Name
Mastery
Learn
Test
Matching
Spaced
Call with Kai

No analytics yet

Send a link to your students to track their progress

37 Terms

1
New cards

Wilkinson Steam Cycle Order

fire tube boiler, steam stop valve, gland sealing steam + air ejector + drain to feed tank, turbine, condenser, condensate pump, air ejector, feed tank, boiler

2
New cards

Wilkinson Boiler

3 pass Hurst fire tube boiler - external firing

3
New cards

1/3 Pass

where the fluid enters is the opposite end from which the flue gas exits

4
New cards

2/4 Pass

where the fluid enters is the same end from which the flue gas exits

5
New cards

Steam Trap

collects condensate that can form when steam loses BTUs from 90 degree turns

6
New cards

ISO New England

shows percentage of what power plants are using what energy sources and more

7
New cards

ASME

sets the minimum standard codes and states can either adhere to it or build off it in a stricter manner

8
New cards

HP Boiler

over 15 psi or 9 horsepower according to ASME section 1

9
New cards

Boiler Inspections

HP boilers annually (522 CMR sec 2.00) for both external and internal

10
New cards

Internal vs External Boiler Inspection

inspector gives a 14-day notice before and a 6-month delay can be requested vs they can check at anytime

- 522 CMR 2.00

11
New cards

Cavitation

formation and collapse of vapor bubbles when hot liquid is put into a centrifugal pump, leading to erosion of components

12
New cards

Boiler Horsepower (chapter 146, sec 48)

- nameplate

- steam output/34.5

- BTU output/33,475

- BTU Input/41840

13
New cards

Certificate of Inspection

required for a HP boiler and it includes the signature, date of inspection, name of owner/user, location of boiler, and the MAWP (Chapter 146 sec. 6)

14
New cards

ASME CSD-1

controls and safety devices for primary and secondary

15
New cards

Low Water Cutoff

protects the boiler in a low water condition

- two methods (float switch or probe)

16
New cards

Float Switch (low water)

consists of the gage glass and tricocks

17
New cards

Probe (low water)

detects the water level and connects to the master control via wires

18
New cards

Permissives

what the master control must see before allowing the boiler to start (purging, fans, low water)

19
New cards

Make-Up Water

city water used to make up losses - a feed tank float control turns on the feed pump to bring in make-up water when the feed tank level is low

20
New cards

Flame Scanner/Eye

scans for UV light to make sure the fire is burning

21
New cards

Pressuretrol

sets the swing of pressure (where it will cut off and where it will start)

22
New cards

Wilkinson MAWP

200 psi

23
New cards

Wilkinson Pressure Protection

pressuretrol has a manual reset - safety valves are the backup

24
New cards

Safety Valves

- more than one required if over 500 ft^2 of heating surface

- nozzle or huddling chamber (both have a blowdown period)

25
New cards

Bottom Blow-Down

remove sludge that is created from corrosion or the addition of chemicals meant to remove minerals - can be done during a fire under a light load

26
New cards

Calcium Magnesium

mineral in city drinking water that must be removed by a water softener and then chemicals

27
New cards

Blowdown/Flash Tank

connected to the blowdown in order to reduce water to 150 degrees and 5 psi

28
New cards

Blowdown Valves

2 required if over 100 psi

- 2 slow valves or a quick and slow (in that order going away from the boiler)

29
New cards

Chemicals

prevents the formation of scales by combatting calcium, oxygen, and PH

30
New cards

PH

keep between 9 and 11

- too alkaline cause caustic embrittlement (likeliness for boiler materials to fracture

- too acidic = corrosion

31
New cards

Boiler Vent

- prevents a boiler vacuum by being open during shutdown

- get rid of air and non-condensable gases during start up

- keep open until pressure gage is engaged and steam flows

- 15 psi goal: leave open until then during shutdown

32
New cards

MDR

specs of a boiler this used for repair, adheres to ASME/National Board/522 CMR, and is prescribed by the manufacturer

33
New cards

Wilkinson Fuel

natural gas that has a pressure of 7 in water column or 1/4 psi

34
New cards

Nox

nitrogen oxide

35
New cards

Sox

sulfur oxide

36
New cards

Nameplate

located at normal operating water level (NOWL)

37
New cards

HP to LP Boiler

a HP boiler can be operated as a LP boiler by changing the pressure swing on a pressuretrol