Architecture Licensure Practice Examination Flashcards

0.0(0)
Studied by 0 people
call kaiCall Kai
learnLearn
examPractice Test
spaced repetitionSpaced Repetition
heart puzzleMatch
flashcardsFlashcards
GameKnowt Play
Card Sorting

1/40

flashcard set

Earn XP

Description and Tags

Vocabulary-style flashcards covering preconstruction activities, administrative protocols, construction observation, project closeout, and professional ethics based on AIA standards and Philippine Republic Acts.

Last updated 8:19 PM on 5/18/26
Name
Mastery
Learn
Test
Matching
Spaced
Call with Kai

No analytics yet

Send a link to your students to track their progress

41 Terms

1
New cards

Addendum

A document used to modify bid documents BEFORE the execution of a construction contract.

2
New cards

General Contractor Responsibility

Under a design-bid-build delivery method, the party primarily responsible for the coordination of construction means and methods.

3
New cards

Open specification

A type of specification that allows the contractor to submit an equivalent product to that which is specified.

4
New cards

AIA A101

The standard form of agreement between Owner and Contractor for a stipulated sum.

5
New cards

Bid bond

A requirement in competitive bidding used to ensure the bidder will enter into a contract if selected.

6
New cards

Unit price

A price primarily used in a bid when the exact quantity of certain work items cannot be determined in advance.

7
New cards

Payment Bond

A document that establishes the contractor's obligation to pay subcontractors and suppliers.

8
New cards

Design-Build Entity

The party in a design-build delivery who holds primary responsibility for both design and construction.

9
New cards

Pre-bid conference

A meeting held primarily to clarify the scope of work and answer bidder questions.

10
New cards

Construction Management at Risk

A delivery method where a single entity is responsible for both design and construction under a guaranteed maximum price.

11
New cards

AIA A201

The AIA document that serves as the General Conditions of the Contract for Construction.

12
New cards

Schedule of values

A document submitted by the contractor to serve as a basis for reviewing applications for payment.

13
New cards

Responsive bid

A bid that complies with all bidding requirements without qualification.

14
New cards

Division 01

The specification section in CSI MasterFormat that covers General Requirements for a project.

15
New cards

Allowance

A fixed sum included in a contract for a specified scope of unknown cost.

16
New cards

Change Order vs. CCD

A Change Order requires agreement by all parties, whereas a Construction Change Directive (CCD) does not.

17
New cards

AIA G704

The AIA document used to certify substantial completion of a project.

18
New cards

Retainage

The percentage of funds withheld from each payment application, typically at 10%10\% per AIA A201.

19
New cards

Request for Information (RFI)

A document used to seek clarification on the contract documents from the architect.

20
New cards

Architect's Supplemental Instruction (ASI)

A document used to issue minor clarifications or instructions that have no cost or time impact.

21
New cards

Liquidated damages

A pre-agreed amount paid by the contractor to the owner for each day the project remains uncompleted past the agreed completion date.

22
New cards

AIA G702/G703

The standard application and certificate for payment forms submitted by the contractor.

23
New cards

Joint check

An arrangement where the owner issues payment to both the general contractor and subcontractor to ensure the latter is paid.

24
New cards

Substantial completion

The stage when the work is sufficiently complete for the owner to occupy or use it for its intended purpose.

25
New cards

Performance bond

A bond that primarily protects the owner against the contractor's failure to complete the project per contract terms.

26
New cards

Standard Correction Period

Per AIA A201, the period for correcting defective work after substantial completion, lasting 1year1\,\text{year}.

27
New cards

Front-loading

Assigning disproportionately high values to early work items in the schedule of values to receive larger early payments.

28
New cards

Field observation report (FOR)

A report issued by the architect to document conditions observed during site visits and note nonconforming work.

29
New cards

Punch list

A list prepared by the architect of items that must be corrected or completed before the owner occupies the building.

30
New cards

Weep holes

Openings in masonry walls that allow water to drain from the wall cavity to the exterior.

31
New cards

Moment connection

A steel structural connection providing resistance to both shear and bending, serving as part of a lateral bracing system.

32
New cards

Temporary certificate of occupancy (TCO)

A certificate issued when a building is partially complete but safe enough for a specific area to be occupied.

33
New cards

Slump test

A test for concrete where a result exceeding the maximum specified value indicates excess water content, potentially reducing compressive strength.

34
New cards

Drip edge

A masonry wall detail oriented to allow water to drip away from the wall face.

35
New cards

Record drawings

Also known as as-built drawings, these document the actual final condition of the building as constructed, incorporating all approved changes.

36
New cards

Post-occupancy evaluation (POE)

A structured assessment of a building's performance after it has been occupied for a period of time.

37
New cards

Republic Act 9266

The Architecture Act of 2004 in the Philippines.

38
New cards

CPD Requirements

Per RA 10912, architects require 4545 credit units per 3-year3\text{-year} compliance period for license renewal.

39
New cards

Standard of Care

The requirement that an architect perform services consistent with the level of skill and care of other architects in similar circumstances in the same locality.

40
New cards

Presidential Decree 1096

The National Building Code of the Philippines, requiring construction to commence within 1year1\,\text{year} after a building permit is issued.

41
New cards

Board of Architecture Composition

Under RA 9266, the board is composed of 33 members including the chairman.