ACI CERTIFICATION

0.0(0)
Studied by 0 people
call kaiCall Kai
learnLearn
examPractice Test
spaced repetitionSpaced Repetition
heart puzzleMatch
flashcardsFlashcards
GameKnowt Play
Card Sorting

1/109

encourage image

There's no tags or description

Looks like no tags are added yet.

Last updated 3:34 AM on 6/12/26
Name
Mastery
Learn
Test
Matching
Spaced
Call with Kai

No analytics yet

Send a link to your students to track their progress

110 Terms

1
New cards

Collecting a representative sample of concrete to be testes is as important as executing the test methods to obtain

Accurate Results

2
New cards

This practice covers sample from four types of equipment, which are ___________, _______________, ______________, __________

Stationary mixers, paving mixers, revolving truck mixers, continuous mixers

3
New cards

The elapsed time between obtaining the first and final portions of a composite sample shall not exceed

15 minutes

4
New cards

Portions of a composite sample shall be thoroughly remixed before beginning tests on the sample? True or False

True

5
New cards

Start tests for slump, temperature, and air content within ___________ after obtaining the final portion of the composite sample

5 minutes

6
New cards

Start molding specimens for strength test withing _______________ after fabricating the composite sample

15 minutes

7
New cards

The concrete sample must be protected from contamination and ______________

Evaporation

8
New cards

The minimum size sample for making strength test speciment is ___________

1 ft³

9
New cards

When sampling from a stationary mixer, the batch must be sampled at _______________ or more regularly intervals during discharge of the middle portion of the batch

2

10
New cards

When sampling from a paving mixer, obtain samples from at least ___________ different portions of the pile and combine them into one composite sample for test purposes

5

11
New cards

When sampling from a revolving truck mixer, sample the concrete by collecting ___________ or more portions take at regularly spaced intervals during discharge of the middle portion of the batch

2

12
New cards

Concrete samples from a truck mixer must be obtained before any water or admixtures are added to the mixer at the job site. True or False

False

13
New cards

When the concrete contains aggregate larger than that permitted for a particular test method, the sample of concrete must be ___________ before making the test

Wet Screened

14
New cards

The stem of the thermometer is submerged a minimum of _________ into the freshly mixed concrete

3 inches

15
New cards

The thermometer shall be capable of accurately measuring the temperature of freshly mixed concrete to ___________ throughout a range of ______

1 degree Fahrenheit, 30 to 120 degree Fahrenheit

16
New cards

The thermometer shall be verified within ____________

1 year of current use

17
New cards

The temperature of concrete may be measured in a wheelbarrow. True or False?

True

18
New cards

The temperature of concrete may be measured in a wall form. True or False?

True

19
New cards

A composite sample of concrete is required even if the only purpose of obtaining the sample is to determine the temperature. True or False?

False

20
New cards

What must be done to the sample container prior to sampling the concrete?

Dampened with water

21
New cards

What must be done to the concrete surrounding the thermometer after the device is submerge in the fresh concrete?

Push concrete around the stem to ensure the concrete is in full contact with the stem

22
New cards

How long must the thermometer remain in the freshly mixed concrete?

2 - 5 minutes

23
New cards

After the temperature of the concrete is read, what is then required?

Record the temperature

24
New cards

The temperature of the concrete is recorded to the nearest

1 degree Fahrenheit

25
New cards

There is a specified maximum temperature of freshly mixed concrete. True or False?

False

26
New cards

The sample of concrete used for temperature determination must be rodded 25 times. True or False?

False

27
New cards

When the concrete contains aggregate larger than allowed for the slump test, the large aggregate must be _________

Wet screened over 1.5 inch sieve

28
New cards

The mold for making the slump test is in the shape of a

The frustum cone

29
New cards

The height of the slump mold is

12 inches

30
New cards

The interior surface of the slump mold is allowed to have minor irregularities. True or False?

False

31
New cards

For use in the slump test, the tamping end or both ends of the tamping rod must be _________

Rounded to a hemispherical tip

32
New cards

The slump mold should be in a dry condition before beginning the test. True or False?

