearn
examPractice Test
spaced repetitionSpaced Repetition
heart puzzleMatch
flashcardsFlashcards
GameKnowt Play
Card Sorting

1/35

encourage image

There's no tags or description

Looks like no tags are added yet.

Last updated 4:29 PM on 6/12/26
Name
Mastery
Learn
Test
Matching
Spaced
Call with Kai

No analytics yet

Send a link to your students to track their progress

36 Terms

1
New cards

Estimating Techniques

Analogous Estimating (Quick and easy)

Parametric Estimating

Three-point Estimating

Bottom-up Estimating( Accurate but time consuming)

2
New cards

Analogous Estimating

Use historical data from a similar project

3
New cards

Parametric Estimating

An estimating technique in which an algorithm is used to calculate cost or duration based on historical data and project parameters.

4
New cards

Three-Point Estimating

Formulas using optimistic, pessimistic and most likely estimate values

5
New cards

Bottom-Up Estimating

Every single component is estimated and then totaled

6
New cards

Effort

The amount of work required to complete the activity

7
New cards

Duration

Takes into account the resources allocated to the task

8
New cards

Elapsed Time

Takes into account the amount of work which can be done each day and week

9
New cards

Contingency reserves or buffers

Building in extra time to our activity estimates in case things don't go to plan

10
New cards

Dependency Types

Mandatory

Discretionary

External

Internal

11
New cards

Mandatory

Hard logic. Roof has to go on after walls are built

12
New cards

Discretionary

Preferred logic. Plumbing first then electric

13
New cards

External

Outside teams control. Permit being issued

14
New cards

Interanl

Within teams control. Cant test it until bob has written it

15
New cards

Successor/Predecessor Activity Relationships

Finish to Start(FS)

Start to Start (SS)

Finish to Finish (FF)

Start to Finish(SF)

16
New cards

Finish to Start (FS)

The predecessor activity mist finish before the successor activity can start.

Build walls then add roof

17
New cards

Start to Start(SS)

The predecessor activity must start for the successor activity to start.

Pour concrete then level concreate

18
New cards

Finish to Finish (FF)

The predecessor activity must finish for the successor activity to finish

Installing power then build rack

19
New cards

Start to Finish(SF)

The predecessor activity must start for the successor activity to finish

Very rare

20
New cards

PERT chart

an example of PDM( Precedence Diagramming Method)

21
New cards

Precedence Diagramming Method(PDM)

a common way of visualizing project work using network diagrams.

22
New cards

The Critical Path

The sequence of tasks which take the longest to complete

23
New cards

Gantt Chart

Another way of representing the project schedule with the width of the nodes(or bars) representing the duration of the tasks

24
New cards

Resource Loading

The process of filling team members available time with project tasks

25
New cards

Resource Leveling

Make adjustments to the schedule according to resource availability

26
New cards

Resource Smoothing

Delay activities according to resource limits only with the available float

27
New cards

Float

The amount of time a task can be delayed without delaying the project

28
New cards

Critical Path

The sequence of tasks that takes the longest to complete. Zero float

29
New cards

Fast Tracking

Add some overlap to tasks on the critical path.

30
New cards

Crashing

Add more resources to the task on the critical path

31
New cards

Schedule compression

Techniques used to shorten or accelerate the schedule duration without reducing scope.

32
New cards

The Cost Baseline

The approved version of the time-phased project budget, excluding any management reserves which can be changed only through formal change control procedure, and is used as a basis for comparison to results.

33
New cards

Contingency Reserves

Money allocated in the cost baseline for known risks with active response strategies

34
New cards

Management Reserves

An amount of the project budget heled outside of the baseline reserved for unforeseen work that is with scope of the porject.

35
New cards

Story Points

Unit of measure for the estimate of the effort required to implement a product backlog item(or user story)

36
New cards

Velocity

Shows how much wok the team can complete in a sprint