BMT 13: Critical Path Analysis (HL ONLY)

0.0(0)
Studied by 0 people
call kaiCall Kai
learnLearn
examPractice Test
spaced repetitionSpaced Repetition
heart puzzleMatch
flashcardsFlashcards
GameKnowt Play
Card Sorting

1/8

encourage image

There's no tags or description

Looks like no tags are added yet.

Last updated 4:57 PM on 5/15/26
Name
Mastery
Learn
Test
Matching
Spaced
Call with Kai

No analytics yet

Send a link to your students to track their progress

9 Terms

1
New cards

definition

a management planning tool which serves to improve the efficiency of the production

processes in a project by systematically scheduling all tasks and resources required to complete a project in the minimum amount of time.

2
New cards

free float definition

The free float refers to the amount of time that an activity can be delayed without affecting the EST of the next activity in the project.

3
New cards

free float formula

Free float= ESTof next node - Duration - ESTof current node

4
New cards

total float definition

amount of spare time available to an activity without causing a delay to the overall (total) project.

5
New cards

total float formula

Total Float= LFT - Duration - EST

6
New cards

Dummy activities

logical dependency between two indirectly linked tasks. It is used to prevent an illogical path and is shown by a dotted arrow line in a network diagram

7
New cards

advantages

visual representation of a complex project which can therefore make it easier for people to interpret, such as the management of different resources at different stages of the project.

promotes operational efficiency by identifying the critical path, reduce any lost time between different activities, thereby ensuring the project runs smoothly.

budgeting and better cash flow management

production planning and stock control. Raw materials and components only need to be ordered in time for the EST reduce storage costs.

8
New cards

limitations

Internal and external factors can cause disruptions and delays to the completion of a project.

only useful if the data used to construct the network analysis is accurate and reliable.

determine the quickest time to complete a given project. However, this does not guarantee that the project is the best one to pursue.

if any necessary steps are not identified in the network analysis then the CPA will be

inaccurate.

complex for huge scale project

9
New cards

Project management

planning and coordination of different jobs and tasks for a particular project.