False

33
New cards

The surface on which the slump mold will be placed must be _____________

Flat, level, damp, nonabsorbent, and rigid

34
New cards

The slump mold is filled in __________ layers

Three

35
New cards

Each layer should fill approximately _________ the volume of the mold

1/3

36
New cards

Rod each layer _________ times uniformly over the cross section with the rounded end of the rod

25

37
New cards

How deep should the tamping rod penetrate into each layer?

Rod each layer throughout its depth on the second and final layer rod should penetrate into previous layer about 1 inch

38
New cards

What must be done if the concrete drops below the top of the slump mold while the top layer is being rodded

Add additional concrete

39
New cards

Prior to lifting the mold, concrete must be removed from

The area surrounding the base of the mold

40
New cards

After the final rodding, the sides of the slump mold should be tapped lightly with the tamping rod. True or False

False

41
New cards

When raising the slump mold, it should not be rotated or twisted. True or False?

True

42
New cards

How much time is allowed for lifting the slump mold?

5 (+ or -) 2 seconds

43
New cards

The measurement for slump is made from the top of the mold to what point of the concrete specimen?

The displaced original center of the top surface of the specimen

44
New cards

The slump of the concrete is measured and reported to the nearest?

¼ inch

45
New cards

How much time is allowed to conduct the slump test from beginning to completion?

2.5 minutes

46
New cards

The length of the tamping rod used in this test method is

At least 4 inches taller than the height of the measure but no more than 24 inches in overall length

47
New cards

What is the required shape of the tamping end of the rod?

Rounded to a hemispherical tip

48
New cards

What is the required minimum frequency of the vibrator used in this test method?

9000 vibrations per minute (150 Hz)

49
New cards

The outside diameter or side dimension of the vibrating element must be at least _________ but not greater than ______

0.75 inch, 1.5 inch

50
New cards

What material is the measure made of?

Typically Metal

51
New cards

What is the minimum thickness of a metal strike off plate?

¼ inch

52
New cards

What is the minimum thickness for a glass or acrylic strike off plate?

½ inch

53
New cards

What is the specified weight of the mallet used on measures that are ½ ft³ or smaller?

1 ¼ (+ or -) ½ lb

54
New cards

What method of consolidation must be used when the slump is greater than 3 inches?

Rodding

55
New cards

What method of consolidation must be used when the slump is less than 1 inch?

Vibration

56
New cards

If rodding is the method of consolidation being used, the measure must be filled in how many layers?

Three

57
New cards

For a measure of ½ ft³, what is the required number of strokes of the tamping rod for consolidation of each layer?

25

58
New cards

When rodding the middle and the top layers, the tamping rod should penetrate into the layer below approximately

1 inch

59
New cards

If vibration is the method of consolidation, the measure must be filled in ____ approximately equal layers

Two

60
New cards

If, after consolidation of the final layer, the concrete level is ½ inch above the top of the measure, what should be done?

Remove enough concrete to ensure you have over filled the measure approximately 1/8 inch above the top of the measure

61
New cards

After completing the strike off procedure, what must be done before weighing the measure and sample?

Clean off any excess concrete

62
New cards

The pressure method of determining air content can be used on concrete containing ___________, and ___________ aggregate.

Normal weight; Heavyweight

63
New cards

The pressure method of determining air content cannot be used on concrete containing the following _____________ or _________

Lightweight aggregates; aggregates of high porosity

64
New cards

What is the specified size of mallet required for a typical air meter?

1 ¼ (+ or -) ½ lb

65
New cards

Wet screening may be necessary when the mixture contains aggregate with a nominal maximum size greater than?

1.5 inches

66
New cards

If the concrete sample is to be consolidated by rodding, the measure is filled in _________ layers

3 equal

67
New cards

If the concrete is to be consolidated by vibration, the measure is filled in _________ layers

2 equal

68
New cards

When rodding the concrete sample, what is the specified number of strokes required for each layer?

25

69
New cards

Vibration of the concrete sample is not allowed when the slump of the concrete exceeds __________

3 inches

70
New cards

In rodding the sample, how deep should the rod penetrate each layer?

