Process analysis
A rigorous framework for understanding the detailed operations of the business. Among other things the process analysis determines how many flow units can be processed per unit of time (the process capacity) and how busy the resources of the process are (utilization).
Process flow diagram
A graphical way to describe the process. It uses boxes to depict resources, arrows to depict flows, and triangles to depict inventory location.
Resource
The group of people and/or equipment that transforms inputs into outputs.
Flow unit
The unit of analysis that we consider in a process analysis; for example, patients in a hospital, scooters and a kick scooter plant, and calls in a call center.
Upstream
The parts of the process that are at the beginning of the process flow
Downstream
Parts of the process that are at the end of the process flow
Processing time
The time it takes a resource to complete one flow unit
Capacity
The maximum number of flowing in second flow through that resource per unit of time
Capacity equation
Resources/processing time
Process capacity
The maximum flow rate the process can provide per unit of time. This determines the maximum supply of the process. The process capacity is the smallest capacity of all resources in the process.
Demand rate
The number of flow unions the customers want per unit of time
Capacity constrained
The case in which demand exceeds supply and the flow rate is equal to process capacity
Demand constrained
The case in which process capacity exceeds demand and thus the flow rate is equal to the demand rate
Throughput
A synonym for flow rate, the number of flow units flowing through the process per unit of time
Utilization
The ratio between the flow rate (how fast the process is currently operating) and the process capacity (capturing how fast the process could be operating if there was sufficient demand). Note that utilization can be defined at the level of an individual resource or at the level of the entire process.
Cycle time
The time between completing two consecutive flow units
Utilization equation
Flow rate/capacity
Cycle time equation
1/flow rate
Lead time
The time between when an order is placed and when it is filled. Process lead time is frequently used as an alternative term for flow time
Bottleneck
Resource with lowest capacity in a process
Worker paced
A process line in which each resource is free to work at its own pace: if the first resource finishes before the next one is ready to accept the flow unit, then the first resource puts the completed flow unit in inventory between the two resources.
Machine pace
A process in which all steps are connected through a conveyor belt and all of the steps must work at the same rate even if some of them have more capacity than others.
Time through the empty system
The time it takes the first flow unit to flow through an empty process; that is, a process that has no inventory
Time through the empty system equation
Number of stations X cycle time
Time required to produce a given quantity X starting with an empty system
The time it takes to process with no inventory to produce a given quantity