TEST BANK FOR PMI (PMP) Exam 6th Edition PMBOK EXAM 2026 (Actual Exam) Questions with verified Answers (Latest Update 2026) UPDATE!!

0.0(0)
Studied by 0 people
call kaiCall Kai
learnLearn
examPractice Test
spaced repetitionSpaced Repetition
heart puzzleMatch
flashcardsFlashcards
Card Sorting

1/99

encourage image

There's no tags or description

Looks like no tags are added yet.

Last updated 12:56 PM on 5/1/26
Name
Mastery
Learn
Test
Matching
Spaced
Call with Kai

No analytics yet

Send a link to your students to track their progress

100 Terms

1
New cards

An element of the project scope statement is:

A. Acceptance criteria.

B. A stakeholder list.

C. A summary budget.

D. High-level risks.

A

2
New cards

Reserves Analysis

Risk management method of determining contingency or management reserves for schedule

3
New cards

Which document describes the necessary information to determine if a project is worth the required investment?

A. Cost baseline

B. Service level agreement

C. Memorandum of understanding

D. Business case

D

4
New cards

Which input to the Plan Risk Management process provides information on high-level risks?

A. Project charter

B. Enterprise environmental factors

C. Stakeholder register

D. Organizational process assets

A

5
New cards

Which item is an example of personnel assessment?

A. Resource calendar

B. Tight matrix

C. Team-building activity

D. Focus group

D

6
New cards

Which input to the Manage Stakeholder Engagement process provides guidance on how stakeholders can best be involved in a project?

A. Feedback analysis

B. Stakeholder analysis

C. Communication management plan

D. Stakeholder management plan

D

7
New cards

Which input to the Identify Stakeholders process provides information about internal or external parties related to the project?

A. Procurement documents

B. Communications plan

C. Project charter

D. Stakeholder register

C

8
New cards

The Identify Stakeholders process is found in which Process Group?

A. Initiating

B. Monitoring and Controlling

C. Planning

D. Executing

A

9
New cards

An input to Develop Project Charter is a/an:

A. Business case.

B. Activity list.

C. Project management plan.

D. Cost forecast.

A

10
New cards

Which Knowledge Area involves identifying the people, groups, or organizations that may be impacted by or impact a project?

A. Project Risk Management

B. Project Human Resource Management

C. Project Scope Management

D. Project Stakeholder Management

D

11
New cards

Which input to Collect Requirements is used to identify stakeholders who can provide information on requirements?

A. Stakeholder register

B. Scope management plan

C. Stakeholder management plan

D. Project charter

A

12
New cards

In which Knowledge Area is the project charter developed?

A. Project Cost Management

B. Project Scope Management

C. Project Time Management

D. Project Integration Management

D

13
New cards

The ability to influence cost is greatest during which stages of the project?

A. Early

B. Middle

C. Late

D. Completion

A

14
New cards

Which process involves developing an approximation of the monetary resources needed to complete project activities?

A. Estimate Costs

B. Control Costs

C. Determine Budget

D. Plan Cost Management

A

15
New cards

Which tool or technique is used in the Develop Project Management Plan process?

A. Pareto diagram

B. Performance reporting

C. SWOT analysis

D. Expert judgment

D

16
New cards

The organization's perceived balance between risk taking and risk avoidance is reflected in the risk:

A. Responses

B. Appetite

C. Tolerance

D. Attitude

A

17
New cards

An output of the Manage Stakeholder Engagement process is:

A. change requests

B. enterprise environmental factors

C. the stakeholder management plan

D. the change log

A

18
New cards

Which process numerically analyzes the effect of identified risks on overall project objectives?

A. Plan Risk Management

B. Plan Risk Responses

C. Perform Quantitative Risk Analysis

D. Perform Qualitative Risk Analysis

C

19
New cards

Which Collect Requirements output links the product requirements to the deliverable that satisfy them?

