What is the purpose of the B101?
defines A scope of services, compensation + responsibilities + relationship between A + O
What articles are included in B101?
Article 1 - Initial Information
Article 2 - Architect’s Responsibilities
Article 3 - Scope of Architect’s Basic Services
Article 4 - Supplemental + Additional Services
Article 5 - Owners Responsibiities
Article 6 - Cost of Work
Article 7 - Copyrights + Licenses
Article 8- Claims + Disputes
Article 9 - Termination Or Suspension
Article 10 - Miscellaneous Provisions
Article 11 - Compensation
Article 12 - Special Terms + Conditions
Article 13 - Scope of Agreement
What is Article 1 - Initial Information
outlines physical proj characteristics, O’s intent for program, budget, anticipated milestone dates, procurement + delivery method, sustainable objective
Name + contacts of O + A’s consultants, contractors, representatives
information may change, everyone must be compensated + in agreement
What is Article 2 - Architect’s Responsibilities?
A must preform services consistent to standard of care
maintain insurance until termination:
commercial general liability
automobile liability coverage
workers compensation
employer’s liability
professional liability → covers negligent acts, errors, omissions of > 2M per claim + in aggregate
certificates of insurance must be provided to O
A will require consultants to carry + maintain sufficient insurance appropriate to proj
Additional Insured: O included as additional insured for claims caused in whole/in part of A negligent acts/omissions
What is Article 3 - Scope of Architect’s Basic Services
retain consultants to produce set of construction documents → structural, mechanical, electrical, plumbing engineers
research applicable design criteria, attend proj meetings, communicate w team + report progress to O
create initial schedule w anticipated dates for commencement of construction, SC, + include allowances for periods + time for O’s + consultants reviews + approvals
submit proposals to gov for approval of construction docs + utility services for proj
assist O for filing documents required for permits + jurisdiction
attend meetings regarding: planning, facility committee, school board, public hearings as necessary/reasonably requested by O
Schematic Design Phase
Design Development Phase
Construction Documentation
Procurement Phase
Construction Administration
What is the A’s responsibilities during the Schematic Design Phase?
prepare prelim evaluation of O’s program, schedule, budget for cost of work, project site, proposed procurement + delivery method + other initial info
preliminary evaluation presented to O + discuss alternatives which O must approve
prepare schematic design documents for O approval
drawings, site plans, prelim building plans, sections, elevations, study models, perspective sketches, digital representations, prelim selections of major bldg systems + construction materials
consider sustainable design, materials, bldg systems + equipment alternatives to meet code/jurisdiction requirements
submit O estimate of Cost of work
What is the A’s responsibilities during the Design Development Phase?
describe development of approved schematic design docs to O for approval
consist of drawings, plans, sections, elevations, construction details, diagrammatic layouts of bldg system for architectural, structural, mechanical, + electrical systems
update cost of work
What is A’s responsibilities during Construction Document Phase?
prepare construction documents + project manual
includes: drawings + specifications w quality lvls + performance criteria of materials + systems
assist O w
submitting docs in O name for jurisdiction over proj
develop + prepare procurement info (time, place, conditions of bidding, proposal forms), agreement between O + CON, conditions of contract for construction (general, supplementary + other conditions)
update cost of work
What is the A’s responsibilities during the Procurement Phase?
assist O with establishing list of prospective contractors
obtaining competitive bids
confirming responsiveness of bids
evaluate bids to determine successful bid/proposal
prepare contracts for construction after award by O
will consider rq for substitutions + prepare addenda for prospective bidders
A CANNOT proceed with competitive bidding until:
A received O approval of construction docs
provided O + O representative w final estimate of cost of work within O budget unless directed to proceed outside budget
A received authorization + direction from O to proceed w competitive bidding
What is A’s responsibilities during construction phase?
provide + advise O during construction + contract between O + A
beings w award of contract for construction, terminates on date A issues final certificate of payment
visit site at intervals appropriate to become familiar w progress + quality of portion of work + keep O updated
must inform O if any deviations/defects observed in work within 10 working days
has authority to require inspection/testing of work to check if work is in accordance with contract documents
if IDM is not designated, A render initial decisions on claims between O + CON
approve CON’s certification of payment before passing bill to O → representation to best of A knowledge/info/belief of CON entitlement to payment
review CON submittal schedule within 15 working days
review + respond to RFIs within agreed upon time/reasonable promptness (3-5 days)
prepare change orders + construction change directives for O’s approval
authorize minor changes in work that are consistent w contract documents (don’t impact sum or time of proj)
project completion responsibilities:
conduct inspections (punch lists) for SC + final completion dates
issue certificates of SC
issue final payment
keep O in loop + ask for approval
What is A not responsible for?
accuracy, completeness, timeliness of services + information furnished by O + O’s consultants
O’s directive/substitutions, acceptance of non conforming work made without A’s written approval
not required to make exhaustive/continuous on site inspections to check quality/quantity of work
does not need to review copies of requisitions received from SCON + suppliers, or other data rq by O to see if CON has right to payment
does not need to know how or for what purpose CON used money previously paid on account of contract sum
rq by O, A perform observation of site w O + provide assistance w enforcing/documenting warranty issues w CON year after SC w/o additional compensation
What is Article 4 - Supplemental + Additional Services?
SUPPLEMENTAL: before contract agreed upon
prelim design phase: programming, multiple prelim designs, value analysis + detailed cost estimating beyond requirement
things to do with preexisting conditions: existing facilities survey, site evaluation + planning
BIM management responsibilities + development of BIM for post construction use
on site proj representation, conformed docs for construction
as designed record drawings + constructed record drawings
post occupancy eval
facility support services + tenant related services
A coordination of O’s consultants or specialty consultants
landscape design, civil engineering, interior design, furniture, furnish + equipment design (FF&E), sustainability proj services, data/telecommunications design, security eval + planning
commissioning
fast track design services
multiple bid packages
ADDITIONAL: proposed after agreement executed
services necessitated by change in initial info
material change, proj size, quality change, change in O schedule/budget for cost of work, procurement or delivery method
enactment of revision of codes, laws, regulations that impact prepared construction docs
editing/changing prepared instruments of services
services that are a result of O’s failure/delays in performance
extra bid proposals
public meetings
assistance to IDM
replacement of work from fire or other dmgs during construction
evaluation of qualities of contractors/other parties
construction phase services that exceed limits set in contract
reviews of shop drawings, product data item, submittals, visits to site, inspection of portion of work in accordance to contract documents or to determine final completion, observation of work
What is Owners Responsibilities?
retain consultants that deal with site → geotechnical or civil engineer
establish O objectives
budget for cost of work/other costs/reasonable contingencies related to proj, schedule, constraints + criteria, program, sustainability goal
identify representative to act on O behalf
surveys/inspections/tests/reports of preexisting site conditions + required by law/contract doc
coordinate services of own consultants w those provided by A
require consultants maintain insurance + professional liability insurance
include A in all communication between CON
What is the O not responsible for?
ensuring there are no errors/omissions/inconsistencies w A’s instruments of service