Load Factor
Load Factor = Average Load / Peak Load = Average Load / Max Load
Plant Use Factor
PUF = Annual Energy Production / Plant Capacity x Hours Operation
PUF = Average Load x 8760 hrs / Plant Capacity x Hours Operation
PUF = Peak Load / Plant Capacity
PUF = Capacity Factor / Load Factor
Annual Energy Production
AEP = Average Load x 8760
Plant Capacity Factor
Plant Capacity Factor = Average Load / Plant Capacity
PUF/PCF
PUF/PCF = 8760 / hours operation
Average Load
Average Load = Energy Consumed in a Time / Time
Diversity Factor
Diversity Factor = Sum of Ind. Max Demand / Max Sim. Demand
Demand Factor
Demand Factor = Actual Max Demand / Total Connected Demand