Project Management: Estimating, Scheduling, and Engineering Economics

0.0(0)
Studied by 0 people
call kaiCall Kai
learnLearn
examPractice Test
spaced repetitionSpaced Repetition
heart puzzleMatch
flashcardsFlashcards
GameKnowt Play
Card Sorting

1/24

flashcard set

Earn XP

Description and Tags

Comprehensive practice flashcards covering NCEES CBT Civil Engineering Project Management: Quantity and Cost Estimating, Project Scheduling (CPM, PDM, AOA, PERT, EVM), and Engineering Economics.

25 Terms

1
New cards

What is the most critical characteristic used to determine the cost estimate class in the Cost Estimate Classification Matrix?

The degree of project definition (expressed as a percentage of complete definition deliverables).

2
New cards

In the Cost Estimate Classification Matrix for Building and General Construction Industries, what are the primary characteristics and expected accuracy ranges for a Class 3 estimate?

A Class 3 estimate corresponds to a project maturity level of 10%10\% to 40%40\% (used for design development, budget authorization, and feasibility). Its expected accuracy range at an 80%80\% confidence interval is Low: −5%-5\% to −15%-15\% and High: +10%+10\% to +20%+20\%.

3
New cards

What is the key conceptual difference between analogous (top-down) estimating and cost-based (bottom-up) estimating?

Analogous (conceptual/top-down) estimating uses historical data to define the overall cost of a typical facility (such as cost per lane mile or cost per building). Cost-based (bottom-up) estimating does not rely on historical bid data; instead, it tallies the contractor's specific direct costs for labor, equipment, materials, and specialty subcontractors needed to complete each work item.

4
New cards

What is the formula for updating the historical purchase cost of equipment or materials in year MM to the current cost using construction cost indices (CCIs)?

Current Cost=Cost in year M×Current IndexIndex in year M\text{Current Cost} = \text{Cost in year } M \times \frac{\text{Current Index}}{\text{Index in year } M}

5
New cards

How are direct (variable) costs differentiated from indirect (fixed) costs on a construction project?

Direct costs are directly associated with project work activities (e.g., materials, labor wages, equipment rental/ownership). Indirect costs are overhead expenses not directly tied to a specific activity (e.g., home office space, administrative staff, taxes, bond premiums) that remain relatively steady per unit of time.

6
New cards

How is the volume of lumber in board-feet (bd-ft\text{bd-ft}) calculated?

1 bd-ft=1 ft×1 ft×1 in thick=144 in31\,\text{bd-ft} = 1\,\text{ft} \times 1\,\text{ft} \times 1\,\text{in thick} = 144\,\text{in}^3; calculated as: Lumber (bd-ft)=Length (in)×Nominal cross section (in2)144 in3/bd-ft\text{Lumber (bd-ft)} = \frac{\text{Length (in)} \times \text{Nominal cross section (in}^2)}{144\,\text{in}^3/\text{bd-ft}}

7
New cards

What does Square Foot of Contact Area (SFCA) measure in concrete formwork estimating?

The total surface area of the formwork that comes into direct contact with the wet concrete (e.g., sides only for slabs-on-grade; sides, underneath, and around columns for elevated slabs).

8
New cards

What is the formula used to estimate the required number of reinforcing steel bars across a structural dimension?

Number of rebars=Dimension of structureRebar Spacing+1\text{Number of rebars} = \frac{\text{Dimension of structure}}{\text{Rebar Spacing}} + 1

9
New cards

What are the formulas for PERT expected activity duration (tet_e), standard deviation (σ\sigma), and variance?

te=Optimistic+4×Most Likely+Pessimistic6t_e = \frac{\text{Optimistic} + 4\times\text{Most Likely} + \text{Pessimistic}}{6}, σ=Pessimistic−Optimistic6\sigma = \frac{\text{Pessimistic} - \text{Optimistic}}{6}, and Variance=(Pessimistic−Optimistic6)2\text{Variance} = \left(\frac{\text{Pessimistic} - \text{Optimistic}}{6}\right)^2

10
New cards

What primary functions differentiate a Gantt (bar) chart from a network diagram?

A Gantt chart primarily displays project progress, whereas a network diagram primarily displays activity sequence and dependencies.

11
New cards

What are the four types of logical precedence relationships used in the Precedence Diagram Method (PDM / AON)?

  1. Finish-to-Start (FS): Initiation of the successor depends on completion of the predecessor.\n2. Finish-to-Finish (FF): Completion of the successor depends on completion of the predecessor.\n3. Start-to-Start (SS): Initiation of the successor depends on initiation of the predecessor.\n4. Start-to-Finish (SF): Completion of the successor depends on initiation of the predecessor.
12
New cards

What are the three types of activity dependencies in project scheduling?

  1. Mandatory dependencies: Inherent to the nature of the physical work (e.g., building foundation before superstructure).\n2. Discretionary dependencies: Defined by the project management team based on best practices.\n3. External dependencies: Inputs or constraints outside the project team's control (e.g., environmental work windows, permits).
13
New cards

How are Total Float (TF) and Free Float (FF) defined and calculated in CPM scheduling?