A. Requirements documentation

B. Requirements traceability matrix

C. Project management plan updates

D. Project documents updates

B

20
New cards

A temporary endeavor that creates a unique product or service is called a:

A. Project

B. Plan

C. Program

D. Portfolio

A

21
New cards

The process of prioritizing risks for further analysis or action is known as:

A. Plan Risk Management.

B. Plan Risk Responses.

C. Perform Qualitative Risk Analysis.

D. Perform Quantitative Risk Analysis.

C

22
New cards

Stakeholder satisfaction should be managed as a key project:

A. Benefit

B. Initiative

C. Objective

D. Process

C

23
New cards

Which cost is associated with nonconformance?

A. Liabilities

B. Inspections

C. Training

D. Equipment

A

24
New cards

Identify Risks is part of which Process Group?

A. Planning

B. Executing

C. Closing

D. Initiating

A

25
New cards

The business needs, assumptions, and constraints and the understanding of the customers needs and high-level requirements are documented in the:

A. Project management plan.

B. Project charter.

C. Work breakdown structure.

D. Stakeholder register.

B

26
New cards

Which Process Group and Knowledge Area include the Sequence Activities process?

A. Executing Process Group and Project Time Management

B. Executing Process Group and Project Cost Management

C. Planning Process Group and Project Time Management

D. Planning Process Group and Project Cost Management

C

27
New cards

In the Plan Stakeholder Management process, expert judgment is used to:

A. Provide information needed to plan appropriate ways to engage project stakeholders.

B. Ensure comprehensive identification and listing of new stakeholders.

C. Analyze the information needed to develop the project scope statement.

D. Decide the level of engagement of the stakeholders at each required stage.

D

28
New cards

Power, urgency, and legitimacy are attributes of which stakeholder classification model?

A. Salience

B. Influence/impact

C. Power/interest

D. Power/influence

A

29
New cards

Through whom do project managers accomplish work?

A. Consultants and stakeholders

B. Stakeholders and functional managers

C. Project team members and consultants

D. Project team members and stakeholders

D

30
New cards

A stakeholder expresses a need not known to the project manager. The project manager most

likely missed a step in which stakeholder management process?

A. Plan Stakeholder Management

B. Identify Stakeholders

C. Manage Stakeholder Engagement

D. Control Stakeholder Engagement

A

31
New cards

Skills necessary for project management such as motivating to provide encouragement; listening actively; persuading a team to perform an action; and summarizing, recapping, and identifying next steps are known as:

A. organizational skills

B. technical skills

C. communication skills

D. hard skills

C

32
New cards

When a project is undertaken to reduce defects in a product or service, the objective of the project

is to create a/an:

A. improvement

B. program

C. result

D. portfolio

A

33
New cards

The degree of uncertainty an entity is willing to take on in anticipation of a reward is known as its risk:

A. management

B. response

C. tolerance

D. appetite

D

34
New cards

The zero duration of milestones in project planning occurs because milestones:

A. Are unpredictable and challenge the Plan Schedule Management process.

B. Occur at random times in the project plans.

C. Represent a moment in time such as a significant project point or event.

D. Represent both significant and insignificant points in the project and are difficult to anticipate.

C

35
New cards

The component of the human resource management plan that includes ways in which team members can obtain certifications that support their ability to benefit the project is known as:

A. recognition and rewards

B. compliance

C. staff acquisition

D. training needs

D

36
New cards

Stakeholders can be identified in later stages of the project because the Identify Stakeholders process should be:

A. Continuous

B. Discrete

C. Regulated

D. Arbitrary

A

37
New cards

In project management, a temporary project can be:

A. Completed without planning

B. A routine business process

C. Long in duration

D. Ongoing to produce goods

C

38
New cards

Which document in the project management plan can be updated in the Plan Procurement Management process?

A. Budget estimates

B. Risk matrix

C. Requirements documentation

D. Procurement documents

C

39
New cards

Which type of probability distribution is used to represent uncertain events such as the outcome of a test or a possible scenario in a decision tree?

