Project ID - Definition
A schedule should have a unique identification number.
2
New cards
Project ID - How to Calculate
Find Project ID; check if Project ID is unique.
3
New cards
Project Name - Definition
A schedule should have a unique, short phrase or label.
4
New cards
Project Name - How to Calculate
Find Project Name; check if Project Name is unique.
5
New cards
Activity Name (Unique) - Definition
Every activity should have a unique name.
6
New cards
Activity Name (Unique) - How to Calculate
Percentage of activities with unique Activity Names.
7
New cards
Milestones with Resources - Definition
Milestones must have no resources.
8
New cards
Milestones with Resources - How to Calculate
Percentage of milestones with resources assigned.
9
New cards
Milestones with Duration - Definition
Milestones must have no duration.
10
New cards
Milestones with Duration - How to Calculate
Percentage of milestones with durations assigned.
11
New cards
Lags - Definition
A lag shall not be used or used rarely.
12
New cards
Lags - How to Calculate
Percentage of lag in predecessor logic relationships.
13
New cards
Leads - Definition
A lead shall not be used or used rarely.
14
New cards
Leads - How to Calculate
Percentage of lead in predecessor logic relationships.