Rod bottom layer through full depth; rod second and final layer penetrating the previous layer about 1 inch

71
New cards

After rodding each layer what should be done to the measure before adding another layer of concrete?

Tap sides of the measure 10 to 15 times with mallet

72
New cards

What tools may be used to strike off the top surface of the concrete following consolidation of the final layer?

A strike off bar or plate

73
New cards

The volumetric method of determining air content of concrete can be used on concrete containing what types of aggregate?

All types of aggregates

74
New cards

What are the requirement for the tamping rod used in this test method?

Steel or plastic, with a hemispherical tip on onr or both ends, at least 4 inches taller than measure but no more than 24 inches in overall length

75
New cards

What are the requirements for the strike off bar used in this test method?

Metal or plastic flat bar at least ¾ inch in width and 12 inches in length. If using a meter made of metal, the thickness must be at least 1/8 inch and if using a meter made of plastic the thickness must be at least ¼ inch.

76
New cards

What is the minimum capacity of the measuring cup used to add alcohol to the air meter?

1 pt

77
New cards

What type of alcohol and concentration must be used in this test method?

Isopropyl, 70% by volume

78
New cards

A mallet weighing _________ must be used to tap the sides of the bowl after rodding each layer

1.25(+ or -) .5 lb

79
New cards

If the concrete contains aggregate that would be retained on the ____________ sieve, you must wet screen a representative portion of the concrete sample over an ____________ sieve

1 ½ inch; 1 inch

80
New cards

When filling the measuring bowl of the air meter, the concrete must be placed in ______ layers of equal volume

2

81
New cards

What is the required number of strokes required when rodding each layer of concrete?

25

82
New cards

It is necessary to tap the sides of the measuring bowl after each layer has been rodded. True or False?

True

83
New cards

The initial quality of water and alcohol added to the air meter can be poured directly into the neck of the top section of the air meter. True or False?

False; the funnel must be used

84
New cards

Upon final filling of the air meter with water what part of the liquid level should be adjusted to the zero mark on the meter?

Bottom of the meniscus

85
New cards

How long should the air meter be inverted and agitated?

No more than 5 seconds at a time, but must be repeated for a minimum of 45 seconds to free concrete from base

86
New cards

How many times does the rolling operation occur?

A minimum of 2, a maximum of 3

87
New cards

Why is the isopropyl alcohol added to the meter?

To dispel any foam

88
New cards

The direct reading of the final liquid level in the neck of the air meter, is estimated to the nearest ______

0.25%

89
New cards

If the air content is greater than the 9% range of the meter ______________

Calibrated cups of water are added to bring the liquid level within the graduated range

90
New cards

In order for an initial meter reading to be valid, the meter must not be leaking, the liquid level must stabilize within 6 min, and the foam on the surface of the liquid must not be greater than 2 full percent divisions. True or False

true

91
New cards

If less than 2.5 pt of alcohol are used, the air content is always indicated by the final meter reading. True or False?

False

92
New cards

If more than 2.5 pt of alcohol are used, the final meter reading is always adjusted using

A correction factor

93
New cards

At the end of the procedure the air meter is ____________

Disassembled and its contents examined

94
New cards

If portions of undisturbed concrete are found in the air meter at the end of the test, _________

The test is invalid

95
New cards

For cylinders with a diameter of 6 inches or greater the tamping rod must have a diameter of _______

5/8 inch

96
New cards

The minimum frequency of an internal vibrator used in this procedure is _____

150 Hz (9000 vibrations per minute)

97
New cards

Concrete containing aggregate with particles not exceeding _______ can be used to cast specimens without the need for wet screening.

2 inches

98
New cards

For concrete with a slump of less than 1 inch, the test specimens must be consolidated by ________

Vibration

99
New cards

If the concrete is to be consolidated by vibration, a standard 4 by 8 inch cylinder mold must be filled in _______ equal layers

2

100
New cards

When rodding a standard 6 by 12 inch cylinder, each layer must be rodded ______ times.

25