A. Uniform

B. Continuous

C. Discrete

D. Linear

C

40
New cards

Which stakeholder approves a project's result?

A. Customer

B. Sponsor

C. Seller

D. Functional manager

A

41
New cards

Which process involves determining, documenting, and managing stakeholders' needs and requirements to meet project objectives?

A. Collect Requirements

B. Plan Scope Management

C. Define Scope

D. Define Activities

A

42
New cards

Plan Communications Management develops an approach and plan for project communications based on stakeholders' needs and requirements and:

A. Available organizational assets

B. Project staff assignments

C. Interpersonal skills

D. Enterprise environmental factors

A

43
New cards

What is the risk rating if the probability of occurrence is 0.30 and the impact if it does occur is moderate (0.20)?

A. 0.03

B. 0.06

C. 0.10

D. 0.50

B

44
New cards

A complete set of concepts, terms, and activities that make up an area of specialization is known as:

A. a Knowledge Area

B. a Process Group

C. program management

D. portfolio management

A

45
New cards

The risk response strategy in which the project team acts to reduce the probability of occurrence or impact of a risk is known as:

A. exploit

B. avoid

C. mitigate

D. share

C

46
New cards

Which process is conducted from project inception through completion and is ultimately the responsibility of the project manager?

A. Control Quality

B. Monitor and Control Project Work

C. Control Scope

D. Perform Integrated Change Control

D

47
New cards

Project management processes ensure the:

A. alignment with organizational strategy

B. efficient means to achieve the project objectives

C. performance of the project team

D. effective flow of the project throughout its life cycle

D

48
New cards

Which project risk listed in the table below is most likely to occur?

RISK PROBABILITY IMPACT

1 L M

2 H H

3 L L

4 M L

A. 1

B. 2

C. 3

D. 4

B

49
New cards

Which is an enterprise environmental factor?

A. Marketplace conditions

B. Policies and procedures

C. Project files from previous projects

D. Lessons learned from previous projects

A

50
New cards

Project Stakeholder Management focuses on:

A. project staff assignments

B. project tea m acquisition

C. managing conflicting interests

D. communication methods

C

51
New cards

A risk that arises as a direct result of implementing a risk response is called a:

A. contingent risk

B. residual risk

C. potential risk

D. secondary risk

D

52
New cards

The purpose of developing a project scope management plan is to:

A. Manage the timely completion of the project.

B. Ensure that the project includes all of the work required.

C. Make sure the project will satisfy the needs for which it was begun.

D. Reduce the risk of negative events in the project.

B

53
New cards

A tool and technique used in the Develop Project Charter process is:

A. change control tools

B. expert judgment

C. meetings

D. analytical techniques

B

54
New cards

A projects purpose or justification, measurable project objectives and related success criteria, a summary milestone schedule, and a summary budget are all components of which document?

A. Work breakdown structure

B. Requirements document

C. Project charter

D. Project management plan

C

55
New cards

Project managers who lead by example and follow through on the commitments they make demonstrate the key interpersonal skill of:

A. influencing

B. leadership

C. motivation

D. coaching

A

56
New cards

The process of defining how the project scope will be validated and controlled is known as:

A. Define Scope.

B. Develop Project Management Plan.

C. Plan Scope Management.

D. Plan Quality Management.

C

57
New cards

Technical capability, past performance, and intellectual property rights are examples of:

A. performance measurement criteria

B. source selection criteria

C. product acceptance criteria

D. phase exit criteria

B

58
New cards

The methodology that combines scope, schedule, and resource measurements to assess project performance and progress is known as:

A. Earned value management.

B. Forecasting.

C. Critical chain methodology.

D. Critical path methodology.

A

59
New cards

Which process is usually a rapid and cost-effective means of establishing priorities for Plan Risk Responses?

