In reviewing the status of a project with top management, a team leader was told that there are only two programmers that can be used for the project. The project is classified as ________blank constrained.
Multiple Choice
time
quality
cost
performance
resource
Why is it necessary to have a time-phased budget baseline?
Multiple Choice
It allows proper resource allocation.
It shows how much work was accomplished for the money spent.
It reduces schedule slippage when scheduling multiproject resources.
It is not necessary to have a time-phased budget baseline.
It reduces fluctuations in cash flow during the project.
A test engineer is to conduct environmental testing but the chamber cannot hold all the equipment that needs to be tested. This is an example of a constraint that could impact the sequence and timing of activities in a project network. What type of constraint is it?
Multiple Choice
Physical
Technical
Resource
Scheduling
Time
Resource leveling or smoothing can have all the following results on a project EXCEPT
Multiple Choice
lower peak resource demand.
reduced resource need over the life of the project.
reduced fluctuations in resource demand.
a longer project duration.
a more sensitive network.
A project budget report is showing our project as spending $50,000 against a budgeted amount of $65,000. Which of the following is true?
Multiple Choice
We are spending less than we should for the project.
We are doing a good job managing the project.
We should check to see if all the bills have been paid.
We have more money to put into budget reserves.
We can't be sure how the project is going.
Which of the following is NOT one of the more common problems associated with scheduling multi-project resources?
Multiple Choice
Overall schedule slippage
Inefficient resource utilization
Decline in project quality
Resource bottlenecks
Delays in one project causing delays in other projects
These are all guidelines a project manager should consider when assigning project work EXCEPT
Multiple Choice
select people with compatible work habits and personalities.
always assign the best people to the most difficult tasks.
when possible, team veterans up with new hires.
select individuals with skillsets that complement each other.
have people work together early so that they can become familiar with each other.
always assign the best people to the most difficult tasks.
When a company will reduce the number of projects they have to manage internally to only core projects and send noncritical projects to contractors and consulting firms this is called
Multiple Choice
outsourcing.
redistribution of projects.
project allocation.
task sharing.
referring.
outsourcing
In a resource-constrained project, the first, or primary, priority in assigning resources is usually given to activities with the
Multiple Choice
smallest duration.
least slack.
most slack.
lowest identification number.
highest cost.
least slack
In a resource-constrained project the second priority in assigning resources is usually given to activities with the
Multiple Choice
smallest duration.
least slack.
most slack.
lowest identification number.
highest cost.
smallest duration
Project budgets are developed by time-phasing which of the following?
Multiple Choice
Resource schedules
Work packages
The network diagram
Critical activities
None of these are time-phased to develop a project budget.
Work packages
When looking at the critical path for a delayed project and the project manager sees that adding resources will reduce or remove the delay, the project manager knows that the project is:
Multiple Choice
Over Allocated.
Time-Constrained.
Institutionally Challenged.
Ahead of schedule.
Unstable.
Time-Constrained.
All resource leveling techniques involve
Multiple Choice
delaying noncritical activities.
delaying critical activities.
using negative slack.
delaying the project.
adding resources.
delaying noncritical activities.
A special truck that is needed on the project has been assigned to another project. This is an example of what type of resource constraint?
Multiple Choice
Working capital
People
Equipment
Information
Materials
Equipment
When leveling schedules to overcome resource constraints, ________blank is increased.
Multiple Choice
impact of risks
scheduling complexity
cost
amount of total slack
amount of free slack
scheduling complexity
Based on the material in the chapter, which of the following is NOT an immediate question that a project manager still should address after staff and other resources have been assigned to the project?
Multiple Choice
Will the assigned labor be adequate and available to deal with my project?
Will outside contractors have to be used?
Will scope have to be redefined/stabilized?
Do unforeseen resource dependencies exist?
How much flexibility do we have in using resources?
Will outside contractors have to be used?
Bjorn and Thor are plumbers who have been scheduled to work on the construction of a new school building. Just before the start of the project, Bjorn broke his arm and cannot work on the project. Now Thor has to handle his own activities as well as Bjorn’s. Level the project Gantt chart so that Thor is responsible for activities 3, 4, 6, and 7.
How will the project completion date be affected?

extended by 4 days
Which of the following is NOT a potential consequence of failing to identify limited resources before project implementation?
Multiple Choice
Activity delays
Project delays
Difficulty in taking quick corrective action
Increase costs
Scope creep
Scope creep
If resources are not adequate to meet peak demands, the resulting reschedule is termed
Multiple Choice
resource-constrained scheduling.
time-constrained scheduling.
mandatory leveling.
project resource adjustment.
allocation
resource-constrained scheduling.
