This flashcard set covers the vocabulary and quantitative parameters found in the project planning notes for a software development information system, including work nomenclature, network graph terminology, and critical path analysis.

Last updated 9:42 AM on 5/20/26
Name
Mastery
Learn
Test
Matching
Spaced
Call with Kai

No analytics yet

Send a link to your students to track their progress

12 Terms

1
New cards

Development of the Technical Assignment

The first work item in the nomenclature, lasting 55 days, which serves as the foundation for the technical proposal.

2
New cards

Technical Proposal

The second development stage, which takes 88 days and is initiated after the completion of the technical assignment.

3
New cards

ASU Control Algorithm

A process (work 6) defining the management logic of the automated control system, followed by an analysis of said algorithm (work 7).

4
New cards

SQL Views

External data viewing structures (work 8) defined after the analysis of the ASU control algorithm, with a duration of 88 days.

5
New cards

OOP Classes

The fundamental classes for Object-Oriented Programming (work 10) identified after defining data objects, with a duration of 1919 days.

6
New cards

Testing

Process step 15, lasting 2020 days, which occurs after the definition of data samples and data protection tools.

7
New cards

Technical Documentation

The final work item (17) in the project schedule, involving the compilation of all technical records over a period of 1414 days.

8
New cards

Network Graph (Сітковий графік)

A visual and mathematical model representing the interdependencies between software development tasks and their sequential flow.

9
New cards

Critical Path (Критичний шлях)

The longest sequence of dependent activities (1-2-3-4-5-6-7-8-9-11-13-14-15-16) that determines the minimum project duration of 118118 days.

10
New cards

Time Reserve (Резерв часу)

The flexibility in scheduling non-critical tasks; tasks on the critical path have a reserve of 00, meaning any delay will postpone the entire project.

11
New cards

TcritT_{\text{crit}}

The total duration of the critical path, calculated in this specific project as 118days118\, \text{days}.

12
New cards

Data Protection Tools

Item 12 in the work nomenclature, lasting 55 days, defined specifically after identifying the main OOP classes.