A. Identify Risks

B. Plan Risk Management

C. Perform Qualitative Risk Analysis

D. Perform Quantitative Risk Analysis

C

60
New cards

Which element does a project charter contain?

A. Management reserves

B. Work breakdown structure

C. Stakeholder list

D. Stakeholder register

C

61
New cards

Every project creates a unique product, service, or result that may be:

A. tangible

B. targeted

C. organized

D. variable

A

62
New cards

The degree, amount, or volume of risk that an organization or individual will withstand is called risk:

A. appetite

B. tolerance

C. threshold

D. management

B

63
New cards

An issue log is an input to which Project Human Resource Management process?

A. Manage Project Team

B. Acquire Project Team

C. Plan Human Resource Management

D. Develop Project Team

A

64
New cards

The component of the risk management plan that documents how risk activities will be recorded is called:

A. tracking

B. scoping

C. timing

D. defining

A

65
New cards

Which Control Stakeholder Engagement tool or technique allows the project manager to consolidate and facilitate distribution of reports?

A. Information management systems

B. Work performance reports

C. Stakeholder analysis

D. Data gathering and representation

A

66
New cards

Which basic quality tool explains a change in the dependent variable in relationship to a change observed in the corresponding independent variable?

A. Cause-and-effect diagram

B. Histogram

C. Control chart

D. Scatter diagram

D

67
New cards

High-level project risks are included in which document?

A. Business case

B. Risk breakdown structure

C. Project charter

D. Risk register

C

68
New cards

The scope management plan and scope baseline are contained in:

A. organizational process assets

B. a requirements traceability matrix

C. the project charter

D. the project management plan

D

69
New cards

Projects that share common outcomes, collective capability, knowledge, or skills are often grouped into a:

A. portfolio

B. program

C. selection

D. sub portfolio

B

70
New cards

The stakeholder register is an output of:

A. Identify Stakeholders.

B. Plan Stakeholder Management.

C. Control Stakeholder Engagement.

D. Manage Stakeholder Engagement.

A

71
New cards

An output of the Develop Project Team process is:

A. change requests

B. team performance assessments

C. project staff assignments

D. project documents updates

B

72
New cards

The formal and informal interaction with others in an organization industry, or professional environment is known as:

A. negotiation

B. organizational theory

C. meeting

D. networking

D

73
New cards

Which process is included in the Project Integration Management Knowledge Area?

A. Manage Project Team

B. Collect Requirements

C. Sequence Activities

D. Direct and Manage Project Work

D

74
New cards

The project manager notes that stakeholders are aware of the project and potential impacts and are actively engaged in ensuring that the project is a success. The engagement level of the stakeholders should be classified as:

A. Supportive

B. Leading

C. Neutral

D. Resistant

B

75
New cards

Which of the following is a narrative description of products, services, or results to be delivered by

a project?

A. Project statement of work

B. Business case

C. Accepted deliverable

D. Work performance information

A

76
New cards

A project manager seeking insight on previous stakeholder management plans and their effectiveness should evaluate:

A. Historical information and the lessons-learned database.

B. Historical information and the stakeholder register.

C. Organizational process assets and the lessons-learned database.

D. Project documents and historical information.

A

77
New cards

Projects are undertaken by an organization to support the:

A. Product performance.

B. Budget process.

C. Collective capabilities.

D. Organizational strategy.

D

78
New cards

What is the probability of occurrence if the risk rating is 0.56 and the impact if the risk does occur is very high (0.80)?

A. 0.45

B. 0.56

C. 0.70

D. 1.36

C

79
New cards

The scope of a project cannot be defined without some basic understanding of how to create the specified:

A. objectives

B. schedule

C. product

D. approach

C

80
New cards

The creation of an internet site to engage stakeholders on a project is an example of which type of communication?

A. Push

B. Pull

C. Interactive

D. Iterative

B

81
New cards

Which is the Define Scope technique used to generate different approaches to execute and perform the work of the project?