When the work in an activity is interrupted to work on another activity and is then resumed at a later point in time, it is called ________blank.
Multiple Choice
prioritizing
preempting
overriding
splitting
All of these alternatives are correct.
splitting
In scheduling resource-constrained projects, ________blank are typically used rather than optimum mathematical solutions.
Multiple Choice
team leaders
project managers
program managers
project leaders
heuristics
team leaders
heuristics
Which constraint category should be considered before all others?
Multiple Choice
Logical and technical constraints
Human resource constraints
Material resource constraints
Equipment resource constraints
Time constraints
Logical and technical constraints
When developing project networks, which of the following is not a reason for delineating technical dependencies first before doing resource dependencies?
Multiple Choice
The interrelationships and interactions among time and resource constraints are complex for even small project networks.
Resource availability may not be known until the initial schedule is completed.
Even if resources are known, one cannot assess the impact of limited resources until a resource-neutral schedule is created.
An effort to examine the interactions between technical/logical constraints and resource limitations frequently uncovers surprising problems.
All of these alternatives are reasons for delineating technical dependencies first before doing resource dependencies.
All of these alternatives are reasons for delineating technical dependencies first before doing resource dependencies.
Resource dependency takes priority over the technological dependency but does not violate ________blank dependencies.
Multiple Choice
equipment
time
technical
resource
logical
technical
A project engineer has been scheduled to run the product system test at the same time as building a marketing prototype. This is an example of what type of resource constraint?
Multiple Choice
Physical
Technical
People
Equipment
Time
People
When there are not enough people, money, and/or equipment available for a project it is known as being
Multiple Choice
managerially resourceful.
operationally successful.
resource constrained.
delayed without prejudice.
project constrained.
resource constrained
Splitting an activity can result in all of the following EXCEPT
Multiple Choice
higher resource utilization.
reduced startup and shutdown costs.
a resource being moved from one activity location to another.
activity work being interrupted.
a better project schedule.
reduced startup and shutdown costs.
A project cost baseline is also called ________blank.
Multiple Choice
earned value (EV)
actual cost (AC)
planned value (PV)
budget distribution
budget allocation
planned value (PV)
In reality resource allocation generally occurs in a(n) ________blank environment where the demands of one project have to be reconciled with the needs of other projects.
Multiple Choice
uncertain
multiproject
budget-constrained
risky
controlled
multiproject
Which one of the following would not typically be considered as a resource to a manufacturing company?
Multiple Choice
materials.
people.
equipment.
finished products.
machinery.
finished products
While balancing assignments, a project manager must also balance:
Multiple Choice
Overall project cost.
Talent development.
Earned value.
Work package slack.
Project cost.
Talent development
If resource demand varies widely over the life of the project, the project manager can try to use slack (delaying noncritical activities) to accommodate insufficient resources. This process is called ________blank.
Multiple Choice
resource scheduling
resource smoothing
resource-constrained scheduling
splitting
resource accommodation
resource smoothing
What is true of risks associated with leveling resources?
Flexibility is decreased.
Risk of delay is increased.
Slack is increased.
Total slack is decreased but free slack is increased.
The project may run out of time before it runs out of resources.
Flexibility is decreased, Risk of delay is increased
Consider a project with the accompanying Gantt chart. Stella is your only electrical engineer and she is responsible for activities 3 and 4, which overlap. Level the project so that Stella is only working a maximum of 8 hours each day. What would the new Gantt chart look like?
What would be the new project completion date?

extended by 2 days
Without a ________blank budget a good project schedule and cost control are impossible.
Multiple Choice
time-phased
project cost baseline
definitive
forecasted
firm
time-phased
If it becomes necessary to delay one or several late starts to accommodate resource limitations, this is called:
Multiple Choice
Resource scheduling
Resource smoothing
Resource-constrained scheduling
Splitting
Resource accommodation
Resource-constrained scheduling
Most of the scheduling methods available today require the project manager to classify the project as either ________blank constrained or ________blank constrained.
Multiple Choice
time, quality
quality, resource
cost, time
quality, cost
time, resource
time, resource
A project purchasing agent is trying to order the concrete needed to continue the project. However, the supplier will not be able to deliver it until next week. This is an example of what kind of resource constraint?
Multiple Choice
Working capital
People
Equipment
Information
Materials
Materials
All of the following are benefits of scheduling resources before project implementation EXCEPT
Multiple Choice
it allows time for considering reasonable options if resource constraints do exist.
the project completion date can be established.
work packages can be time-phased.
it allows managers to share resources with other project managers if it is requested without negatively impacting their project.
it ensures low network sensitivity.
it ensures low network sensitivity