Civil Engineering Project Management: Detailed Scope and Project Execution Planning

0.0(0)
Studied by 0 people
call kaiCall Kai
learnLearn
examPractice Test
spaced repetitionSpaced Repetition
heart puzzleMatch
flashcardsFlashcards
GameKnowt Play
Card Sorting

1/24

flashcard set

Earn XP

Description and Tags

Vocabulary practice flashcards covering detailed scope development, Project Execution Plan components, PDRI scoring, design procurement, contract fee structures, and project management roles.

25 Terms

1
New cards

Project Execution Plan (PEP)

A comprehensive planning document that answers 'What are we building and what work needs to be done to build it?' by integrating scope, schedule, budget, risk management, and monitor and control procedures for project authorization.

2
New cards

Tempering Role

The project manager's responsibility during detailed scope to verify that scope and requirements are thoroughly defined before design begins, moderating an eager owner who wants to rush into execution.

3
New cards

PM's Initial Review

The first step upon bringing on an owner's project manager, consisting of a critical evaluation of existing scope, budget, and schedule plans for reasonableness, preparation methodology, authorship, and required technical expertise.

4
New cards

Owner's Orientation

A forward-looking alignment process between the project manager and the owner to establish project priorities (typically prioritizing cost over time), clarify management parameters, and determine the owner's desired involvement.

5
New cards

Project Definition Rating Index (PDRI)

A structured scope checklist and scoring tool used to assess scope completeness; lower scores indicate better scope definition, with a threshold of less than 200200 typically required for funds authorization.

6
New cards

Funds Authorization (Sanction Gate)

The formal approval gate at the conclusion of the detailed scope phase where project funding is released to initiate detailed design and construction.

7
New cards

Work Breakdown Structure (WBS)

A hierarchical decomposition of the total project scope into distinct task groups, activities, and work packages, establishing the framework to link tasks to schedule, costs, and responsible parties.

8
New cards

Cost Estimate

A prediction or calculation of expected costs, time, and resources based on historical data and project assumptions, used for planning, decision-making, and comparing design alternatives.

9
New cards

Project Budget

A financial allocation plan that distributes estimated costs across project components and establishes the maximum authorized spending limit and control framework.

10
New cards

Contingency Reserve

A financial reserve (typically 5%5\% to 15%15\% of construction cost) established through risk assessment to absorb unforeseen specific events and uncertainties in scope or estimating.

11
New cards

Milestone Schedule

A high-level schedule within the Project Execution Plan that outlines major project events, sequencing, task durations, and critical completion dates derived from the Work Breakdown Structure.

12
New cards

Brooks Act

Federal legislation mandating that architectural and engineering firms be selected based upon demonstrated competence, qualifications, and experience rather than cost or competitive bidding.

13
New cards

Request for Proposal (RFP)

A formal procurement solicitation issued to potential design firms detailing project information (basis for design), required proposal deliverables, evaluation criteria, and the scope of services to be hired.

14
New cards

Hourly Rate Fee Structure

A payment method where the firm bills for actual hours worked at agreed-upon hourly rates plus reimbursable expenses, commonly used for early studies, feasibility work, and small tasks.

15
New cards

Lump Sum Fee Structure

A fixed-price payment agreement where a firm completes a well-defined, unchanging scope of work for a set total price paid according to milestones or percentage of completion.

16
New cards

Percentage of Construction Cost Fee Structure

A compensation model where the design fee is calculated as a direct percentage of the project's final construction cost.

17
New cards

Cost Plus Fixed Fee Structure

A contract payment structure where the owner reimburses direct labor and expenses while providing a pre-agreed fixed fee (profit) to the firm, used when the project scope is uncertain or evolving.

18
New cards

Cost Plus Percentage Fee Structure

A reimbursement structure where a firm receives payment for all incurred costs plus an additional percentage fee of those costs, which is rarely used because it incentivizes higher project expenditures.

19
New cards

In-House Design Procurement

A design procurement strategy where the owner executes the design entirely using internal resources and staff directly employed by the owner.

20
New cards

Phased Design Procurement

A procurement strategy where design begins in-house (such as by a Department of Transportation) before handing off the project to an external engineering firm for completion.

21
New cards

Outsource Design Procurement

A procurement option where an outside consulting or design firm is hired to both initiate and complete the entire scope of design.

22
New cards

Authority Having Jurisdiction (AHJ) Requirement

A mandatory legal or code constraint imposed by governing regulatory authorities, such as a requirement that a building design meet municipal fire codes.

23
New cards

Scope Freezing

The practice of establishing a formal cutoff date after which no major design changes will be accepted unless they are deemed mission-critical.

24
New cards

Weak Matrix Structure

An organizational setup where functional discipline leaders retain primary decision-making authority over the project manager, often prioritizing technical optimization over budget and schedule constraints.

25
New cards

Building Use Requirement (PDRI Category A1)

The highest-weighted individual scope element in the building PDRI (44 points44\text{ points}) that defines the intended operational function of the facility (e.g., research, retail, food service, recreation).