A. Build vs. buy

B. Expert judgment

C. Alternatives identification

D. Product analysis

C

82
New cards

Most experienced project managers know that:

A. every project requires the use of all processes in the PMBOK® Guide.

B. there is no single way to manage a project.

C. project management techniques are risk free.

D. there is only one way to manage projects successfully.

B

83
New cards

The product scope description is used to:

A. Gain stakeholders' support for the project.

B. Progressively elaborate the characteristics of the product, service, or result.

C. Describe the project in great detail.

D. Define the process and criteria for accepting a completed product, service, or result.

B

84
New cards

Which of the following is TRUE about most project life cycles?

A. Staffing level is highest at the start.

B. The stakeholders' influence is highest at the start.

C. The level of uncertainty is lowest at the start.

D. The cost of changes is highest at the start.

B

85
New cards

An input required in Define Scope is an organizational:

A. structure.

B. process asset.

C. matrix.

D. breakdown structure.

B

86
New cards

Which of the following risk response strategies involves allocating ownership of a positive risk to a third party?

A. Mitigate

B. Transfer

C. Share

D. Avoid

C

87
New cards

Which activity is an input to the Conduct Procurements process?

A. Organizational process assets

B. Resource availability

C. Perform Integrated Change Control

D. Team performance assessment

A

88
New cards

Which of the following investigates the likelihood that each specific risk will occur?

A. Risk register

B. Risk audits

C. Risk urgency assessment

D. Risk probability and impact assessment

D

89
New cards

What is a hierarchically organized depiction of the identified project risks arranged by risk category?

A. Risk register

B. Risk breakdown structure (RBS)

C. Risk management plan

D. Risk category

B

90
New cards

Which of the following is an enterprise environmental factor that can influence the Develop Project Charter process?

A. Organizational standard processes

B. Marketplace conditions

C. Historical information

D. Templates

B

91
New cards

The Define Scope process is in which of the following Process Groups?

A. Initiating

B. Planning

C. Monitoring and Controlling

D. Executing

B

92
New cards

Organizations perceive risks as:

A. events that will inevitably impact project and organizational objectives.

B. the effect of uncertainty on their project and organizational objectives.

C. events which could have a negative impact on project and organizational objectives.

D. the negative impact of undesired events on their project and organizational objectives.

B

93
New cards

Who selects the appropriate processes for a project?

A. Project stakeholders

B. Project sponsor and project stakeholder

C. Project manager and project team

D. Project manager and project sponsor

C

94
New cards

The scope management plan is a subsidiary of which project document?

A. Schedule management plan

B. Project management plan

C. Quality management plan

D. Resource management plan

B

95
New cards

The Verify Scope process is primarily concerned with:

A. formalizing acceptance of the completed project deliverables.

B. accuracy of the work deliverables.

C. formalizing approval of the scope statement.

D. accuracy of the work breakdown structure (WBS).

A

96
New cards

Which is a tool or technique used in Define Scope?

A. Templates, forms, and standards

B. Change requests

C. Product analysis

D. Project assumptions

C

97
New cards

Which of the following is an output of the Define Activities process?

A. Activity list

B. Project plan

C. Activity duration estimates

D. Project schedule

A

98
New cards

Which process uses occurrence probability and impact on project objectives to assess the priority of identified risks?

A. Identify Risks

B. Perform Qualitative Risk Analysis

C. Plan Risk Management

D. Perform Quantitative Risk Analysis

B

99
New cards

What is one of the objectives of Project Risk Management?

A. Decrease the probability and impact of an event on project objectives.

B. Distinguish between a project risk and a project issue so that a risk mitigation plan can be put in place.

C. Increase the probability and impact of positive events.

D. Removal of project risk.

C

100
New cards

Which type of managers do composite organizations involve?

A. Functional managers and manager of project managers

B. Functional managers only

C. Project managers only

D. Technical managers and project managers

A