Construction Methods and Project Management Final Exam

0.0(0)
Studied by 0 people
call kaiCall Kai
learnLearn
examPractice Test
spaced repetitionSpaced Repetition
heart puzzleMatch
flashcardsFlashcards
GameKnowt Play
Card Sorting

1/64

encourage image

There's no tags or description

Looks like no tags are added yet.

Last updated 5:08 AM on 6/21/26
Name
Mastery
Learn
Test
Matching
Spaced
Call with Kai

No analytics yet

Send a link to your students to track their progress

65 Terms

1
New cards

Project Schedule

Contractual network diagram of planned activities: their sequence, durations, and completion conditions

2
New cards

Job Logic

The logical production sequence in which activities must be performed

3
New cards

CPM Advantages

Instant monitoring, higher productivity, and a court-admissible delay-claim document

4
New cards

Project Conception

Pre-production planning, production planning & scheduling, and the project scheduling phase

5
New cards

S-Chart (S-Curve)

Graphical total schedule that also records progress over time

6
New cards

Gantt / Bar Chart

Simple chart relating each task to its schedule timeline

7
New cards

Long-Lead Items

Materials/equipment with long procurement times, flagged for close monitoring

8
New cards

Progress Schedule Regimentation

Setting precedence for all milestones, meetings, inspections, deliveries, and payments

9
New cards

Precon Meeting

Prebid meeting of all vested parties to settle production-scheduling details

10
New cards

Shop Drawing Log

Tracker of received/sent shop drawings, durations, and submittal dates (reviewed by PM and owner first)

11
New cards

Milestone

Benchmark marking the completion of a project phase

12
New cards

Network Diagram

Map of all production activities plus job logic that makes a schedule operable

13
New cards

Scheduling Philosophy

Selection of the scheduling system, which sets the production contracting basis

14
New cards

Workarounds

Alternative activities substituted when the critical path hits a bottleneck

15
New cards

Field Scheduling

Site-level scheduling that monitors projected vs. actual progress, critical path first

16
New cards

Proposal Scheduling

Preliminary bar-chart schedules contractors prepare (unpaid) during bidding

17
New cards

PERT

Military-origin technique estimating duration via the average of optimistic and pessimistic dates

18
New cards

CPM

Critical Path Method; late-1950s scheduling/logic tool, modernized by James Kelly (1967)

19
New cards

CPM Objectives

Schedule, Control, Organize, Implement

20
New cards

Activity

An item of work, shown as an arrow, with or without duration

21
New cards

Node / Event

The start and finish point of an activity

22
New cards

Arrow Diagram (AOA)

Network of activities/events drawn as arrows and nodes; needs dummies

23
New cards

Precedence Diagram (AON)

Activity-on-node diagram; eliminates dummies and is easy to modify

24
New cards

Time-Scale Diagram

Simple schedule-vs-time picture for management, not for detailed control

25
New cards

Restraint / Dummy

Non-time-consuming logic tie showing dependency between activities

26
New cards

Critical Path

Longest-duration chain in the network; its activities have zero float

27
New cards

Early Start (ES)

Earliest time work can begin on an activity

28
New cards

Early Finish (EF)

ES + duration

29
New cards

Late Start (LS)

Latest an activity can start without affecting project duration

30
New cards

Late Finish (LF)

Latest an activity can finish without affecting project duration

31
New cards

Forward Pass

Add durations left to right; take the LARGEST number at a merge → ES/EF

32
New cards

Backward Pass

Subtract durations right to left; take the SMALLEST value at a merge → LF/LS

33
New cards

Total Float (TF)

LS − ES (= LF − EF); delay possible without delaying the project

34
New cards

Free Float (FF)

ES(following) − EF(current); delay possible without delaying any successor

35
New cards

Time-Scaled Network

Network diagram plotted against a real time axis (based on early/late start) in bar-and-arrow form

36
New cards

Manpower Leveling

Smoothing worker/equipment counts to a stable level to cut the cost of employment fluctuation

37
New cards

Employment Fluctuation

Repeated hiring/laying off that adds cost; solved by keeping employment level

38
New cards

Program of Work (POW)

The master plan/budget document for executing a project

39
New cards

Direct Costs

Mobilization/demobilization, materials, labor, supervision (3% of labor), and equipment

40
New cards

Indirect Costs

OCM (8% of direct), contractor's profit (8% of direct), and VAT (5% of direct+OCM+profit)

41
New cards

Supervision Cost

Estimated at 3% of labor cost

42
New cards

OCM

Overhead, Contingencies & Miscellaneous; 8% of total direct cost

43
New cards

Contractor's Profit

8% of total direct cost

44
New cards

VAT

5% of (Total Direct Cost + OCM + Contractor's Profit)

45
New cards

Bill of Quantities (BOQ)

Detailed list of all work-item quantities for pricing

46
New cards

Detailed Estimate

Priced computation of all work items

47
New cards

S-Curve

Cumulative progress-versus-time curve

48
New cards

Gantt Chart

Simple task-versus-time bar chart

49
New cards

Equipment Utilization

Optional record of how equipment is used over the project

50
New cards

Cash Flow Plan

Plan of money inflows/outflows over time, drawn from economics

51
New cards

Minimum Project Contents

POW, BOQ, Detailed Estimate, PERT/CPM, Time-Scaled Network, Gantt, Manpower Leveling, S-Curve, Equipment Utilization (optional), Cash Flow, Plans & Specs

52
New cards

PERT

Program Evaluation Review Technique; handles duration uncertainty with three estimates and statistics

53
New cards

Optimistic Time (a)

Minimum time an activity will take; probability about 1%

54
New cards

Most Likely Time (m)

Normal duration most frequently required under identical conditions

55
New cards

Pessimistic Time (b)

Maximum time under the worst conditions; probability about 1%

56
New cards

Expected Time E(t)

Weighted average duration = (a + 4m + b)/6; equals the mean μ

57
New cards

Variance (σ²)

Measure of spread = (b − a)²/36

58
New cards

Standard Deviation (σ)

Square root of variance = (b − a)/6

59
New cards

Standard Normal Distribution

Normal curve with mean 0 and variance 1

60
New cards

Z-Score

Standardized value: z = (x − μ)/SD

61
New cards

Path Expected Time

Sum of the expected times of the activities on the path

62
New cards

Path Variance

Sum of the variances of the activities on the path

63
New cards

Critical Path (PERT)

Path with the greatest total expected time; controls completion probability

64
New cards

Central Limit Idea

Sum of many activity times is approximately normally distributed

65
New cards

On-Time Probability

P(z ≤ (target − μ)/SD) read from the standard normal table