New cards

affadavit

a sworn statement

2
New cards

metes and bounds

a system or method of land surveying that defines the boundaries of the real property

3
New cards

for lien notices the requirements of compliance of deadlines is typically

strict

4
New cards

the deadlines for a lien notice differ based on what?

the claimant’s role (gc or sub), and what industry the project is in (res. or com.)

5
New cards

to reach substantial compliance on a lien notice, what is sufficient?

the property description (an address)

6
New cards

lien release

an official legal document issued by a contractor or creditor confirming that a debt or financial claim on an asset has been paid off in full and the legal claim is removed

7
New cards

miller’s act

a federal law that requires contractors to post surety bonds on federal public building and construction projects over $150,000

8
New cards

what is the purpose of the miller act?

federal property is exempt from traditional mechanics lien

9
New cards

wrongful lien

a legal claim placed on real property that was filed improperly without legal basis, such as missed deadlines or malicious intent

10
New cards

surety bonds

a three-party legally binding agreement that guarantees a contractor will fulfill their contractual obligations

11
New cards

who is involved in a surety bond?

  1. a surety (insurance company)

  2. a contractor

  3. an owner


12
New cards

what happens in a surety bond, if the contractor fails to perform?

the surety company covers the financial loss or completes the work

13
New cards

for the surety company to cover financial comp., it is limited to what?

the og bond amount

14
New cards

who pays the bond premium (a % of total bond coverage)

the contractor

15
New cards

principal (prime)

the party that is required to obtain the bond and fulfill the obligations, typically the prime contractor

16
New cards

obligee (owner)

the party that is protected by the bond

17
New cards

surety (bond comp)

the bonding company that guarantees the principal's obligations

18
New cards

what are the main 2 types of surety bonds?

  1. performance bond

  2. payment bond


19
New cards

performance bond

guarantees the contractor will complete the project as agreed

20
New cards

payment bond

if the contractor doesn't pay subcontractors, this ensures that the parties are paid

21
New cards

who has lien rights

Anyone who provides services or goods to improve real property, like GCs, subs, suppliers, and architects.

22
New cards

how long do you have to sue to foreclose?

1 year

23
New cards

what are the 3 types of changes in work?

  • Change Order

  • Construction Change Directive

  • Minor Changes


24
New cards

change order

a written document that modifies a construction contract after it has been signed by both parties

25
New cards

what is the first step to analyzing a change claim?

To establish the contractually agreed scope of work

26
New cards

Construction Change Directive (CCD)

a written order from the Owner that instructs the contractor to perform work immediately, when there isn't total agreement on the cost or time yet

27
New cards

minor change

a small adjustment to the work that remains consistent with design intent, and doesn't alter the contract time or price

28
New cards

cardinal change

a drastic, unauthorized change to a project's scope that is so profound it fundamentally changes the nature of the scope

29
New cards

flow down cause

a contractual mechanism in a construction subcontract that binds a subcontractor to the terms, obligations, and responsibilities of the prime contract between the general contractor and the project owner

30
New cards

what is the purporse of a flow down clause

  • incorporate prime contract documents into subcontract

  • for consistency


31
New cards

a flow down clause is also known as what

conduit clause or pass through clause

32
New cards

indemnification

clause that shifts financial and legal risk from one party (the indemnitee) to another party (the indemnitor) in the event of a loss, claim, or lawsuit

33
New cards

what are the 3 types of indemnification

  1. limited

  2. intermediate

  3. broad form


34
New cards

limited indemnification

a contractual promise where one party agrees to pay for losses, damages, or legal costs of another party only to the extent that the losses were caused by their own negligence or fault

35
New cards

intermediate indemnification

a contract clause where one party (the indemnitor) agrees to cover 100% of the losses for the other party (the indemnitee), unless the indemnitee is 100% at fault.

36
New cards

broad form indemnification

a contractual clause where one party (the indemnitor) agrees to pay for losses, damages, or legal costs suffered by the other party (the indemnitee), even if the indemnitee is 100% at fault for the incident

37
New cards

give the simple def of the 3 types of indemnification

  1. limited: own fault

  2. intermediate: cover all, even if partially at fault

  3. broad form: cover all, even if no fault


38
New cards

anti-indemnity act

renders broad and intermediate indemnification unenforceable

39
New cards

the anti-indemnity act is limited to what?

the indemnitors negligence

40
New cards

indemnitee

The one being shielded from financial harm

41
New cards

indemnitor

The person or company that promises to pay for those losses or defend the indemnitee

42
New cards

texas doesn’t allow which forms of indemnity?

broad & intermediate

43
New cards

standard of care

commensurate with that provided by other professionals providing the same services in the same community

44
New cards

who is typically responsible for the design of the project?

arch or engineer (design professional)

45
New cards

what can design professionals get in order to protect themselves?

professional liability insurance

46
New cards

actual authority

expressly conferred by the contract

47
New cards

implied authority

can act in reasonable and necessary manner to exercise their actual authority

48
New cards

apparent authority

owner acts in a way that leads a gc or 3rd party to reasonably believe that the a/e has authority

49
New cards

spearin doctrine

owner provides implied warranty of accuracy of plans/specs when given to contractor

50
New cards

how does a contractor assume liability?

contract terms, indemnification clause, specifications, shop drawings/submittals

51
New cards

waiver of consequential damages

giving up the right to claim consequential damages

52
New cards

in the AIA, if the contractor discovers errors or omissions in the plans who should he inform?

a/e (design professional)

53
New cards

in the CD, if the contractor discovers errors or omissions in the plans who should he inform?

the owner

54
New cards
55
New cards
56
New cards
57
New cards
58