Total Float is the maximum time an activity can be delayed without delaying the overall project completion date (TF=LS−ES=LF−EF\text{TF} = \text{LS} - \text{ES} = \text{LF} - \text{EF}). Free Float is the time an activity can be delayed without delaying the early start of any immediate successor (FFi=min⁡(ESi+1)−EFi\text{FF}_i = \min(\text{ES}_{i+1}) - \text{EF}_i).

14
New cards

What is the difference between project schedule crashing and fast tracking?

Crashing is a schedule compression technique that evaluates cost and schedule trade-offs to obtain the greatest compression for the least incremental cost (e.g., adding crews or paying overtime). Fast tracking compresses the schedule by performing activities in parallel that are normally executed in sequence.

15
New cards

In Earned Value Analysis, what do BCWS, BCWP, and ACWP represent?

BCWS (Budgeted Cost of Work Scheduled / PV) measures what was planned; BCWP (Budgeted Cost of Work Performed / EV) measures what was done; ACWP (Actual Cost of Work Performed / AC) measures what was paid.

16
New cards

How are Cost Variance (CV), Schedule Variance (SV), CPI, and SPI calculated in earned value management?

CV=EV−AC\text{CV} = \text{EV} - \text{AC} (positive indicates cost savings)\nSV=EV−PV\text{SV} = \text{EV} - \text{PV} (positive indicates schedule advantage)\nCPI=EVAC\text{CPI} = \frac{\text{EV}}{\text{AC}} (>1.0> 1.0 indicates cost efficiency)\nSPI=EVPV\text{SPI} = \frac{\text{EV}}{\text{PV}} (>1.0> 1.0 indicates schedule efficiency)

17
New cards
<p>Based on this earned value analysis diagram, which vertical differences define Cost Variance and Schedule Variance at time T-now?</p>

Based on this earned value analysis diagram, which vertical differences define Cost Variance and Schedule Variance at time T-now?

Cost Variance is the vertical difference between Budgeted Cost of Work Performed (BCWP) and Actual Cost of Work Performed (ACWP). Schedule Variance is the vertical difference between Budgeted Cost of Work Performed (BCWP) and Budgeted Cost of Work Scheduled (BCWS).

18
New cards

What are the formulas for Estimate to Complete (ETC) and Estimate at Completion (EAC) when work is expected to proceed at the current Cost Performance Index (CPI)?

ETC=BAC−EVCPI\text{ETC} = \frac{\text{BAC} - \text{EV}}{\text{CPI}} and EAC=AC+ETC=BACCPI\text{EAC} = \text{AC} + \text{ETC} = \frac{\text{BAC}}{\text{CPI}}, where BAC is the Budget at Completion.

19
New cards

What is the formula to convert a nominal annual interest rate (rr) with mm compounding periods per year into an effective annual interest rate (iei_e)?

ie=(1+rm)m−1i_e = \left(1 + \frac{r}{m}\right)^m - 1

20
New cards

How does compounding frequency influence the effective annual interest rate (iei_e)?

More frequent compounding periods (e.g., monthly or daily compared to annually) result in a higher effective annual interest rate for the same nominal annual rate.

21
New cards

What is the formula for calculating the inflation-adjusted interest rate (dd)?

d=i+f+(i×f)d = i + f + (i \times f), where ii is the real interest rate per period and ff is the general inflation rate per period.

22
New cards

What are the formulas for annual depreciation (DD) and Book Value in year jj (BVj\text{BV}_j) using the Straight-Line Depreciation (SLD) method?

D=P−SnnD = \frac{P - S_n}{n} and BVj=P−j(P−Snn)\text{BV}_j = P - j\left(\frac{P - S_n}{n}\right), where PP is the initial purchase price, SnS_n is expected salvage value in year nn, and nn is the depreciable asset life.

23
New cards

What is Capitalized Cost, and how is it calculated for an annual perpetual expense (AA) at effective rate (ii)?

Capitalized cost is the present worth of an asset or project assuming a perpetual lifespan (n→∞n \rightarrow \infty), calculated as: P=AiP = \frac{A}{i}.

24
New cards

When comparing mutually exclusive engineering alternatives, when should Present Worth (PW) Analysis be used versus Equivalent Uniform Annual Cost (EUAC) Analysis?

Present Worth (PW) Analysis is used when alternatives have the exact same lifespan. Equivalent Uniform Annual Cost (EUAC) Analysis is used when alternatives have unequal lifespans, assuming each alternative is replaced by an identical twin at the end of its useful life.

25
New cards

How should the Benefit/Cost (B/C) ratio be calculated when comparing alternatives with unequal study lifespans?

Benefits and costs must be converted into Equivalent Uniform Annual Benefits (EUAB) and Equivalent Uniform Annual Costs (EUAC) before taking the ratio: B/C=EUABEUAC\text{B/C} = \frac{\text{EUAB}}{\text{EUAC}}. A ratio ≥1.0\ge 1.0 justifies the project.