1/62
Looks like no tags are added yet.
Name | Mastery | Learn | Test | Matching | Spaced | Call with Kai |
|---|
No analytics yet
Send a link to your students to track their progress
What are the components of a schedule?
- activities
-duration
-logic/sequence/constraints
Can lag be negative?
-Yes
-Called lead
What are the most common scheduling relationships?
-Finish to start
-Start to start with lag
-Finish to Finish with lag
Every activity should have at least one predecessor except the _____.
First
Can the specs define late finish?
yes
What is the difference between lag and float?
lag is the relationship we are designing and float is the difference calculation of early and late days
In a precedence diagram, the delta between early and late start should be the same as what?
early and late finish
What does it mean if an item is on the critical path?
mathematically there is no float
An item is not on the critical path if it has what?
float
What is the only activity that does not need a successor?
the last one
What qualifies a precedence diagram?
logic
By making early finish and late finish the same, what are you able to determine?
activities on the critical path
What are the 2 types of elevators?
-traction
-hydraulic
Not all companies cost load projects, but what companies always will?
ones working on federal jobs
What activities release skin?
structural activities
What are the 2 types of roofs?
-flat
-pitched
What are the 2 fundamentals for basis of payment?
-lump sum
-cost plus
What do cost plus contracts almost always include?
a guaranteed maximum price
What is the metric for cost plus contracts?
-give receipts and get paid
-reimbursed
What is the metric for lump sum contracts?
get paid for percent complete
In a lump sum contract what is irrelevant to the owner?
how much you spend
What are things are needed for cost plus payments to be made?
-labor reports
-monthly statements
-invoices with purchase orders
Who decides the level of detail needed for the Schedule of Values?
the owner but often influenced by the architect and the lender
A more detailed Schedule of Values are more ____ and more ____.
complex, accurate
For Schedule of Values, in order from most level of detail to least level of detail
1.CSI/Trade and locations, phases, floor, etc. 2.Expanded CSI by trades
3. CSI
4. Consolidated CSI
5. Sheet of Paper with prices
When you submit a Schedule of Values, what do you also submit?
a cover sheet
The schedule of values can account for your jobsite overhead and markup or you can do what?
add line items you bill against
Can you prorate and add a line item for jobsite overhead and fee?
Yes
For lump sum projects, the estimate is a proposal but once the contract is executed the GC is contractually obligated to carry the price out. T/F
True
Do subcontractors show a schedule of values to the GC as the GC does to the owner?
Yes
A bonus is a form of profit sharing. T/F
True
Formula to determine Proration
Activity/Line Item x 1.______ = Activity Value
The summation of activity values =
the contract amounts
Contract Value - (Fee+ Jobsite Overhead) =
activity costs
On a pay app, do materials stored affect the percentage in the G column?
Yes
The G column on a pay app represents what?
Total completed and stored to date
Does the GC have to disclose the fee to the owner on a bid job?
No
Does a GC have to submit a change order for every change on the job?
-No
-You can execute change orders that encompass many changes to the job
What has bearing on whether you conduct a change order?
size and scale
What are reasons for a change order to be executed?
-weather or other delays
-owner preference (scope, time)
-errors and omissions
-unforeseen conditions
-adjustment (unit cost, allowances)
-inspections/code
-contractual (remedy, terms)
Why type of insurance do architects have for mistakes made?
errors and ommissions
AIA G701
change order
AIA G702
pay app cover sheet
AIA G703
pay app
Communication for a change order
-Precipitate
-Respond
-Accept/not
Precipitating a change order can include:
-memo
-min.
-Authority having jurisdiction
Responding to a change order includes:
proposing cost change and time change
What makes up the contract value?
-summation of activity costs
-fee
-jobsite overhead
Can some line items be prorated more than others?
yes
How do you determine monthly payment for a pay app?
(Completed and stored to date and adjusted retainage) -payment to date
Why would you need a project to accelerate/expedite?
-behind schedule
-owner request
-accommodate crew progression
-GC preference
-weather
Why might an GC prefer a job to accelerate?
-accommodate crew and man power
-Bonus
-resources to next/other job
-save jobsite overhead
How to accelerate/expedite a project?
-critical items allow everything else to be expedited
-low float items
-materials
if a job is accelerated and crews are working overtime, you have to pay time and a half in addition to regular contracted hours. T/F
False. You only have to pay the premium.
Does a GC have to pay extra for the materials if they have to be expedited?
No. The materials themselves are covered by the contract but the expedited freight/delivery is additional cost.
What are some benefits of expediting/accelerating a project?
-owner happy
-avoid liquidated damages
-bonus
-avoid further delays
-resources can go elsewhere
-save jobsite overhead
Direct Costs of accelerating/expediting a project:
-premium and PTI
-freight/delivery
-speed up fabrication
-wage differential
-per diem
-lighting, hoisting, etc.
What are indirect costs of accelerating/expediting a project?
-QC can decrease resulting in rework
-morale, fatigue resulting in safety issues
-owner "concerns"
-community/municipality
-supervision
What are the 2 constraints of finishes?
-inspections
-required sequence
What are the major factors affecting a laydown area for site utilization?
-accessibility to unload
-where is it going?
-damage
-excessive handling
When concerning site utilization, what activities change over the duration of the project?
-access, traffic, security
-hoisting and scaffolding
-materials
-waste
Do waste needs increase or decrease as the project progresses?
increase
Does the footprint of the building grow or shrink throughout the duration of the project?
grows